HomeMy Public PortalAboutResolution 22-36 Agreement Addendum ITD Key #13471 DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
City of McCall
RESOLUTION NO. 22-36
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF McCALL, VALLEY
COUNTY, STATE OF IDAHO, PROVIDING FOR FINDINGS AND PURPOSES;
AUTHORIZING THE MAYOR TO ENTER INTO, ON BEHALF OF SAID
MUNICIPALITY, AN ADDENDUM TO THE FINAL DESIGN COOPERATIVE
AGREEMENT KEY #13471 BETWEEN THE CITY OF McCALL AND THE IDAHO
TRANSPORTATION DEPARTMENT,AND PROVIDING AN EFFECTIVE DATE.
WHEREAS, the Idaho Transportation Department, hereafter called the STATE, has
submitted an Addendum to the Agreement stating obligations of the STATE and the CITY OF
McCALL, hereafter called the CITY, for participating in work to identify and quantify the cost of
improving SH55 and Dienhard Ln; and
WHEREAS the STATE is responsible for obtaining compliance with laws, standards and
procedural policies in the development, construction and maintenance of improvements made to
the Federal-aid Highway System when there is federal participation in the costs; and
WHEREAS certain functions to be performed by the STATE involve the expenditure of
funds as set forth in the Agreement; and
WHEREAS The STATE can only pay for work associated with the State Highway system;
and
WHEREAS the CITY is fully responsible for its share of project costs; and
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL:
Section 1: That the Addendum for providing additional design services for the project is
hereby approved.
Section 2: That the Mayor and the City Clerk are hereby authorized to execute the
Agreement on behalf of the CITY.
Section 3: That duly certified copies of the Resolution shall be furnished to the Idaho
Transportation Department.
Section 4: That this resolution shall be in full force and effect upon its passage and
approval.
Resolution 22-36 ITD Addendum
October 20,2022 Page 1 of 2
DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
Passed and approved this 20 day of October 2022.
CITY OF MCCALL
Valley County, Idaho
obert S. Giles, Mayor
CERTIFICATION
I hereby certify that the above is a true copy of a Resolution passed at a regular, meeting of the
City Council, City of McCall, held on October 20, 2022
>•' of Mc° ,
(Seal) cs.qo..�..®so�q
% (.424/3
gifiC/
a 4QL a 1 BessieJo W gner, City lerk`�
'44,3 IDA1 S
Resolution 22-36 ITD Addendum
October 20,2022 Page 2 of 2
DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
ADDENDUM TO
COOPERATIVE AGREEMENT
SH-55 AND DEINHARD LANE INTERSECTION IMPROVEMENTS
CITY OF MCCALL
PROJECT NO. A013(471)
KEY NO. 13471
PARTIES `�//
THIS ADDENDUM is made and entered into this v70 day of Oe �"o Imo'
N.D.,by and between the Idaho Transportation Department,hereafter called the State, and the
City of McCall, hereafter called the City.
PURPOSE
This Addendum will modify the Cooperative Agreement (Agreement No. 7231) entered
into on the 11th day of April, 2022, (hereinafter"Agreement") between the same parties.
The parties agree to the following revisions:
A. Section I of the Agreement will be amended by revising Paragraph 1 and adding a new
paragraph 3 as follows:
1) Upon execution of this agreement,pay to the City the amount of$76,601.80 as the
State's estimated portion.
3) Upon execution of this Addendum, pay to the City the amount of$4,531.70 as the State's
estimated portion of additional design services as noted in the attached Exhibit C.
B. Section II of the Agreement will be amended by revising Paragraph 2 to read as follows:
2) Be responsible for all costs over and above the $81,133.50 paid by the State as noted
above, unless otherwise determined and authorized by the State in writing.
C. All other terms and conditions previously agreed to and set forth in the Agreement shall
remain in full force and effect.
Addendum to Cooperative Agreement
SH-55&Dienhard Lane Int.Impr.
Key No. 13471
Page 1
DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
EXECUTION
This Agreement is executed for the State by its District Engineer, and executed for the City by
the Mayor, attested to by the City Clerk,with the corporate seal of the City of McCall.
IDAHO TRANSPORTATION DEPARTMENT
p--DocuSigned by:
-F313956FE E284A6...
Caleb Lakey,District Engineer
ATTEST: CITY OF MCCALL
BessieJo ague t �ec°A°°°, Robert S. Giles,Mayor
0 oO�pA®mec.0
IS • c000'r 'e
(Seal) a* SE4
oQ �® O �
s * s'
By regular '�1,„ z, I D
meeting On 10/20/22
hm:13471 Int SH55_Deinhard Impr Coop2 Addendum
Addendum to Cooperative Agreement
SH-55&Dienhard Lane Int.Impr.
Key No. 13471
Page 2
DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
City of McCall
TASK ORDER 21-16A—Addendum 1
Deinhard Lane, SH-55 to Samson Trail — BIDDING
This TASK ORDER, Number 21-16A—Addendum 1, under the current AGREEMENT(the
AGREEMENT) between the City of McCall, Idaho (OWNER) and HORROCKS Engineers
(Engineer), Engineer shall perform the following Services required to prepare a bid set for the
improvements to Deinhard Lane from SH-55 to Samson Trail.
Engineering services under this task order will be provided by Horrocks Engineers according to
the attached Scope of Work dated 09/20/2022.
In return for the performance of the foregoing obligations, OWNER shall pay to Engineer on an
hourly basis an amount not to exceed as follows:
Total Amount Authorized $ 11,329.25
Original Contract Amount $194,544.82
Total Contract Amount with Addendum $205,874.05
The hours and amounts are shown in the Engineer's Projected Labor Hours and Cost
Worksheet attached to this TASK ORDER (ATTACHMENT"B-1") and Labor Hours and Cost
Breakdown (ATTACHMENT "B-2").
Engineer shall bill the OWNER monthly at the specific billing rates for each staff type indicated
on the attached Projected Labor Hours and Cost Worksheet for the actual number of hours
worked by employees and for the actual number of reimbursable expenses used, up to the
maximum amount identified.
Except to the extent modified herein, all terms and conditions of the AGREEMENT shall
continue in full force and effect.
ENGINEER: OWNER:
HORROCKS ENGINEERS, INC. CITY OF MGGAduobed by:
L,°' Qt& ffi, Spir, a�
Signature: Signature: —11FC5C6F527A4AE...
V Anette Spickard
Name: Heidi Carter Name:
Title: Principal Title: City Manager
October 13, 2022 1 11:26 AM MDT
Date: 09/20/22 Date:
Task Order 21-16A—Addendum 1 Page 1 of 5
DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
Deinhard Lane, SH-55 to Samson Trail Improvements HORROCKS
—ull
ENGINEERS
City of McCall
City of McCall
Deinhard Lane, SI455 to Samson Trail Improvements Final Design
TO 21-16A Addendum 1 — Re-Bidding
09/20/2022
Executive Summary
The work for this Addendum 1 -Task Order will include a summary of the additional efforts
associated with the preparation of the final plans, specifications, and estimates (PS&E) for
Deinhard Lane, SH-55 to Samson Trail for re-bidding and contract award.
1. General Provisions
It is assumed that there will be three project invoices.associated with this effort. Horrocks
Engineers (Horrocks)will prepare and submit invoices on a monthly basis. Each invoice will
include a brief project status summary.
Products and Deliverables
• Monthly invoices
2. PS&E Bid Set and Bid Support (September 2022)
Horrocks will remove the addendum call outs in the previously bid plan set and create a new bid
set for re-bidding in late September.
Horrocks will provide bid support with the following tasks:
• Attend Pre-bid Meeting
• Issue Addendums to bid package as needed
• Be available by phone for the bid opening
• Coordinate with the City during the bidding process
• Review received bids and provide recommendations
Products and Deliverables
• Bid Package
• Bid Advertisement
• Pre-bid Meeting agenda
• Letter of bid recommendation
City of McCall Responsibilities
• Distribute the Bid Advertisement
• Secure location for pre-bid meeting
• Lead pre-bid meeting
Assumptions
• One Horrocks representatives will attend the pre-bid meeting
• At least one Horrocks representative will be available by phone for the bid opening
City of McCall Horrocks Engineers
Deinhard Lane, SH-55 to Samson Trail Final Design 09/20/2022
Addendum 1 -Scope of Work Page 2 of 5
DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
Deinhard Lane, SH-55 to Samson Trail Improvements HORROCKS
-
h N Ci 1 N E r 12 S
City of McCall
3. Public Outreach and Information (January 2023)
3.1: Property Impacts Letter
Horrocks will prepare a letter to be sent to the property and business owners that will be
impacted by the Deinhard Lane construction. The purpose of this letter is to inform the
property and business owners of any anticipated impacts to their respective property or
business and the timeline of construction.
3.2. Temporary. Easement Letters
For construction and property repair purposes., it is assumed that a minimum 5'
temporary construction easement will be needed along all project adjacent properties. If
properties are impacted beyond 5' behind the proposed back of sidewalk; temporary
easements will be adjusted accordingly. Horrocks Will send out the Right-of-Entry forms
to all business/property owners for approval. This will be accomplished prior to
construction and after the property impact letters from Task 2.1 have been sent.
Products and Deliverables
• Hard copy of letter, mailed out to property.and business owners
• Exhibit of proposed improvements and impacts to each property
City Responsibilities
Provide property/business owner contact information and review draft letter prior to
being mailed
• Coordinate with property owners for approval of easement needs
• Provide typical Right-of-Entry form used
Assumptions
• Horrocks will act on the City's behalf in presenting easement needs to property owners
• Horrocks will mail out the Right-of-Entry forms
• Any permanent.easements required for the franchise utilities will be acquired by the
individual company
City of McCall Horrocks Engineers
Deinhard Lane, SH-55 to Samson Trail Final Design 09/20/2022
Addendum 1 -Scope of Work Page 3 of 5
DocuSign Envelope ID:7052E238-EOF5-4E33-BABA-FD5A768543A1
ATTACHMENT"B-1" HORROCKS
Projected Labor Hours and Costs Worksheet ENGINEERS
Task Order 21-16A
City of McCall-Deinhard Lane,SH-55 to Samson Trail Improvements
Addendum 1-Re-Bidding
A. LABOR COSTS
Man Total Raw
Hours Labor Cost
1 Principal Engineer Bryan Foote,P.E.,Horrocks 3 @ $103.36 = $ 310.08
2 Project Manager Heidi Carter,P.E. Horrocks 14 @ $82.02 = $ 1,148.28
3 Project Engineer Will Rice,P.E.Horrocks 8 @ $49.57 = $ 396.56
4 CADD, Peter Remus Horrocks 16 @ $44.66 = $ 714.56
5 Staff Engineer Emily Peters,Horrocks 28 @ $34.37 = $ 962.36
6 Accounting Julie Johnson Horrocks 3 @ $46.44 = $ 139.32
TOTAL RAW LABOR COST = $ 3,671.16
B. OVERHEAD&PROFIT
Total Raw Labor Cost OVERHEAD MULT
HORROCKS $3,671.16 X 1.8000 = $ 6,608.09
C. REIMBURSABLE EXPENSES Estimated
Expense
Estimated Quantity Unit Cost Horrocks
1 Mileage 0 @ $ 0.580 = $ -
2 Meals Travel Day Per Diem 0 @ $ 41.250 = $ -
3 0 0 @ $ - = $ -
4 0 0 @ $ - _ $
TOTAL REIMBURSABLE EXPENSES = $D. SUBCONSULTANTS
Fee
1 Construction Engineering and Inspection by Crestline Engineer $ 1,050.00
TOTAL SUBCONSULTANT FEES = $ 1,050.00
•
TOTAL(A thru D) _ $11,329.25
$6,797.55 City of McCall
$4,531.70 ITD
•
•
Task Order 21-16A Page 4 of 5
DocuSign Envelope ID:7052E238-EOF5-4E33-BABA-FD5A768543A1
ATTACHMENT"B-2" HORROCKS
LABOR HOUR AND COST BREAKDOWN p,p
City of McCall-Deinhard Lane,SH-55 to Samson Trail Improvements. ENGINEERS
TO21-16A Addendum 1
Principal Project Project CADD, Staff Engineer Accounting
Engineer Bryan Manager Heidi Engineer Will Overhead 8
Peter Remus Emily Peters, Julie Johnson Labor Cost Total Fee
Foote,P.E., Carter,P.E. Rice,P.E. Horrocks Horrocks Horrocks Total Hours Horrocks Profit Horrocks Horrocks Assumptions
Horrocks Horrocks Horrocks
Task Description Salary Rate $103.36 $82.02 $49.57 $44.66 $34.37 $46.44 180.00%
Task 1 General Provisions -
Project Invoices I 3 I 1 I I I 3 I 6 I I I I Assume 3 Invoices
Task 1 SUBTOTAL I 3 I 0 I 0 I 0 I 0 I 3 I 6 I $449 I $809 I $1,258 I
Task 2 PS&E Bid Set and Bid Support
2.1 Preparation of Bid Set 8 8 8 24
2.2 Bid Support 4 8 8 8 28 via Phone
Task 2 SUBTOTAL I 0 I 12 I 8 I 16 I 16 I 0 I 52 I $2,645 I $4,762 I $7,407 I
Task 3 Public Outreach and Information •
3.1 Property Impact Letters 1 6 7
3.2 Temporary Easement Letters 1 6 7
Task 3 SUBTOTAL 0 2 0 0 12 0 14 $576 I $1,038' $1,614
•
•
SUBTOTAL 3 14 8 16 .28 3 . - 72 $3,671 $6,608 $10,279
Principal Project Project CADD, Staff Engineer Accounting
Engineer Bryan Manager Heidi Engineer Will Labor Cost Overhead Labor and
Foote,P.E., Carter,P.E. Rice,P.E. Peter Remus Emily Peters, Julie Johnson Total Hours Horrocks Horrocks Overhead Horrocks Assumptions
Horrocks Horrocks Horrocks Horrocks Horrocks Horrocks
TOTAL LABOR HOURS 3 14 8 16 28 3 72
TOTAL LABOR COSTI $310 I $1,148 I $397 I $715 I $962 I $139 I — I $3,671 I $6,608 I $10,279 I
Note: See scope of work for assumptions. Construction Engineering and Inspection by Crestline Engineers $1,050.00 $1,050 see attached
' Mileage miles $0.58 $0
Meals Travel Day Per Diem day $41.25 $0
TOTAL $11,329
•
Task Order 21-16A Page 5 of 5
DocuSign Envelope ID:7052E238-E0F5-4E33-BABA-FD5A768543A1
Crestline Engineers,Inc. EXHIBIT B
Deinhard Lane,SH-55 to Samson Trail
Client-City of McCall/Horrocks Engineers,Inc.
Man Hour/Budget Estimate to Rebid Project 9/19/2022
Senior
Principal Project Project Associate Construction Project
Crestline Tasks Engineer Manager Engineer Engineer I Manager Inspector II CAD/Support Admin Mileage Comments
Bid Support
Pre-Bid Meeting Agenda and Meeting Attendance •
4
Potential Contractor Coordination and Outreach 2
Bid Comparison 2
Contract Administration and Coordination with City 2
Total Hours 0 0 0 0 10 0 0 0 0
Hourly Rate $143.00 $125.00 $113.00 $90.00 $105.00 $93.00 $70.00 $65.00 $0.585
Estimated Budget $0.00 $0.00 $0.00 $0.00 $1,050.00 $0.00 $0.00 $0.00 $0.00
Total Budget* $1,050.00
*Estimate is for efforts associated with the rebidding of the project in the Fall of 2022 and is in addition to the budget estimate provided on 2/7/2022