Re: LHT AC Quarter!~ Progress Report
. I
I City of McCall I.
Robert Giles . · I
216 E: Park St. I
! McCall, ID 83638 1
Dear Mayor Giles, . ,
Phil Lampert
Chairman.
Mac Pooler
Vice Chairman
Kevin Renfrow
· Secretary/Treasurer
Laila Kral, P.E.
Administrator
RECEIVED
FEB O 5 2024
The Local High_way Technical Assistance Council (LHTAC) provides an important
linkage between Loc~I Highway Jurisdictions (LHJs) and the Idaho Transporta~ion
Department in the uti,lization of Federal-aid highway funds available to ~he LHJs in
Idaho. LHTAC staff provides the administration,and oversight to ensure the Federal-
aid process is followed, and to protect the LHJ frpm repaying Federal funds. This letter
includes the status listing of current and upcoming local Federal-aid projects for
District 3. , l·
. . . . .
LHT AC is committed to helping sponsors through the Federal-aid process and
developing a succes~ful project. We hope you find this information informative. If you .
have any questions <Dr need any additional information, please Qontact our staff at 208-
344-0565. _· . I ·. . . .
i
Sincerely, ,~,J/P{
Laila Kral, P.E.
· Administrator I
Local Highway Techrical Assistance Council
Association of Idaho Cities
Mayor Mac Pooler
City of Kellogg
Mayor Robert (BJ) Berlin
. City of Roberts
Councilmember Kari Peterson
City of Fruitland
!
!
I
Idaho Association of Highway Districts
Commissioner Kevin Renfrow
South Latah Hirihway District
Commissioner Neal Gier
Buhl Highway District
Commissioner Gilbert Hofmeister
Power CoimtyHighway District
Idaho Association of Counties
Commissioner Phil Lampert
Benewah County
Comri,issioner Mark Rekow
Gem County
Commissioner Todd Smith
· Madison County
Ex~Officio Members
Kelley Packer, Executive Director
Association of Idaho Cities
Nick Veldhouse, Executive Director
. Idaho Association of Highway Districts
Seth Grigg; Executive Director
Idaho ~sdciation of Counties
,,
C .
'
I
i District 3 Projects in Design Phase
Quarterly Update October through December 2023
I I •
Old Hwy 30/Ply~outh St .Bridge Replacement, Sponsor: Canyon HD, Key Number:
13494
' I
Description: This project will construct a new bridge at a new location. The existing bridge will
be left in place to serve pedestrians and bicyclists and provide connectivity for the City of
Caldwell's Greenbelt pathway. The project includes three canal crossings and approximately
. . . I . . . . .
2200 feet of new approach roadway construction. ·
Status: The projec~ consultant is preparing Final Design plans and Environmental ·
documentation. i · . . i -'
Project Manager: ~manda LaMott
. !
Construction Year: 2026 . I
i
I
I
N 10th Ave ITS & Overlay, Sponsor: City. of .Caldwell, Key Number: 13905
i ' \
Description: This project will overlay a one-half mile section of tath Avenue in downtown
Caldwell from the ~ailroad overpass to 1-84 to replace the roadway surface thatis in poor
condition, This project also includes installation of an intelligent transportation system (ITS)
components to connect signals and bring pedestrian facilities to current standards. I . . .
Status: The cbnsu.ltarit for this project has submitted the PS&E package. The project is waiting .
for construction fu~ding in FY2026.
Project Manager: ~manda LaMott
Construction Year: 2026
I
i I • • •
Rail with Trail Pathway, Sponsor: City of Meridian, Key Number: 13918 . . . I . . . . . . . . . . . . . .
Description: This project will construct a multi-,use pathway along the railroad tracks for one-
half niile near downtown Meridian. . . . . I . . .
Status: The Cohsu:ltant is currently developing Preliminary Design Plans and working on the
Environmental Doqument.
Project Manager: !Amanda LaMott
Construction Year: 2025 . . I
I
Desert Canyon trail Bike-Ped, Sponsor: City of Mountain Home, Key Number:
18827 i
, I .
Description: This broject will construct sidewalks, bicycle lockers, shelters, benches, drinking
fountains, Hghting, land information boards on the besert Canyon Trail in Mountain Home.
I . •
Status: The City of Mountain Home continues working on a revised Plan, Specifications, and
Estimate (PS&E) 9ubmitt_al so that this project can be re-advertised.
. I
Project Manager: ilisa Popoff
. . . i
Construction Year: 2024
I .
Cove Rd Bridge[ ·Washington Co, Sponsor: Washington County, Key Number:
19129 I
I
I
·~
I
I
I
J District 3 Projects in Design Phase
· Qyarterly Update October through December 2023
'
Description: This broject is for work to replace the 3-span steel truss bridge on Cove Road over
the Weiser River w)th a L-Spah steel girder bridge, and raise the approach grades.
Status: The Proje~t Consultant is currently working on Final Permits and Plan, Specifications,
and E~tiniate (PS~E) Submittc;1I so that construction funds can b.e obligated. The Right-of-Way
acquisition for this project is underway. ·
Project Manager; ;Scott Wood ·
Construction Year: 2025 . . . l
Old Hwy 30; Sarid Hollow Rd to Sl-1-44, Sponsor: Canyon HD, Key Number: 19951 i . . . .
Description: The project will rehabilitate approximately 3.4 miles of Old Highway 30, a major
rural collector serv(ng northern Canyon County, as well as·southern Payette and Gem Counties.
This is the final phase of rehabilitating Old Highway 30 from the vicinity of Caldwell to Payette
County. ! ·
Status: The projedt·s Plan, Specifications, and Estimate (PS&E) has been submitted. The
project is currently'iwaiting for 2027 funding. Project received clear Right-of,.Way certificate and
environmental re-e'.valuation has been submitted to ITD for approval.
Project Manager: loan Coonce · . . I
Construction Year: 2027
!
: i
Ola Hwy; Powerline Rd to 2nd Fork Rd, Sponsor: Gem County, Key Number:
20100
I
Description: The Ola Highway Improvement project is located near the unincorporated
comm·unity of Oia in Gem County. The project is anticipated to overlay two miles of existing
pavement and pav~ three miles of existing gravel road to keep paved roads in good condition
and also to pave al road that exceeds the Averge Daily Traffic for a gravel type surface-.
Status: The consu11tant has submitt~d draft Plan, Specifications, and Estimate (PS&E) :package
to LHTAC. Utility coordination with. Idaho Power continued;
• I • •
Project Manager: iMuhanimad Zubery
I ' .
Construction Year: 2027
I
I
!
i
I
i
I
I
i
!
I
i
I
. . . I
Mission Street; Southern City Limits to Deinhard Lane, Sponsor: City of McCall,
Key Number: 20146
I
. i -' -
Description: The ~ission Street Rehabilitation project is·located in the City of McCall in Valley
County The projecf is scheduled to include the removal ofthe existing asphalt pavement
!
I.
I
I ;
I . .
J · District 3 Projects in Design· Phase
Q4arterly Update October through December 2023
I
surface; widening Jf the road section, verifying the structural integrity of the base and sub-base,
new asphalt paven\ent, striping, utility relocations, and the instaliatiori of stormwater .
conveyance ahd tr~atment systems to improve the condition of the roadway. It is also
anticipated to inclupe the ·design of a multi-use pathway adjacent to the roadway.
Status: LHTAC will submit the project Plan, Specifications, and Estimate (PS&E) package to . . I . . .
ITD in early JanuartY 2024. . ·
Project Manager: !Sam Larrondo ·
Construction Year: 2024
I
I .
-E Lake ~k Rd: EJ Lake Fk Cr Br To SHSS, Sponsor: valley County, Key Number:
20242 · / · ·· · · · - · · -
I
Description: This is a 0.55 mile long rehabilitation project on East Lake Fork Road between
Lake Fork .Creek ~ridge-arid the intersection with SH 55. This project is expected to widen the
roadway and less~n the vertical grade near the SH-55 intersection tq bring it into compliance
with current standards. Additional improvements will inQlude replacing deteriorated culverts at
an irrigation canal crossing; acquiring Right-of-Way, and mitigating impacts to wetlands adjacent
to the roadway. I · · · -,
Status: The consultant is currently developing Preliminary Design Plans and working on the
Environmental Dotument. · . . . • i . ' ..
Project Manager:: Dan Coonce
Construction Yea'r: 2028
I
Simco Rd Rehabilitation, Sponsor: Mountain Home HD, Key Number: 21981
• • • • I • •
Description: This project will rehabilitate a 5 mile stretch of Simco Road. This is a rural asphalt
surface and a major collector in Elmore County
I . -
Status: PS&E pa~kage for original ~cope of work has been delivered. This project received
additional funding 1:md project scope has been updated. Preliminary Design for new scope of
work has began. I
- - I
Project Manager:! Muhammad Zubery
Construction Yea,r: 2027
!
. I . -
Midway Rd: Karcher to Caldwell Blvd, Sponsor: Canyon HD, Key Number: 22016
i
Description: This iproject will rehabilitate pavem~ht and construct shared-use shotJld~rs on
Midway Road between SH-55(KarGher Road) and l-84B(Caldwell Boulevard) in Canyon County. I , - . -
Stat1.:1s: The Project is completed and is awaiting for funding due to the urban project list may be.
funded earlier with! end of year funding, if available. · ·
I
Project IYlanager:J Dan Coonce
Construction Year: 2027
I
I
!
"
I
\ District 3 Projects in Design Phase .
Qyarterly Update October through December 2023
. I . . -. . . . . .. .
Cherry Ln: Franl<lin Blvd to 11th AveN, Sponsor: City.of Nampa, Key Number:
22017 I
I
Description: This project will rebuild Cherry Lane from 11th Ave North to Fra'nklin Boulevard. ,
Status: The Consu
1
1tant has submitted a Draft Plan, Specifications, and Estimate (PS&E)
Submittal and it is ~waiting to receive funding. ·
. I . .
Project Manager: pan Coonce
Construction Yea~: 2027
I
I
Montana Ave: Ped lmpnr & Widening, Sponsor:-City of Caldwell, Key Number:
2201s I ·· ·
i
Description: This project will construct sidewalk from Syringa Middle School to Spruce Street
on the West Side of Montana Avenue in the City of Caldwell. The project includes a ped~strian
crossing and a rectangular rapid flashing beacon crossing at the Alder Street and Spruce Street
intersections acres~ Montana Avenue. · · · · .
. • I • . . . .
Status: Right of Way (ROW) is needed and a consultant is working on ROW documentation to
help the City with a~quisition. The Plan, Specifications, and Estimate (PS&E) Submittal has
been completed. I . · \
i
Project Manager: lr\manda LaMott
I
Construction Year: 2024 . • . . . i
Franklin Blvd & Karcher Rd Int, Sponsor: City of Nampa, Key Number: 22102
I
Description: This project will construct a dual lane offset roundabout at Franklin Blvd. and
Karcher Rd. in the dity of Nampa. The project indudes Right-of-Way, curb, gutter,' sidewalk,
lighting, pedestrian jramps, and lane widening.
Status: The projec~ is anticipating a bid advertisement date to be set.
Project Manager: ?an Coonce
Construction Year.: 2023
i
l
I
Int 3rd Ave N & W Industrial Rd, Sponsor: City of Nampa, Key Number: 22103
De~cription: This ~reject yvill instaU a new signalized intersection approxirnatei°y orie quarter
mile south of the ex,isting Franklin Blvd. and Industrial Rd. intersection in the City of Nampa.
I
Status: The Concept Report has been approved on June 30, 2021. The Freight Plan has been
approved on June gg, 2023, second design contract has been submitted for approval, anticipate
Notice to Proceed. The second design contract triggered a new State and Local Agrementto be .
executred and additional funding has also been requested awaiting a response from ITD. . . I . .
Project Manager: ~an Coonce ·
. .· f
Construction Year: 2030 . . . I .
i
I
I
I
I
I
i
' '
District 3 Projects in Design Phase
Quarterly Update October through December 2023
I .
. I . . . . .
Cherry Lane: 11th Avenue N to Idaho.Center Blvd, Sponsor: City of Nampa, Key
Number: 22438 I
Description: This hroject will rebuild Cherry Lane between 11thAvenueNorth and l~aho Center
Boulevard in the C\ty of Nampa. Work includes adding a center tum lane, pedestrian/bicycle
Janes, and interseqtion improvements,
.. Status: This proje¥ is currently developing Preliminary Design Pl~ns and working on the
Environmental Document.
I
I
Project Manager: /Dan Coonce
I .
Construction Year: 2030 . . . . . I .
I . . . . I . . . . . .
Pine-Featherville Rd Rehab, Mt Home HD, Sponsor: Mountain Home HD, Key
Number: 22606 J· .
Description: This project will rehabilitate the roadway surface with the use of CRABS (Cement
Recycled Asphalt Base Stabilization) process. The paved roa·dway currently varies between 22
feet and 26 feet wi~e with approximately 1 foot gravel shoulder on both sides of the road. The
new design will m~intain 26 feet of pavement with 2 foot gravel shoulders. The project will also
include the replacement of one set of culverts at Dog Creek with a clear span bridge.
· Stat~s: This proje!t is currently developing Preliminary Design .Plans and working c;m the
Environmental Do~ument.
Project Manager: [oan Coonce
Construction Year: 2024 . . . i
J
Homedale Rd Curve Improvement, Sponsor: Canyon HD,:Key Number: 22878
Desc.ription: This project will improve safety for roadway users by widening a bridge, widening -
shoulders, installing white thermoplastic rumble strips, and flattening side slopes. This will .
remove obstructiorns .to errant vehicles, increase the recovery area on pavement, provide drivers
1 • . . •
visual guidance with an alert of lane departure, and improve recovery area with a reduction in
overturning potential. · · ·
Status: The Intermediate Design Submittal has been received and reviewing submittal is
underway. I
. Project Manager: Dan Coonce
. . I . .
Construction Year: 2024
I
I
I
I
!
I
i
i
I
. !
I
I
l . . . .
I District 3 Projects in Design Phase
Qyarterly Update October through December 2023
I
I -- - -- -
Simco Road Saf~ty Improvements, Sponsor: Mountain Home HD, Key Number:
22879 :
I
I
Oescription: This project will improve safety for all roadway users by redesigning the
alignment's horizo~tal and_ vertical curves, adding flashing LED curve warning signs, and
rehabilitation of the: asphalt pavement surface.
Status: This has b~en combined with KN 21981. The draft Plans, Specifications, and Estimate
(PS&E) package isl on file.
Project Manager: Muhammad Zubery
• I Construction Yeat: 2025
I . I
I --- -
Pine-Featherville Rd Rehab, Sponsor: Mountain Home HD, Key Number: 22889 -- -I - - - - - --- --
Description: This project will rehabilitate the Pine...;Featherville Road by using a RABS
(Recycled Asphalt Base Stabilization) or CRAB (Cement Recycled Asp~alt Base) process in
conjunction with a rilew layer of plant mix asphalt. . · ·
I
Status: This project is currently developing Preliminary Design Plans and working on the
Environmental Doc~ment-:-·
-I -
Project Manager: pan Co<:>nce
Construction Yeaf:: 2024
' ' ' . ' ' ' .
1st St Pedestrian Safety, Sponsor: City of McCall, Key Number: 22950 -- - - I - - ---------
Description: The 11st Street Pedestrian Safety Project will construct 10 foot wide sidewalk, curb
and gutter along the east and west sides of 1st Street within the City of McCall's downtown core
1 • I . between E Lake Street SH55 south to Park Street. . · ·
, ' I
Status: This project was advertised December 2023 and is in the process of being awarded.
Constructioq to begin Summer 2024.
. I
Project Manager: ~manda LaMott
Construction Yea~: 2024
I
. I --,
Main St Sidewalk & Beacon, Sponsor: City of Cascade, Key Number: 22953
Description: This ~reject will construct a 10 foot sidewalk downtown on SH-55, Pine Street to
Lake Cascade Parkway.
-I
Status: LHTAC ha~ approved the project Plan, Specifications, and Estimate (PS&E) package.
The anticipated co~struction advertisement is April 2024.
Project Manager: E3rian Wright
!
Construction Year': 2023 - I -
I
, I
I
I
I
I
., I
I
I
I I ,
! · . District 3 Projects in Design Phase
I . . . .
Q~arterly Update October through December 2023
. .: i . . . . . ..
Grimes City Pathway.Extension, Sponsor: City of Nampa, Key Number: 23025
! .
Description: This project is a pathway extension within the City of Nanipa.
i . . . ' . .
Status: Final Design Revi.ew for this project is complete. The Consultant is working on revisions
to prepare the Plan, Specifications, and Estimate (PS&E) Submittal. lhis submittal shouid occur . I . .
_in March 2024. -I · · · ' · ·
Proiect Manager: ban Coonce ~ . I . .
Construction Year: 2025
I
I
I
. . I . . . . .
Signing Improvements (GS), Gem HD, Sponsor: Gem. HD, Key Number: 23292
!
Description: For t~e work of installing solar powered flashing traffic signs at multiple locations.
Improvements inchllde all material costs to construct 18 solar powered signs on wooden posts.
Status: LHTAC is burrently developing Preliminary Design and working on the Enviro~mental ,
Document. j . ~ · ·
Project Manager: !Brian Wright
Construction Year 2023
I
. I
Strand Trail Paving and Ped/Cyclist Safety Project, Sponsor: City of Cascade, Key
Number: 23896 I . . . . . . . . . . . . ...
Description: For t~e work of improving the Pine Street Safe Route to Schqol by installing 2
Rectarigul~r Rapi~I Flashing B_eacons on Main Street and paving_ almost 1 mile of exis~ing_ wide
non-motorized tra11 1from the Pine Street Connector to Kelly's Whitewater Park. The trail will be
paved at a width ot 1 O' and meet Americans with Disabilities Act (ADA) accessible trail
guidelines. J
Status: The consu,tant is currently developing Preliminary Design Plans and working on the
Environmental Document.
Project Manager: 1:Brian Wright
Construction Yea~: 2024
I . i. . ...
North Simco Rd1Safety Improvements, Sponsor: Mountain Home HD, Key . . . . . . I . . . . . . . . .
__ N.._u __ m=b=e""""r::...2;;;;..4=2=8.;;.0 /
i
Description: For t~e work to rehabil_itate the roadway with base stabilization and an asphalt ·
overlay along with p,odifications to the roadway alignment by flattening vertical curvature,
increasing horizont;a1 curve radius, updating curve superelevation, and flashing LED signs to
improve safety for ?II roadway users.
Status: This proje1t is being developed under Simco Road project KN 21981.
Project Manager: ,Muhammad .Zubery
Construction Yeai: 2025
I
I
I
., I
I I.
I District 3 Projects·in Construction Phase
Qu,rterly Update October through December 2023
. I . . . . . .
Middleton & Ustick Roundabout, Sponsor: .City of Caldwell, Key Number: 13487
I
. I . .
Description: This project will improve a four-way stop at the Middleton Road and Ustick Road
Intersection by buil~ing a roundabout to help traffic flow and congestion;
Status: The projec~ is complete. The Construction Engineering and Inspection (CE&I)
Consultant is cu~ertly working on project close-out. .
Project Manager: Matt Koster ·
. ' I
Construction Year: 2023
i
1
Peckham Road Rehabilitation, Sponsor: Golden Gate HD; Key Number: 13964
Description: The Jroject will improve 3.75 miles of Peckham Road between US-95 and Notus
Rd. The project includes curb, gutter, and sidewalk in select locations within the city limits of
Wilder and Greenl~af. ,
Status: This projedt has been awarded and construction is anticipated to. begin in April 2024.
• I
Project Manager: ,vlegan Kautz
Construction Yea~: 2023 . . . I
I
Peckham Rd lnt~rsections, Sponsor: Golden Gate HD, Key Number: 22101 . . .. . I -. .. . . . • ... -.....
Description: This J?roject will reconstruct three intersection on Peckham Road at Travis Road,
Allendale Road and Van Slyke Road. Each intersection is substandard for truck turning
movements. The reconstruction will provide large turning radii to eliminate truck off-tracking and
reduce edge breakpp. The intersection improvements will also allow trucks to maintain their own
travel lane while m~king turns ..
Status: This projest has been awarded and construction is anticipated to begin in April 2024.
, Project Manager: ~egan Kautz
Construction Year: 2023
i
Recreational Ro~ds Signing, Sponsor: Valley County, Key Number: 22406 ·
i
Description: The s:cope of the Recreational Roads Signing & Delineation Safety Improvements
project, located in \(alley County, will be accomplished by providing extra signage to help drivers
safely navigate the Jroadways and increase driver awareness of corners at various locations
along recreational r:oads within Valley County. I .
-I Status: The projec~ is currently in construction. The anticipated completion date is Spring 2024.
Project Manager: ~rian Wright
. I
Construction Year:: 2021 . i
,·