HomeMy Public PortalAbout14187O RDINANCE NO. 14187
AN ORDINANCE, making a supplemental appropriation of Three Million Five
Hundred Thousand Dollars ($3,500,000.00) from the Sanitary Replacement Fund to be used for
engineering services for pre-design of Lower Meramec River System Improvements -
Baumgartner to Fenton WWTF Tunnel (11746) in the Cities of Fenton and Sunset Hills, and
Unincorporated St. Louis County, Missouri; and authorizing the Executive Director and
Secretary-Treasurer on behalf of The Metropolitan St. Louis Sewer District to amend Contract
No. 20202 with HDR Engineering Inc. for the aforesaid engineering services.
WHEREAS, Ordinance No.13969 adopted October 9, 2014, appropriated the
initial funding for and authorized Contract No. 20202, and
WHEREAS, the Director of Finance has certified that there is an unencumbered
balance in the above-named fund sufficient to pay the obligation authorized herein.
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF
THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Three Million Five Hundred Thousand Dollars
($3,500,000.00) is hereby appropriated from the Sanitary Replacement Fund for engineering
services for pre-design of Lower Meramec River System Improvements - Baumgartner to Fenton
WWTF Tunnel (11746) in the Cities of Fenton and Sunset Hills, and Unincorporated St. Louis
County, Missouri.
Section Two. The Executive Director and Secretary-Treasurer are hereby
authorized on behalf of The Metropolitan St. Louis Sewer District to amend Contract No. 20202
with HDR Engineering Inc., for engineering services for pre-design for Lower Meramec River
System Improvements - Baumgartner to Fenton WWTF Tunnel (11746) in the Cities of Fenton
and Sunset Hills, and Unincorporated St. Louis County, Missouri.
Section Three. This ordinance, being an appropriation ordinance, shall take effect
immediately upon its enactment.
The foregoing ordinance was adopted on August 13, 2015.