CHANGE ORDER
CHANGE ORDER NO.: 3
TO CONTRACTOR:
Dalrymple Construction Services, Inc.
PROJECT: Senior Center Building & Envelope Improvements PROJECT NO: N.A.
OWNER: City of McCall
STAFF: John Powell
The following modification(s) to the Contract are hereby ordered (use additional pages if required):
See attached list
Reason for Modification(s):
Changes to project-no change in price.
Attachments (List Supporting Documents):
See list attached
Contract Amount or Price Contract Times (Calculate Days)
Original Contract Amount 338,765 Original Duration Days
Previous Change Order(s)
(Add/Deduct) 20,050
Previous Change Order(s)
(Add/Deduct) Days
This Change Order
(Add/Deduct) 0.00
This Change Order
(Add/Deduct) Days
Revised Contract Amount 358,815 Revised Contract Time Days
The Contract Completion Date is now October 31, 2022
Owner Contractor Staff Recommendation
By: By: By:
Date: Date: Date: 8/03/2022
DocuSign Envelope ID: 53E85A2C-BC8F-4493-985F-3D1F54172531
August 4, 2022 | 9:29 AM MDT August 5, 2022 | 10:06 AM CDT
Change of Scope-McCall Community Center
ALT2 wall insulation -11,340.00
add roof insulation +5000.00
savings 6,340.00
ALT6 kitchen service door -5300.00
add 1/2 light kit to existing door +1500.00
savings 3800.00
ALT4 hvac extension -6390.00
add gravity vent roof hood
system balance +14766.00
deficit <-8376.00>
ALT3 door opener +3357.00
add lighted switch and wiring
to tie into light circuit +1764.00
deficit <1764.00>
total change to contract 0.00