HomeMy Public PortalAbout12304O R D I N A N C E NO. 12304 AN ORDINANCE, appropriating Two Hundred Five Thousand Dollars
($205,000.00) from the Operation, Maintenance and Construction Improvement
Fund of Sugar Creek to be used for project costs for the construction of storm sewers
in W. Adams Storm Sewer Replacement (CIP 2007) (2005145), in the City of
Kirkwood, Missouri; and authorizing the Executive Director and Secretary-
Treasurer on behalf of The Metropolitan St. Louis Sewer District to enter into a
contract with XL Contracting, Inc. for the construction of the aforesaid storm
sewers.
WHEREAS, the bid for the construction of said storm sewers is One
Hundred Eighty-seven Thousand Three Hundred Twenty-four Dollars
($187,324.00), and the allowance for construction change orders is Seventeen
Thousand Six Hundred Dollars ($17,676.00), and
WHEREAS, the Director of Finance has certified that there is an
unencumbered balance in the above-named fund sufficient to pay the obligation
authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF
TRUSTEES OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Two Hundred Five Thousand Dollars
($205,000.00) is hereby appropriated from the Operation, Maintenance and
Construction Improvement Fund of Sugar Creek to be used for project costs for the
construction of storm sewers in W. Adams Storm Sewer Replacement (CIP 2007)
(2005145), in the City of Kirkwood, Missouri.
Section Two. The Executive Director and Secretary-Treasurer are
hereby authorized on behalf of The Metropolitan St. Louis Sewer District to enter
into a contract with XL Contracting as the lowest responsible bidder for the
construction of storm sewers in W. Adams Storm Sewer Replacement (CIP 2007)
(2005145), in the City of Kirkwood, Missouri, pursuant to bids received and opened
on the 9th day of August, 2006.
Section Three. This ordinance, being an appropriation ordinance, shall
take effect immediately upon its enactment.
The foregoing Ordinance was adopted October 12, 2006.