HomeMy Public PortalAbout100_045_ gefaschedule - UV.pdfUV Disinfection Project
6) Schedule: What is the proposed project schedule? If actual dates are available, please include them in the appropriate column
ACTION ACTUAL DATE(S) PROPOSED DATES(S)
Complete project planning 07/01/2016
Initiated design 08/20/2016
Plans & specs submitted to EPD 10/31/2016
Bid opening 2/1/2017
Notice of award 2/15/2017
Notice to proceed with construction 3/15/2017
Initiation of construction 3/15/2017
Completion of construction 12/01/2017