HomeMy Public PortalAbout12322O R D I N A N C E NO. 12322
AN ORDINANCE, making a supplemental appropriation of Seventy Thousand
Dollars ($70,000.00) from the Sanitary Replacement Fund for additional engineering services for
the final design of Fenton Wastewater Treatment Plant Improvements (2001068); and
authorizing the Executive Director and Secretary-Treasurer on behalf of The Metropolitan St.
Louis Sewer District to enter into Amendment No. 8 of Contract E-1014 with HDR Engineering,
Inc., for the aforesaid additional engineering services.
WHEREAS, Ordinance No. 11135, adopted December 13, 2001, appropriated the
initial funding for and authorized Contract E-1014, and
WHEREAS, the Director of Finance has certified that there is an unencumbered
balance in the above-named fund sufficient to pay the obligation authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF
THE METROPOLITAN ST. LOUIS SEWER DISTRICT
Section One. The sum of Seventy Thousand Dollars ($70,000.00) is hereby
appropriated from the Sanitary Replacement Fund for additional engineering services for the
final design of Fenton Wastewater Treatment Plant Improvements (2001068).
Section Two. The Executive Director and Secretary-Treasurer are hereby
authorized on behalf of The Metropolitan St. Louis Sewer District to enter into Amendment No.
8 of Contract E-1014 with HDR Engineering, Inc. for additional engineering services for the
final design of Fenton Wastewater Treatment Plant Improvements (2001068); said contract
amendment to be comprised of such terms and conditions as are approved by the office of the
General Counsel of the District.
Section Three. This ordinance, being an appropriation ordinance, shall take effect
immediately upon its enactment.
The foregoing Ordinance was adopted October 12, 2006.