Loading...
HomeMy Public PortalAbout100_045_ gefaschedule - UV.pdfUV Disinfection Project 6) Schedule: What is the proposed project schedule? If actual dates are available, please include them in the appropriate column ACTION ACTUAL DATE(S) PROPOSED DATES(S) Complete project planning 07/01/2016 Initiated design 08/20/2016 Plans & specs submitted to EPD 10/31/2016 Bid opening 2/1/2017 Notice of award 2/15/2017 Notice to proceed with construction 3/15/2017 Initiation of construction 3/15/2017 Completion of construction 12/01/2017