1. Obstruction Removal Plan
A surveyor has agreed to survey the lowered apple tree to the south of the airport. Once this data is
submitted to FAA, the instrument approach the RWY 34 should be reinstated.
2. Airport Water/Sewer
Granite Excavation, Inc. installed the new sewer line across Taxiway A the week of October 17 - 21.
Payette Lakes Recreational Water and Sewer District verified the work on Thursday, Oct. 20, and
the asphalt was installed within specifications on Friday, Oct. 21 before winter weather commenced.
3. Hangar Inspections
Hangar inspections have gone well. Current, tagged fire extinguishers have been verified in all
inspected hangars and other fire hazards have been addressed. There are about 20 inspections
remaining to be done out of 84. Additionally, the Airport’s complement of extinguishers had their
annual certifications.
4. Taxiway D Final Marking and Reseeding
Final centerline marking of new Taxiway D was completed Oct. 14 and reseeding was done on Oct.
17. These were the final two punch list items for AIP 033.
5. October 2022 Airport Agenda Bills
Oct. 20: AB 22-274 Request to Approve termination of Tim Noga lease on Hangar 560 and
new lease on Hangar 560 for Ken Lawson