Re: PROJECT # 5515168 Aerial to Underground Relocation on Deinhard Ln, Mccall
This is in response to your request for Ziply Fiber to perform the following work: Ziply will relocate all existing
aerial facilities on Deinhard Ln, near the intersection with Hwy 55, in McCall ID.
The city of McCall is responsible for paying the difference in costs to relocate from Overhead to Underground
compared to what it would have been to relocate from Overhead to Overhead. This includes the labor, material,
and engineering.
Scope of work: Place new underground path in the open trench along the section that is in conflict. Pull new
copper and fiber cables and tie into the existing. Splice all new facilities to keep all customers and networks
working properly. Remove all existing aerial strands and cables in order to take down the poles that are in conflict
in this project.
See Exhibit A for the cost breakdown
PROJECT # 5515168
We have determined that your cost of this work effort will be: $ 85,973.57
This amount is payment in full (including tax). You will not receive an invoice or refund.
You must return this signed agreement, along with the full advance payment, before your work will be scheduled
with our Construction Department.
If you agree to these terms, please sign below and return this signed letter and a check for $ 85,973.57 made
payable to Ziply Fiber and mail to:
Ziply Fiber
Attn: Shelley Haugstad
Engineering Dept. WA0102OS
1800 41st ST, N-100
Everett, Washington 98203
Ziply shall not be responsible to the extent its performance is delayed or prevented due to causes beyond its
control, including but not limited to acts of God or the public enemy, terrorism, civil commotion, embargo, acts
DocuSign Envelope ID: 9935C180-8D51-4404-B51A-34E77669B3F1
ziplyfiber.com
2
of government, any law, order, ordinance, regulation, or requirement of any government, fires, explosions,
weather, quarantine, strikes, labor disputes, lockouts, and other causes beyond the r easonable control of Ziply
Fiber.
Should you have any questions or concerns regarding these terms, please contact me at #208-957-2816.
Please be advised that the price quoted above is only valid for sixty (60) days from the date of this letter. If we
do not receive this signed agreement and your full advance payment within this sixty (60) day period, we will
assume that you do not want the work to be undertaken and the project will be cancelled.
Sincerely,
Jon Cortabarria
Ziply – Signature
Jon Cortabarria
I agree to the terms of this agreement:
Accepted (Signature): __________________________________
Print Name & Title:____________________________________
Company: ___________________________________________
Billing Address: ______________________________________
____________________________________________________
Telephone #: _________________________________________
Email address:________________________________________
Date: _______________________________________________
DocuSign Envelope ID: 9935C180-8D51-4404-B51A-34E77669B3F1
208-634-7142
City of McCall
216 E. Park Street
McCall, ID 83638
Robert S Giles
ap-city@mccall.id.us
August 1, 2022 | 11:43 AM MDT
Exhibit A
Overhead vs underground relocation cost breakdown for the Deinhard road move:
Overhead to Underground: Place new underground path in the open trench along the section that is in
conflict. Pull new copper and fiber cables and tie into the existing. Splice all new facilities to keep all
customers and networks working properly. This is the main fiber backbone so fiber splicing will have to
be done at midnight. Remove all existing aerial strands and cables in order to take down the poles that
are in conflict in this project. Place new risers and anchors at the ends of the aerial section, where we
come down to underground. Traffic control for 1-2 days to remove all abandoned facilities.
Overhead to Overhead: Place 2 new Ziply poles and remove the old ones. Transfer all aerial
attachments as is onto the new aerial lead (4 IPCO poles and 2 new Ziply fiber poles). No need for any
new copper or fiber. No need for any new splicing. Ziply would need traffic control for 1-2 days for the
pole replacement and facility transfer.
TOTAL PROJECT COST TO RELOCATE FROM OVERHEAD TO UNDERGROUND $103,388.57
PLACING OF NEW CONDUIT PATH
PULLING ALL NEW FIBER AND COPPER CABLES
FIBER AND COPPER SPLICING
REMOVING AERIAL STRAND AND
CABLES
REMOVE ZIPLY POLES (2)
PLACE DOWN GUY AND ANCHORS
ENGINEERING AND DESIGN
MATERIAL: 4" CONDUIT, 288 FIBER, 50 PAIR COPPER, 100 PAIR COPPER, 50 PAIR COPPER, 2 RISERS, 2 DOWN GUY
AND ANCHORS
TOTAL PROJECT COST TO RELOCATE FROM OVERHEAD TO
OVERHEAD $17,415
PLACING NEW ZIPLY POLES
(2)
REMOVING EXISTING ZIPLY POLES (2)
TRANSFER EXISTING AERIAL ATTACHMENTS (ON 6 POLES, 2 ZIPLY AND 4 IPCO)
ENGINEERING AND DESIGN
EASEMENT COST
TRAFFIC CONTROL
MATERIAL: 30-4 POLES
City of McCall to pay the difference in cost between what it costs to relocate overhead to underground
compared to what it would cost to relocate overhead to overhead: $85,973.57
DocuSign Envelope ID: 9935C180-8D51-4404-B51A-34E77669B3F1
AERIAL SECTION
THAT HAS TO COME
DOWN
COME DOWN AT ZIPLY
POLE (RPT NEXT TO
POLE). PLACE DG & A
COME DOWN AT
ZIPLY POLE. PLACE
DG & A -50PR CBL
-50PR CBL
-75PR CBL
-288F
-(3 STRANDS)
EXISTING HH TO MOVE EAST
-50PR CBL
-50PR CBL
-75PR CBL
-144F
-(3 STRANDS)
Intercept existing 48 fiber going EAST
DocuSign Envelope ID: 9935C180-8D51-4404-B51A-34E77669B3F1
44.898996, -
116.096945
NORTHERN POLE
WHERE WE COME
DOWN
TO C. O.
DocuSign Envelope ID: 9935C180-8D51-4404-B51A-34E77669B3F1
44.896432, -
116.095816
SOUTHERN POLE
WHERE WE COME
BACK UP
DocuSign Envelope ID: 9935C180-8D51-4404-B51A-34E77669B3F1
NEW
3X5 HH
EXISTING 3X5
HH, NEED TO
RELOCATE
EXISTING 24F
EXISTING 48F
EXISTING 20F
TO C.O.
EXISTING 288F
EXISTING 144F
NEW EXISTING 4” CONDUIT SYSTEM. PULL
NEW 288F. EXISTING 24F TRAFFIC WILL BE
TRANSFERED TO THE 288F. 24F COMING
FROM C.O. WILL BE ABANDONED.
NEW
2X3 HH
NEW EXISTING 4”
CONDUIT SYSTEM.
PULL NEW 144F+24F
PLACE NEW 2” TO
INTERCEPT EXISTING
48F. PULL NEW 48F
X
X
X
X
X
X
X
DocuSign Envelope ID: 9935C180-8D51-4404-B51A-34E77669B3F1