HomeMy Public PortalAbout2020.036 - (03-18-20) RESOLUTION NO. 2020.036
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LYNWOOD
ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2020-21
FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT
OF 2017
WHEREAS, Senate Bill 1 (SB - 1), the Road Repair and Accountability Act of 2017
(Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the
Governor in April 2017 in order to address the significant multi-modal transportation
funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will
ensure the residents of our City are aware of the projects proposed for funding in our
community and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a list of projects proposed to receive
fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA),
created by SB 1, which must include a description and the location of each proposed
project, a proposed schedule for the project's completion, and the estimated useful life of
the improvement; and
WHEREAS, the City, will receive an estimated $1,347,444 in RMRA funding in
Fiscal Year 2020-2021 from SB 1; and
WHEREAS, this is the fourth year in which the City is receiving SB 1 funding and
will enable the City to continue essential road maintenance and rehabilitation projects,
safety improvements, repairing and replacing aging bridges, and increasing access and
mobility options for the traveling public that would not have otherwise been possible
without SB 1; and
WHEREAS, the City Council allows public comments at the start of the Council
Meeting prior to considering and approving the list of projects for the use of SB1 funds;
and
WHEREAS, the City used a Pavement Management System to develop the SB 1
project list to ensure revenues are being used on the most high-priority and cost-effective
projects that also meet the communities priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate
segments of Wright Road, Gertrude Drive, Stoneacre Avenue, Virginia Avenue, Duncan
Avenue, Edgebrook Avenue, Elmwood Avenue, Fernwood Avenue, Harris Avenue and
Lavinia Avenue this year and similar improvements projects into the future; and
WHEREAS, the 2018 California Statewide Local Streets and Roads Needs
Assessment found that the City's streets and roads are in an "at-risk" condition and this
revenue will help us increase the overall quality of our road system and over the next
decade will bring our streets and roads into a "good" condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and
roads infrastructure with a focus on basic maintenance and safety, investing in complete
streets infrastructure, and using cutting-edge technology, materials and practices, will
have significant positive benefits to the City.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF LYNWOOD DOES
HEREBY FIND, PROCLAIM, ORDER, AND RESOLVE AS FOLLOWS:
Section 1. The foregoing recitals are true and correct.
Section 2. The following list of proposed project will be funded in-part or solely
with Fiscal year 2020-21 Road Maintenance and Rehabilitation Account revenues:
Project Title: Wright Road Street Improvement
Project Code: 67.911
Project Description: Rehabilitation of street pavement. Removal and reconstruction of
PCC concrete driveway, PCC sidewalk, PCC curb ramp, and 6" PCC curb and gutter.
Includes traffic striping and markings, adjustment of manhole cover to grade, etc.
Project Location: Wright Road from Fernwood Avenue to Duncan Avenue
Estimated Project Schedule:
Start Date: July 1, 2018
Completion Date: December 30, 2021
Estimated Project Useful Life: 20 to 30 Years
Technology, Climate Change, and Complete Streets Considerations: To the extent
possible will try to use materials that lowers GHG
Section 3. The following previously proposed and adopted projects may utilize
Fiscal year 2020-21 Road Maintenance and Rehabilitation Account revenues in their
delivery. With the relisting of these projects in the adopted fiscal year resolution, the City
is reaffirming to the public and the State our intent to fund these projects with Road
Maintenance and Rehabilitation Account revenues:
2
l
Project Title: Wright Road Street Improvement
Project Code: 67.911
Project Description: Rehabilitation of street pavement. Removal and reconstruction of
PCC concrete driveway, PCC sidewalk, PCC curb ramp, and 6" PCC curb and gutter.
Includes traffic striping and markings, adjustment of manhole cover to grade, etc.
Project Location: Wright Road from Fernwood Avenue to Duncan Avenue
Estimated Project Schedule:
Start Date: July 1, 2018
Completion Date: June 30, 2021
Estimated Project Useful Life: 20 to 30 Years
Technology, Climate Change, and Complete Streets Considerations: To the extent
possible will try to use materials that lowers GHG
Project Title: Gertrude Drive from Cul-de-sac to Woodlawn Avenue, Gertrude Drive
from Agnes Avenue to Magnolia Avenue, Stoneacre Avenue from Olanda Street to
McMillan Street, and Virginia Avenue from Cortland Street to Fernwood Avenue.
Project Code: 4011.68.080 and 4011.68.083
Project Description: Rehabilitation of street pavement. Removal and reconstruction of
PCC concrete driveway, PCC sidewalk, PCC curb ramp, and PCC curb and gutter.
Includes traffic striping and markings, adjustment of manhole cover to grade, etc.
Project Location:
Gertrude Drive from Cul-de-sac to Woodlawn Avenue,
Gertrude Drive from Agnes Avenue to Magnolia Avenue,
Stoneacre Avenue from. Olanda Street to McMillan Street, and
Virginia Avenue from Cortland Street to Fernwood Avenue.
Estimated Proiect Schedule:
Start Date: July 1, 2019
Completion Date: December 30, 2021
Estimated Useful Life: 20 to 30 Years
3
Technology, Climate Change, and Complete Streets Considerations: To the extent
possible will try to use materials that lowers GHG
Project Title: Duncan Avenue, Edgebrook Avenue, Elmwood Avenue, Fernwood
Avenue, Harris Avenue and Lavinia Avenue Street Improvement
Project Code: To be determined
Project Description: Rehabilitation of street pavement. Removal and reconstruction of
PCC concrete driveway, PCC sidewalk, PCC curb ramp, and 6" PCC curb and gutter.
Includes traffic striping and markings, adjustment of manhole cover to grade, etc.
Project Location:
Duncan Avenue from Clark Street to Lavinia Avenue,
Edgebrook Avenue from Rayborn Street to Clark Street,
Elmwood Avenue from Atlantic Avenue to Duncan Avenue,
Fernwood Avenue from Vieta Avenue to Wright Road,
Harris Avenue from Walnut Avenue to Platt Avenue, and
Lavinia Avenue from Thorson Avenue to Harris Avenue.
Estimated Project Schedule:
Start Date: March 17, 2020 Completion Date: December 30, 2020
Estimated Useful Life: 20 to 30 Years
Technology, Climate Change, and Complete Streets Considerations: To the extent
possible will try to use materials that lowers GHG
Section 4. That the City Council hereby directs the City Manager to incorporate
the aforementioned projects in the FY21 Budget as appropriate and add to the Capital
Improvement Program of the FY21 Budget the project sheet attached hereto as "Exhibit
A"
Section 5. This resolution shall take effect immediately upon its adoption.
Section 6. The City Clerk shall certify as to the adoption of this_City Council
Resolution.
4
PASSED, APPROVED and ADOPTED this 17th day of March, 2020.
Aide Castro, Ma or
ATTEST:
Marfa Quinonez, Jose OR-eteotl,
City Clerk / City anager
APPROVED AS TO FORM: 7EDA O C e p ENT:
Noel Tapia, Richard J. Sand. mier,
F City Attorney Director of Public Works
ti
{
5
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES )
I, the undersigned, City Clerk of the City of Lynwood, do hereby certify that the
foregoing Resolution was passed and adopted by the City Council of the City of Lynwood
at a regular meeting held on the 17th day of March 2020, and passed by the following
votes:
AYES: COUNCIL MEMBERS ALATORRE, SANTANA, SOLACHE, MAYOR POR
TEM CASANOVA, AND MAYOR CASTRO
NOES: ' NONE
ABSTAIN: NONE
ABSENT: NONE
l
Maria Quinonez,
City Clerk
STATE OF CALIFORNIA )
)
COUNTY OF LOS ANGELES )
I, the undersigned, City Clerk of the City of Lynwood, and the Clerk of the City,
Council of said City, do hereby certify that the above foregoing is.a full, true and correct
copy of Resolution No. 2020.036 on file in my office and that said Resolution was
adopted on the date and by the vote therein stated. Dated this 17th day of March 2020.
Cagizei(g7tez,a497
Maria Quinonez,
City Clerk
6