HomeMy Public PortalAboutTIMSC Phase 1 GMP 11.29.18.pdfTybee Island Marine Science Center 11/29/2018 General Conditions 105,417.00 Temporary Toilets 1,200.00 Temporary Utilities 5,500.00 Temporary Office Trailer 4,924.00 Project Manager 19,350.00 Superintendent 43,000.00 Project Administration 2,500.00 Interim Clean-up 3,010.00 Dumpster 5,688.00 Rental Equipment 4,300.00 Final Cleaning - Temporary Protection 3,225.00 Temporary Site Fencing 7,720.00 Legal Fees 3,500.00 Plan Reproduction 1,500.00 Testing & Special Inspections By Others Sitework 183,528.00 Site Preperation 24,260.00 Field Engineering 3,500.00 Earthwork 36,625.00 Soil Treatments 738.00 Utilities (within 5' of building)56,600.00 Paving 43,005.00 Landscaping & Irrigation 6,800.00 Site Improvements (dumpster enclosure)12,000.00 Concrete 538,661.00 Foundation, Piers & PT Slab 434,536.00 Pavers/Concrete Paving 65,910.00 Cistern 38,215.00 Equipment Pads (allowance: at ground floor)- Thermal & Moisture Protection 1,700.00 Waterproofing 1,700.00 Sub-Total: 829,306.00 Permitting Allowance: By Owner Builder's Risk 1,643.00 P & P Bond 15,707.00 Fee:42,410.00 Total 889,066.00$