HomeMy Public PortalAboutAB 22-149 Park Street PH-2-Recommendation to Award Bid Alt. 1McCALL CITY COUNCIL 216 East Park Street AGENDA BILL McCall, Idaho 83638 Number AB 22-149 Meeting Date June 9, 2022 AGENDA ITEM INFORMATION  SUBJECT: Park Street and Thompson Avenue - Phase 2: Recommendation to Modify Contract Award to Include Base Bid and Bid Alternate 1 Department Approvals Initials Originator or Supporter   Mayor / Council     City Manager     Clerk     Treasurer     Community Development     Police Department     Public Works  Originator   Golf Course    COST IMPACT: $362,875.25 - $1,022,953.75 Parks and Recreation    FUNDING SOURCE: Streets LOT: ~$40,000 – 700,000 Tourism LOT: $119,000 Streets Department: $213,500 Airport      Library    TIMELINE: Summer 2022 Information Systems      Grant Coordinator    SUMMARY STATEMENT: On April 28, 2022, City Council voted to award the base bid for the Park/Thompson Phase 2 Project (see attached select plans). As part of the discussion, Council deliberated additionally awarding Bid Alternate #1 that would extend the project improvements east from 4th Street to 3rd Street. Staff explained that the bidding was considered competitive and that total project low bid from Falvey’s Earthworks was within 17% of the Engineer’s estimate (see attached recommendation for Contract Award and bid tabulation). However, staff cautioned that awarding the bid alternate #1 (an additional ~$660K) could impact funding availability for future projects, pending the future development of the draft 6 year CIP/MIP. On May 27th, the Public Works Director/City Engineer presented to the City Council the draft 6 year CIP which outlined estimated future project costs. Staff also identified that the projected Streets LOT revenue for FY22 had significantly increased from what was assumed in late April, $2.2M, to $3.0M based on latest collection information from the LOT Administrator. In light of the new information provided in the draft CIP, and as directed by Council, staff was asked to prepare this agenda item to reconsider awarding the bid alternative. Staff has confirmed that Falvey’s Earthworks will warrant the Bid Alternate #1 price from their original bid. The City has not yet executed the construction contract with Falvey’s Earthworks for the base bid, so if Council choses to award Bid Alternate #1, staff can finalize the contract documents accordingly.  RECOMMENDED ACTION: Modify the contract award to Falvey’s Earthworks to include the Base Bid and Bid Alternate #1 for a total contract price of $1,022,953; authorize the Mayor to sign all necessary documents; and authorize staff to manage change orders up to 10% over the original contract amount.  RECORD OF COUNCIL ACTION  MEETING DATE ACTION  4/28/22 AB-22-107: Council awards Park/Thompson PH-2 contract award for base bid only to Falvey’s Earthworks, LLC