HomeMy Public PortalAboutTIMSC Prelim. Schedule 11-12-18.pdfID Task Name Duration Start Finish1Pre Construction224 daysMon 4/16/18Thu 2/21/192Project Award6 daysMon 4/16/18Mon 4/23/183Kick‐Off Meeting1 dayThu 6/7/18Thu 6/7/184A/E:135 daysFri 6/8/18Thu 12/13/185Schematic Plans (SD)13 daysFri 6/8/18Tue 6/26/186Phase 1 Foundation Pkg (CD)10.5 wksFri 8/17/18Tue 10/30/187Phase 1 Civil Pkg (CD)9 wksFri 8/17/18Thu 10/18/188 Construction Document  Plans (CD)17 wksFri 8/17/18Thu 12/13/189Estimating / GMP:117 daysWed 8/1/18Thu 1/10/1910SD Budget1 dayWed 8/1/18Wed 8/1/1811TIMSC Committee Meeting & SD Review1 dayThu 8/16/18Thu 8/16/1812Foundation / Civil Package SOV10 daysTue 10/30/18Tue 11/13/1813CD SOV15 daysFri 12/14/18Thu 1/3/1914GMP Amendment 1: Foundation / Civil0 daysTue 11/20/18Tue 11/20/1815GMP Amendment 2: Balance of Bldg.0 daysThu 1/10/19Thu 1/10/1916Permitting:55 daysFri 10/19/18Thu 1/3/1917Foundation3 wksTue 10/30/18Tue 11/20/1818Civil   2 wksFri 10/19/18Thu 11/1/1819Building3 wksFri 12/14/18Thu 1/3/1920Submittals:67.5 daysTue 11/20/18Thu 2/21/1921Foundation / Civil Submittals4 wksTue 11/20/18Tue 12/18/1822Shell Pkg. Submittals5 wksFri 1/11/19Thu 2/14/1923Build‐Out / MEP Submittals6 wksFri 1/11/19Thu 2/21/1924Construction   287.5 daysTue 11/27/18Thu 1/2/2025GMP 1107.5 daysTue 11/27/18Thu 4/25/1926Mobilization1 wkTue 11/27/18Tue 12/4/1827Groundbreaking Ceremony0 daysTue 12/4/18Tue 12/4/1828Erosion Control / Demo / Grading2 wksTue 12/4/18Tue 12/18/1829Foundations5 wksTue 12/18/18Tue 1/22/1930Detention System4 wksTue 1/15/19Tue 2/12/1931CIP Columns5 wksTue 1/22/19Tue 2/26/1932CIP Walls2.5 wksTue 2/26/19Thu 3/14/1933Slab on Grade2 wksFri 3/15/19Thu 3/28/1934PT Slab 2 wksFri 3/29/19Thu 4/11/1935Water / Sewer Utilities4 wksFri 3/29/19Thu 4/25/19Pre ConstructionProject AwardKick-Off MeetingA/E:6/26Phase 1 Foundation Pkg (CD)Phase 1 Civil Pkg (CD) Construction Document Plans (CD)Estimating / GMP:SD BudgetTIMSC Committee Meeting & SD ReviewFoundation / Civil Package SOVCD SOV11/201/10Permitting:FoundationCivil BuildingSubmittals:Foundation / Civil SubmittalsShell Pkg. SubmittalsBuild-Out / MEP SubmittalsConstruction GMP 1Mobilization12/4Erosion Control / Demo / GradingFoundationsDetention SystemCIP ColumnsCIP WallsSlab on GradePT Slab Water / Sewer Utilities2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2Tybee Island Marine Science CenterPreliminary ScheduleMon 11/12/18 Page 1 ID Task Name Duration Start Finish36GMP 2 (Preliminary Only)190 daysFri 4/12/19Thu 1/2/2037Shell / Deck Framing6 wksFri 4/12/19Thu 5/23/1938Roofing4 wksFri 5/24/19Thu 6/20/1939Storefront Glazing 3 wksFri 6/21/19Thu 7/11/1940MEP Rough‐In4 wksFri 7/12/19Thu 8/8/1941Exterior Trim5 wksFri 7/5/19Thu 8/8/1942Porch, Ramp, & Theatre Framing / Trim5.5 wksFri 8/9/19Tue 9/17/1943Exterior Finishes4 wksTue 9/17/19Tue 10/15/1944Interior Finishes7 wksFri 7/26/19Thu 9/12/1945MEP Trim‐Out6 wksFri 9/6/19Thu 10/17/1946Finishes / Pedastal Flooring4 wksFri 10/18/19Thu 11/14/1947Hardscapes / Landscaping5 wksTue 10/15/19Tue 11/19/1948Exhibit Coordination3 wksFri 11/15/19Thu 12/5/1949Accessories, Lift, Hardware. Etc.2 wksFri 12/6/19Thu 12/19/1950CO0 daysThu 12/19/19Thu 12/19/1951Final Cleaning / Punch List / CO2 wksFri 12/20/19Thu 1/2/205253Note ‐ this schedule does not consider weather delays, unforseen conditions, or conditions out of thecontractors control. If encountered, WCC will immediately notify Owner per contract requirements. GMP 2 (PreliminShell / Deck FramingRoofingStorefront Glazing MEP Rough-InExterior TrimPorch, Ramp, & Theatre Framing / TrExterior FinishesInterior FinishesMEP Trim-OutFinishes / Pedastal FloorinHardscapes / LandscapingExhibit CoordinationAccessories, Lift, HaCOFinal Cleaning / P2nd Quarter3rd Quarter4th Quarter1st Quarter2nd Quarter3rd Quarter4th Quarter1st Quarter2Tybee Island Marine Science CenterPreliminary ScheduleMon 11/12/18 Page 2