HomeMy Public PortalAboutExhibit MSD 84K - Program ImplementationPROGRAM IMPLEMENTATION MSD Engineering has developed an integrated team approach to the Consent Decree (CD) Program Implementation. The integrated approach started long before the actual CD was approved. In 2008 MSD Engineering Planning established its Program Planning platform based on the team concept and organization hierarchy. That has been used as the model as different teams have been brought on to address the three major facets of the CD: Program Planning; Capacity, Management, Operations, and Maintenance (CMOM) Program, and Program Delivery. Below are brief descriptions of the roles related to this Program Implementation. STEERING COMMITTEE: consisting of the Executive Director as well as Director’s from most Departments of the District, the STEERING COMMITTEE has total oversight of all facets related to complying with the CD. This Committee is briefed on a monthly basis by the PROGRAM PLANNING TEAM, with support from the CMOM PLANNING and PROGRAM DELIVERY TEAMS. Additionally, this team is the clearinghouse for all CD submittals and updates the EPA, Coalition for the Environment and State of Missouri with a semi-annual meeting. PROGRAM PLANNING PROGRAM PLANNING TEAM: consisting of the Assistant Director of Engineering/Planning, Assistant Director of Operations, and Program Manager of Planning. This team reports directly to the STEERING COMMITTEE. All SERVICE AREAS, WATERSHED TEAMS, CSO TEAMS and PROGRAM PLANNING SUPPORT roles report the PROGRAM PLANNING TEAM. This team is responsible for the overall development of the MSD Capital Improvement and Replacement Program (CIRP) which consists of the CSO Long Term Control Plan, SSO Control Plan, WWTP Plan and District Asset Management. Detailed responsibilities and activities include: •Formation of Service Area/Watershed Teams consisting of cross-divisional, cross-department, and cross-functional members from MSD staff and Jacob’s Engineering. •Develop organizational hierarchy per attached organizational chart. •Development of Technical Memorandum Manual (TMM) that outlines processes and principals integral to the execution of the SSO Control Plan. •Development of a best management practice (BMP) documents that set standard procedures used by all the teams for major tasks to be performed during the SSO Control Plan development •Training of teams on the TMM and BMP documents established for the program. •Service Area/Watershed teams meet on weekly or bi-weekly basis reporting directly to the Program Team •Program Team meets twice monthly to overall program development issues, program schedule, consistency issues, and review of DRAFT deliverables. •The Program Team is responsible for all document review and approval prior to Legal and Steering committee approval. •The Program Team reports directly to the Steering Committee through monthly update meetings. Update meetings typically discuss CIRP project delivery and schedules, CD milestones and deliverables, report schedules, and other pertinent issues. PROGRAM PLANNING SUPPORT: Planning support is provided by contract from Jacob’s Engineering. Responsibilities include: •Hydraulic Modeling support •Management and Preliminary design support •Scheduling support •GIS and System Characterization support •CSO Long Term Control Plan Development •SSO Master Plan development and report development. •Technical support associated with lawsuit mediation and CD negotiations Exhibit MSD 84K CAPACITY, MANAGEMENT, OPERATIONS, AND MAINTENANCE (“CMOM”) PROGRAM CMOM PLANNING TEAM: consisting of the Assistant Director of Engineering/Planning, Assistant Director of Operations. This team is responsible for the overall development Operational activities associated with the Collection System Capacity, Management, Operation and Maintenance (CMOM) Plan. This team’s effort is coordinated through the PROGRAM PLANNING TEAM. The CMOM SUPPORT role reports to this team. Detailed responsibilities and activities include: • Formation of Asset Management Team consisting of cross-department, and cross-functional members from MSD staff. • Develop work process flows and service level production rates for sewer system operation and maintenance (i.e. sewer cleaning, sewer inspection, repair, and rehabilitation of sewer system). In line with requirements of the CD. • Develop work process flows and service level production rates for pump station and forcemain operation and maintenance (i.e. pump station inspection, force main inspection and testing, repair and rehabilitation program). In line with requirements of the CD. • Development of dashboard to measure productivity of all system operation and maintenance. • Completed development of Standard Sewer Pipeline Defect Coding and Evaluation Manual for sewer inspection. • Development of sewer system condition and criticality rating system for use in projecting sewer system rehabilitation and replacement. • Future development of Asset Management program for WWTP operations and maintenance. PROGRAM DELIVERY PROGRAM DELIVERY TEAM: consisting of the Assistant Directors of Engineering from both Design and Construction. This team is responsible for the overall execution of the design and construction of all projects. This team’s effort is coordinated through the PROGRAM PLANNING TEAM. All PROJECT STEERING COMMMITTEES as well as the GREEN INFRASTRUCTURE, DESIGN and CM SUPPORT roles report to the PROGRAM DELIVERY TEAM. Detailed responsibilities and activities include: • Meets at least once a month with each PROJECT STEERING COMMITTEES • Major contractual issue • High level project status tracking • Ensure consistency across DESIGN SUPPORT teams as necessary • Evaluation of project execution scope and budget changes • Facilitate synergy efforts with other governmental agencies • Coordination with PROGRAM PLANNING and PROJECT CONTROLS • Reports Monthly to the STEERING COMMITTEE PROJECT STEERING COMMITTEE(S): consisting of cross-department, and cross-functional members from MSD staff that provide direction and guidance in the execution of the design and the resulting construction projects. Detailed responsibilities and activities include: • Separate Steering Committee for each design team • Meets at least monthly and as technical issue warrant • MSD Design, Construction, Operations representatives • General project direction, coordination and monitoring • Report directly to PROGRAM DELIVERY TEAM GREEN INFRASTRUCTURE SUPPORT: consisting of cross-department, and cross-functional members from MSD staff that provides technical support to the execution of the Green Infrastructure and City Shed components of the CD. Detailed responsibilities and activities include: " Identify opportunities for Green Infrastructure " Coordinate with St. Louis City leaders " Coordination with development community " Implement new initiatives " Provide technical expertise for design and monitoring " Develop criteria related to Green Infrastructure implementation " Administer Pilot and Early Action Programs " Perform public engagement on Green Infrastructure Program DESIGN SUPPORT: consists of five consultant design teams, with three being geographic based and two formed to design tunnel / large facilities. Detailed responsibilities and activities include: " One year contracts with extensions upon good performance " Annual appropriations for mostly lump sum design assignments " Last team brought on in 2015 " Develop planning data into detailed construction solutions " Propose alternative solutions for evaluation " Monitor and report upon adherence to schedule and budget CM SUPPORT: consists of three construction management teams. Two of the teams will be specifically geared toward tunnels and one for large facilities. Detailed responsibilities and activities include: " Infused early in design to provide feedback throughout entire project " Serve as technical advisors to the PROJECT STEERING COMMITTEES " Independent MSD representative between designer and contractor " Monitor, report and track all construction efforts for MSD PROGRAM DELIVERY TEAM Asst. Dir. of Engineering / Design Asst. Dir. of Engineering / Construction PROJECT STEERING COMMITTEE Design Representative Construction Representative Operations Representative CM SUPPORT Consultant Teams (3) PROGRAM PLANNING TEAM Asst. Dir. of Engineering / Planning Asst. Dir. of Operations Program Manager / Planning STEERING COMMITTEE Executive Director General Counsel Secretary Treasurer Director of Engineering Director of Operations Director of Finance Director of Information Systems PROGRAM PLANNING SUPPORT Jacobs Engineering PROGRAM CONTROLS SERVICE AREA / WATERSHED TEAM / CSO TEAM Engineering Representative Operations Representative Jacobs Representative RESOURCES AND SUPPORT SERVICES SKME Reports Scheduling Modeling Flow Monitoring I/I Investigation CCTV Radar Rainfall Maximo / Hansen Data Public Relations Private I/I Removal GIS Compliance Monitoring Water Quality Data Stormwater Plan Coordination New Development Review & Coordination Compliance / Regulatory (DEC) Operations – WWTP Operations – Pump Stations Operations – Collection Systems Rehabilitation / Repair Data DESIGN SUPPORT Consultant Teams (5) PROGRAM IMPLEMENTATION ORGANIZATION CMOM PLANNING TEAM Asst. Dir. of Operations Asst. Dir. of Engineering / Planning CMOM SUPPORT Asset Management Team (Internal) GREEN INFR. SUPPORT Green Infr. Team (Internal) CIRP CMOM PROGRAM REPORTING OPERATING BUDGET