HomeMy Public PortalAbout2. Airport - August 2023Monthly Department Report – Airport Memo To: City Council From: Emily Hart, Airport Manager CC: Anette Spickard, City Manager Date: 09/05/2023 Re: Monthly Department Report – August 2023 1. AIP 034 Taxiway E Reconstruction Full depth reconstruction started July 24. The three-week project was substantially completed three days early, on August 8. Final markings will be done in September. 2. Airport Engineering RFQ The Professional Services agreement for airport engineering with Ardurra has been reviewed by Ardurra and the City Attorney and will go before Council on Sept. 14. 3. ITD Aero Leading Edge Grant funds The new operations pick up was delivered August 31. 5. Infield Infrastructure Airport management continues to work with PLRWSD and Ardurra to finalize approval and hook- up of the new manhole and sewer line. 6. Airport BBQ The Airport Manager and Superintendent hosted a BBQ on August 18 for the businesses that operate at McCall Airport. It was a resounding success, and everyone enjoyed getting together. 5. South Mission Street Parvel/FAA Part 77 Surface Evaluation The Airport Manager and Ardurra met with Crestline Engineers, Brian Parker, Michelle Groenevelt, and representatives from St. Luke’s Foundation to discuss aeronautical impacts of housing development on the parcel north of McCall Cemetery. Some of this parcel is in the approach surface and would require significant excavation to lower building elevations for safe aeronautical use. Discussions continue. Monthly Department Report – Airport 5. AIP 031 Close-out FAA Grant AIP 031/Taxiway D Design achieved final FAA completion and all invoices and required FAA forms have been submitted. AIP033/Taxiway D Construction is nearing close-out. 5. August 2023 Airport Agenda Bills August 24 - AB 23-174 Request to Assign Lease for Hangar 545 from Fitzpatrick Revocable Trust to Dennis B. Fitzpatrick