Loading...
HomeMy Public PortalAbout2. Airport - OctoberMonthly Department Report – Airport Memo To: City Council From: Emily Hart, Airport Manager CC: Anette Spickard, City Manager Date: 10/31/2022 Re: Monthly Department Report –October 2022 1. Obstruction Removal Plan A surveyor has agreed to survey the lowered apple tree to the south of the airport. Once this data is submitted to FAA, the instrument approach the RWY 34 should be reinstated. 2. Airport Water/Sewer Granite Excavation, Inc. installed the new sewer line across Taxiway A the week of October 17 - 21. Payette Lakes Recreational Water and Sewer District verified the work on Thursday, Oct. 20, and the asphalt was installed within specifications on Friday, Oct. 21 before winter weather commenced. 3. Hangar Inspections Hangar inspections have gone well. Current, tagged fire extinguishers have been verified in all inspected hangars and other fire hazards have been addressed. There are about 20 inspections remaining to be done out of 84. Additionally, the Airport’s complement of extinguishers had their annual certifications. 4. Taxiway D Final Marking and Reseeding Final centerline marking of new Taxiway D was completed Oct. 14 and reseeding was done on Oct. 17. These were the final two punch list items for AIP 033. 5. October 2022 Airport Agenda Bills Oct. 20: AB 22-274 Request to Approve termination of Tim Noga lease on Hangar 560 and new lease on Hangar 560 for Ken Lawson BLANK PAGE