EAST COLLINS 3/18,3/31 3/20 3/30
WEST COLLINS 3/18,3/31 3/23 3/19 3/30
CENTER MEDIAN N/A 3/19
96TH ST 3/18,3/31 3/24,3/25 3/28 3/30,4/1
HAULOVER BRIDGE 3/18,3/31 3/28 3/21 3/25,3/28,3/29
FOUNDERS CIRCLE 3/28 3/23 4/1 3/25,4/1
REPLACEMENT/ADDITIONAL DATE WORK PERFORMED
HAULOVER 3/17 INSTALLED CONGO ROJOS UNDER SEAGRAPE BY HAULOVER BRIDGE.
3/25 INSTALL ZOYSIA IN FOUNDERS CIRCLE.
HAULOVER 3/25 INSTALLED FIREBALL BROMELIADS UNDER SEAGRAPE BY HAULOVER BRIDGE.
HAULOVER 3/25-3/28 MOUNTED AN ASSORTMENT OF BROMELIADS IN SEAGRAPE WEST OF HAULOVER BRIDGE.
HAULOVER 3/29 INSTALLED MICRO IRRIGATION ON SEAGRAPE FOR BROMELIADS.
EAST COLLINS 3/30 BASAL DRENCH ON ZAHIDI DATES WITH T-METHYL.
WEST COLLINS 3/30 BASAL DRENCH ON ZAHIDI DATES WITH T-METHYL.
96TH ST 3/30 BASAL DRENCH ON ZAHIDI DATES WITH T-METHYL.
UPCOMING:
HAULOVER 4/2-4/5 INSTALL NEW PLANT MATERIAL IN PLANT BEDS UNDER THE HAULOVER BRIDGE.