HomeMy Public PortalAbout14884 CCTV Inspection and Physical Inspection of Sewers (2017) (11999)ORDINANCE NO. 14884
AN ORDINANCE, making a supplemental appropriation of Two Million Three
Hundred Thousand Dollars ($2,300,000.00) from the General Fund and Two Hundred Thousand
Dollars ($200,000.00) from the Operation, Maintenance, Construction, Improvement Fund of
Clayton Central to be used for CCTV inspection and physical inspection of sewers, sonar
inspections, laser profiling, and sewer cleaning in CCTV Inspection and Physical Inspection of
Sewers (2017) (11999) throughout the Metropolitan Sewer District Service Area; and
authorizing the Executive Director and Secretary-Treasurer on behalf of The Metropolitan
St. Louis Sewer District to enter into Amendment No. 3 to Contract No. 20688 with Ace Pipe
Cleaning, Inc. for the aforesaid CCTV inspection and physical inspection of sewers, sonar
inspections, laser profiling, and sewer cleaning.
WHEREAS, Ordinance No. 14655, adopted May 11, 2017, appropriated the
initial funding for and authorized Contract No. 20688; and
WHEREAS, said contract provides for an initial term of one (1) year with two (2)
additional one-year renewal terms at the option of the District, and
WHEREAS, the District desires to exercise the option to renew said contract for
the first option year, and
WHEREAS, the Director of Finance has certified that there is an unencumbered
balance in the above-named fund sufficient to pay the obligation authorized herein.
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF TRUSTEES OF
THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Two Million Three Hundred Thousand Dollars
($2,300,000.00) is hereby appropriated from the General Fund and the sum of Two Hundred
Thousand Dollars ($200,000.00) is hereby appropriated from the Operation, Maintenance,
Construction, Improvement Fund of Clayton Central for CCTV inspection and physical
inspection of sewers, sonar inspections, laser profiling, and sewer cleaning in CCTV Inspection
and Physical Inspection of Sewers (2017) (11999) throughout the Metropolitan Sewer District
Service Area.
Section Two. The Executive Director and Secretary-Treasurer are hereby
authorized on behalf of The Metropolitan St. Louis Sewer District to enter into Amendment No.
3 to Contract No. 20688 with Ace Pipe Cleaning, Inc. for CCTV inspection and physical
inspection of sewers, sonar inspections, laser profiling, and sewer cleaning in CCTV Inspection
and Physical Inspection of Sewers (2017) (11999) throughout the Metropolitan Sewer District
Service Area; said contract being comprised of such terms and conditions as have been approved
by the Office of the General Counsel of the District.
Section Three. This ordinance, being an appropriation ordinance, shall take effect
immediately upon its enactment.
The foregoing ordinance was adopted on June 14, 2018.