Loading...
HomeMy Public PortalAbout2019 Undergrounding of Utilities - Master Plan.pdfUTITITIES itBü\$K3ËFtffiR4,åUhåÐ RESILIENT. REt-IABLE. PROTECTED. ,1i:iì,'..ti. ;t i :' ;r ij t i,a; t',.) t., . t' i. t'. : : i: i TAB1 03/19/19 CLERK'S COPY -=' Masterffiffimffi ".,1 t'i,.,,'\i i: ' i I ;' ; ; i, ' , .;". .;, äã radærg r,æ,ru ndñx *g *# {"ðüfr ñ frËHes 'r, / rl* A f¿ r* -:',,fr,í i f j r* Kirnley))Þ Horrl ,,.-r't..,I E ø taElo. Expect More. Experience Befier wwsw w.r. www/wwwww wwwwwww wwwwwws tee" 4, r/ • I a i1 ble of ntents Chapter 1 - Executive Summary 1 il 3 o ) ,) ) 3 3 Chapter 2 - lntroduction and Project Goals I Chapter 3 - Existing Ut¡l¡ty System Overview 15 Chapter 4 - Data Collection 21 Chapter 5 - Design Criteria and Conceptual Design Description 35 Chapter 6 - Phasing and Sequencing 51 Chapter 7 - Project Delivery Methods 63 Chapter I - Risk Assessment 77 Chapter 9 - Transportation Management Plan 87 Chapter 10 - Public Outreach Program 105 Chapter 11 - Overall Program Opinion of Schedule 109 Chapter 1 2 - Overall Program Opinion of Probable Construction Cost......115 o o o o o oJJ JJ '-) U '{,) O J l)J U J !.) J J U Kimley>)Horn .0. r. . • J, l Key Biscayne • sh, litek • T • t t • • { _ . • . . • Z I l \, ì ) ) ) ) ) ) apter 1 EXECUT¡VE SUMMARY ln 2006 the Florida Public Service Commission (PSC)voted to amend the Florida Administrative Code to require investor owned utilities (lOU) to file comprehensive storm hardening plans. These plans included storm preparedness initiatlves including the hardening of existing transmission structures. Storm hardening is ihe upgrading of electrical facilities, as well as maintenance practices, so they are better able to withstand extreme weather. Storm hardening of overhead utilities includes: . replacement of wood poles with concrete or steel poles ' addition of guy wires for pole support . addition of poles to decrease the span between poles Florida Power & Light (FPL) has implemented these measures in many municipalities as these initiatives were rolled out through their service area. Based on the substantial costs and impacts to the electrical grid caused by past hurricanes, FPL has embarked on a program to harden their network of poles supporting feeder infrastructure to increase their resiliency during future storm events. The Village decided that FPL's storm hardening program would have a negative impact on the Village's aesthetics. Considering those impacts along with the reliability and safety benefits, the Village decided that a conversion of the overhead utilities to an underground location, also known as undergrounding, should be pursued. The conversion from overhead to underground facilities will improve the safety, reliability, and aesthetics of the electric and communications infrastructure serving the Village. ln the Spring of 2017, Village Council took the first step in the undergrounding process and approved to move forward with a publicly advedised RFQ, which would initiate the process of finding a consultant to prepare a Master Plan to map out the underground conversion to its completion. This master plan will provide a guide for the design and implementation of the undergrounding program. lt also provides guidance on how to balance and manage priorities, such as cost, project duration, traffic impacts, and other capital improvement needs during this ambitious project. This master plan summarizes the following activities and recommendations: .î. Data Collection * Design Criteria and Conceptua¡ Design Description * Phasing and Sequencing Plan * Project Delivery Methods * Risk Assessment * Traffic Management Plan * Public Outreach Program * Opinion of Schedule A Opinion of Probable Cost Data Collection The Village of Key Biscayne is provided with electric service through redundant subaqueous crossings of transmission [ines below Biscayne Bay from the mainland to Key Biscayne's substation. Communication services are routed from the main land over the Rickenbacker Causeway and then underground along Crandon Boulevard to the Village where they are then converted to aerial lines mounted to wood or concrete poles shared 1Kimley)>Horn VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN with electrical lines. There are approximately 16 pole-miles of overhead infrastruclure and 12 miles of underground infrastructure within the Village limits, Much of the overhead utility infrastructure is located in rear yard easements between street blocks within the single-family residential areas on the west side of Crandon Boulevard and multi-family areas on the east side of Crandon Boulevard, Underground infrastructure is often located within the public right-of-way of ihe Village, The masler plan considers the various aspects that make the Village unique, such as zoning and land use designations, traffic, general topography and soils, types of underground infrastructure that exist, and plans for other future infrastructure improvements. Future infrastructure improvements include projects planned by the Village of Key Biscayne, Miami Dade County Water and Sewer, Miami Dade Traffic, and Hotwire Communications. Each of these consideralions play a role in how the overall program will be executed. Design Criteria and Conceptual Design Description Development Through a series of meetings with the Village, FPL, AT&T, Comcast, and other stakeholder utilities, Kimley-Horn assembled general guidelines for design criteria for the undergrounding program, These criteria are intended as guidance for the design of the physical location and placemeni of conduit and equipment so that consisiency in design and construction can be realized over lhe life of the program. They do not govern the detailed electrical or commlrnications network design that will be performed by FPL, AT&I and Comcast, Network design by the utility owners will be per-formed based on their then-current design standards. Utility owners and stakeholders participated in workshops to review design requirements for the proposed underground infrastructure, define significant equipment needs to implement the program, and determine their approximate locations. The Village is currently implementing a street light program to install new light poles and fixtures. The undergrounding project will impact a significant number of street lights within the Village that are currently mounted to FPL- owned utility poles that will ultimately be removed. Slreet lighting throughout the Village can be replaced with Village owned custom lighting or with FPL owned and maintained light poles and fixtures provided under FPLs street lighting program, included in their Ll-1 Tariff, Phasing and Sequencing Plan Development The masler plan provides a recommended phasing and sequencing plan for the implementation of the undergrounding program. This plan provides overall guidance of timing and sequence, but adjustments may be needed in the future to account for changes in technology, various utility and stakeholder requirements, and changes with other work programs within the Village during the implementation of the undergrounding program. Timing and sequencing should be reviewed at the time of design for each phase so any necessary adjustments can be made. 2 Example of hardened utility poles The program is proposed to contain four phases, ln an effort to accelerate the implementation schedule each phase may contain separate sub- phases or work areas. Each phase is anticipated to have a consiruction duration of 18 to 24 months. A new phase will begin construction In each year between2O2O and2024. This allows for adjacent phases to overlap in their duration, which in turn accelerates the implementation schedule. ln general, phase 1 through 3 work will begin at the south end of the Village and progress north while phase 4 will return to the south to convert Mashta lsland and finish up the west side of the Village. This plan also provides recommendations related to the timing of major infrastructure projects performed by the Village and outside entities in an effort to minimize community impacts and take advantage of potential cost saving efficiencies. Project Delivery Method Recommendation The Village's undergrounding program is a very large and complex infrastructure program that will be implemented in a phased manner over the next four to six years. lt may include not just the undergrounding scope of work, bul also roadway and stormwater improvements, water main replacement, and landscaping upgrades. ln developing recommendations for projecl delivery methods for each of phases, the risks to schedule, level of service expectations, and cost must be carefully considered. The more improvements you include in the program the higher the risk. lf any single-phase falters in any of those three areas of risk, the remaining phases of the program will be detrimentally affected, For this reason, the project delivery method must balance those risks while yielding the highest probability of project success. Although the delivery meihod that ultimately gets chosen may depend largely on how much work the Village would like to accomplish as part of the program, this master plan recommends that the Conslruction Manager at Risk (CMAR ) method of project delivery be used because, in our opinion, it yields the highest probability of success for delivering ihe various phases of the Village's Undergrounding Program. Kimley>)Horn 1.0 EXECUTIVE SUMMARY 3 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Risk Assessment Risks are involved with any project, and a propct of this magnitude is no exception. These risks can impact the project schedule and/or the project costs. By identifying these risks ahead of time, steps can be taken to mitigate them. An assessment of known risks to budget and schedule, both in terms of the design phase and construction phase, was made in order to identify these risks and take steps to mitigate them. Traffic Management Plan Development A Transportation Management Plan f-MP) was developed to coordinate traffic impacts related to both the undergrounding program and other known significant infraslructure projects to minimize impacts to the residents and businesses. Based on the recommended phasing and the sequencing plan, Kimley-Horn assessed the potentialtraffic impacts from construction of each phase of the project. The TMP ^^+ô +^p+t\ ^',^.^ll ^' 'iÀi^^ ^.i^^i^l^ô iÀ^^+i.Fi^¡ in ñl-'nn+nr al +^' , ,nn l-.r,ùçLù tvtLttuvçt ail vutuiltv vt iltutvtgù, tugt tLiltgu ilI vr rqvLgr ü, rvr uùg uy the Village and affected contractors during the implementation of the undergrounding program. The TMP may evolve over time, but its current role is to assist in the development of the construction phasing plans, traffic control plans, and project specification documents, and to facilitate discussions between the Village, designers, utility owners, contractors, and other key stakeholders related to traffic impacts. lt is a tool to better coordinate construction traffic impacts as specific permits are applied for by the construction community. Graphical TMP maps for each phase of the undergrounding program, along with general traffic control guidelines for the program, were developed and are contained in this master plan. Public Outreach Program Recommendations The undergrounding project in the Village of Key Biscayne will incorporate a Public Oulreach Program to ensure that the community is informed on the process, the benefits, and costs, The Community Outreach Program is a critical part of the public education and transparency efforts. lt will create a link between the engineering team, Village staff, elected leaders, the Undergrounding Task Force (UUTF), utility owners, Village residents, and the media. The program will engage and communicate with the community through presentations, print and electronic media, public meetings, and through a Speakers Bureau. lnformation and communications to the community should be made through a variety of mediums and be pedormed in a manner that is most suitable for the intended audience. For broad based messaging and project updates, the following methods should be employed: . Project website . Project Facebook page/Iwitter postings . Use of the social app, Nextdoor, to connect neighbors and the community . Newsletters or postcards (electronic and prinied direct mailers) . Email blasts . Public meetings (including live Tele-Town Hall meetings) . Media releases . Communications hotline (telephone) For messaging related to communicating how the project and individual phases may impact a particular resident or business owner, the communication should be tailored to the specific situation. These 4 1.0 EXECUTIVE SUMMARY ) ) ) ) situations include communicating information related to specific design and construction activities that specifically affect the individual resident or business owner. The following methods should be employed to communicate with individuals during the design and construction phases: Direct email, telephone, and/or direct mailings Neighborhood meetings lndividual meetings with residents/business owners As a lesson learned on prior projects it is recommended that direct mailings be made to inform residents and business owners that the contractor will be placing equipment within the right-of-way adjacent to their properties. This enables the project team to get ahead of and coordinate with property owners who may have questions or concerns regarding the equipment that will be located adjacent to their homes. This minimizes the impact to the community as they will know exactly what io expect regardless of whether or not they granted an easement. Consistent messaging should occur throughout the duration of the program to keep the community informed about the various stages of the process, the progress that is being made, and the goals and milestones that are being achieved. To that end, a brand logo and tag line has been developed so that residents can immediately identify communications related to this project. Opinion of Schedule Based on the Phasing and Sequencing Plan, an opinion of schedule was developed to better understand how each individual phase of the program would interact with each other during the implementation process. Schedule considerations were developed through discussions with the Village, area contractors with expertise in undergrounding, our experience with recent undergrounding projects, and the utility owners. Construction activity durations are based on reasonable production rates from area contractors with undergrounding experlise. Combining these production rates with mass quantities for the project that were developed as a part of the opinion of cost development yielded significant activity durations that were then incorporated into the overall schedule. Utility design timeframes experienced on other projects currently undenvay were also considered. Appropriate schedule contingencies were also applied to account for normalweather impacts, potential geological challenges (rock), and unforeseen conditions. The program schedule began in February 2018 with the development of this master plan. Subsequent to design of Phase '1, construction activities are expected to begin in the summer ol2O2O. Construction durations for each phase range from 'l 8Io 24 months depending on the quantity of work to be performed and complexity of each Phase. To accelerate the work, the construction schedule for each phase overlaps the previous adjacent phase construction schedule by six months to one year. The overlap of the construction activities in each phase is subject to conduit installation being complete in the previous phase prior to allowing conduit installation activities to begin in the subsequent phase, This is done primarily to mitigate traffic impacts, There is an opporlunity to compress the schedule further by splitting each phase up into two work areas, however, any fudher compression will be contingent on the utility company design schedules and easement acquisition timeframes. The final six months of the construction activity schedule for each phase is reserved for overhead infrastructure demolition, lt is not expected that this will be a continuous construction activity. Experience with similar projects has shown that the coordination required with FPL, AT&T, and Comcast can be time consuming and lhey need to work sequentially rather than concurrently to remove facilities. Therefore, this activity requires a certain duration of time to be accomplished. Based on our opinion of schedule, all areas of the Village are anticipated to be converted underground by the end of 2025. Final pole removal is anticipated to be completed by the end of the first quarter in 2026. The schedule does contain time contingencies for normalweather impacts, rock conditions, and typical unforeseen conditions. lt does not account for significant schedule impacts related to significant weather events that cause the utility owners to focus efforts on storm recovery rather than undergrounding, lt also does not consider significant contractor issues related to litigation, bankruptcy, non-performance, and the like because these types of issues are impossible to predict. ) ) ) ) ) ) ) ) 5KimleyDHorn VILLAGE OF KËY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Opinion of Probable Cost The master planning process included the development of a Conceptual Opinion of Probable Cost for the undergrounding program. The Village does not have an existing budget established for this project, therefore, there was a desire to evaluate and update the potential costs based on information obtained through the master planning process. A summary of total projecf cosfs, including contingency and inflation, is provided in the following table. Village of Key Biscayne Overall Program Opinion of Probable Cost Summary - August 201 I 1 Overhead to Underground Conversion - FPL $17,900,000 Pro¡ect costs should be tracked throughout the life of the program so that the opinions of cost for subsequent phases can be updated as actual expenditures are realized. This may increase the accuracy of the budget forecasting for the balance of the program as cost projections would be based on realized Village of Key Biscayne project costs rather than similar representative projects, As shown in the summary table, the FPL Government Adjustment Factor (GAF)Waiver credit has been estimated, lt is expected the Village will enter into an Underground Facilities Conversion Agreement with FPL for the conversion of Village-wide overhead facilities. ln accordance with the FPL Tariff, this program qualifies for a GAF waiver credit of 25o/o. The GAF waiver credit amount has been estimated at 25o/o of the total estimated FPL CIAC (contribution-in-aid-of-construction) cost to install the underground system. Additionally, this past spring the FPL Tariff was revisecl to inch¡cle acJrJitional cJiscounts. Effective Febnrary 22,2018, cerlain elements of the CIAC calculation can be excluded if the applicant intends to convert existing non-hardened feeder facilities to underground feeder facilities. The calculation would exclude the cost to remove the existing overhead feeder facilities and the net book value of those feeder facilities. ln turn, however, the applicant does not get credit for the estimated salvage value of the existing overhead facilities to be removed, Revenue generated, or costs related to potentialVillage-owned broadband infrastructure improvements, are not considered in this opinion of cost. This is because the Village has not yet formally decided whether or rroi lhey will proceed wiih i.l-re irrslailalioir of a [.¡roadtrand irrírasiruclur'e network. The opinion of cost to construct a broadband network and the projected revenues vary widely across the various options that exist. While these improvements may be construcled concurrently with the undergrounding program, any costs related to this effort are not included in the undergrounding program because this is considered an investment into improving broadband service to the community and is not a "like-for- like" replacement of what already exists in an aerial configuration within the Village. Expected cost variations may occur throughout the life of the program based on market conditions, labor and material price fluctuations, and olher factors. Kimley-Horn has no control over the cost of labor, materials, equipment, or over the Contractor's methods of determining prices or over competitive bidding or market conditions. Opinions of probable costs provided herein are based on the information known to Kimley-Horn at this time and represent only Kimley-Horn's judgment as a design professional familiar with the construction industry, Kimley-Horn cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its opinions of probable costs. 6 2 Utility Conversion Costs - ATT & Comcast $9,200,000 3 lmpacted Street Light Replacement (Village Custom)$1,100,000 4 Restoration $6,000,000 5 Construction Management $3,800,000 6 Eng i neeri n g/Perm itti ng/Su rveyin g $2,000,000 7 Construction Administration $1,800,000 8 Legal Fees/Easement Acquisition $500,000 I Public Outreach $goo,ooo 10 FPL Credit - 25Yo GAF Waiver $(4,400,000) 11 Subtotal Undergrounding Project Costs $38,200,000 12 10% Contingency $3,900,000 13 lnflation $4,900,000 14 Total Undergrounding Project Costs $46,800,000 Opinion of Probable Cost DescriptionItem No. .1 .O EXECUTIVE SUMMARY E ..//' 7 ) ) ) .) Kimley>)Horn ì I I ) ') ) ) ) ) ) ) ) ) ) ) ) ) ) th r2 INTRODUCTION AND PROJECT GOALS lntroduction Over the past decade, multiple hurricanes have impacted the South Florida area and caused widespread power and communications systems disruptions, ln September of 2017 , Hurricane lrma made landfall in the Florida Keys as a Category 4 hurricane. Within the Village of Key Biscayne Village) there were reports of many property owners either without power or communications service for days as utility crews repaired the damage. Similar to many other municipalities in South Florida, these severe weather events prompted the Village to investigate the feasibility of relocating the existing overhead utility infrastructure (electric, telephone, and cable)to an underground location, also referred to as "Undergrounding." Over time, portions of the Village have seen conversions of overhead utilities to an underground location, Much of the overhead utilities for the east side of the Village are already underground due to large scale redevelopment. Several small-scale neighborhood projects on the west side of the Village have undergrounded overhead utilities, including the Cape Florida neighborhood and more recently, the Harbor Point area including W Matheson Drive and Bay Lane. While additional projects were discussed with FPL as far back as 2008, including Crandon Boulevard and Mashta lsland, these projects were not pursued. Over the last decade, FPL has been required by the Florida Public Service Commission (PSC)to harden their electrical distribution infrastructure to increase system reliability in the wake of the hurricanes experienced in FPL's service area. Hardened infrastructure generally consists of replacing existing utility poles with larger concrete poles that can withstand higher wind speeds. Converting overhead utilities underground is also considered an equivalent form of hardening. FPL's hardening plan would only harden the main feeder lines in the Village, but not harden any of the lateral radial infrastructure. lt is these laterals that serve most of the homes and business In the Village. Village Council agreed that hardened poles would have a negative impact on the Village's aesthetics. Considering those impacts along with IKimley)>Horn VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN the reliability benefits, the Village Council decided that a conversion of the overhead utilities to an underground location should be pursued, ln the fall of 2016 a feasibility study was prepared that discussed the conversion process in generalterms and provided a conceptual schedule and opinion of cost. After the feasibility study was received, and through numerous public meetings and discussions, the process moved fon¡rard to begin a master planning process. An Underground Utility Task Force (UUTF) comprised of citizens of the Village was formed and began to provide guidance and recommendations to the Village Council on the underground utility conversion, ln June of 2018, the Village Council approved a resolution to engage a financial consultant to begin working on an assessment methodology to figure out if that would be the best way to assess residents for these improvements. The assessment methodology report will identify several distinct, direct, and special benefits derived from an underground utility system consisting of improved safety, reliability, and aesthetics of these facilities wiihin ihe Viiiage. A brief description of each of these attributes follows: Safety: An underground utility system is generally safer than an overhead utility system because the electric and communication cables and equipment are less accessible to accidental contact with the public and the elements. For example, during windstorm events overhead facilities may be blown down, creating impacts to property and exposing the public to the risk of electric shock. Additionally, routine maintenance of landscaping may cause accidental contact with overhead powerlines causing a risk of electric shock, Reliabifity: Based on a report entitled Out of Sight, Out of Mind, An Updated Study on the Undergrounding of Overhead Power Lrnes by the Edison Electric lnstitute (2012), an underground utility system is generally more reliable than an overhead utility system because it is less susceptible to impacts from weather events, exposure to wildlife, and contact with vegetation. This is further supported by findings recently reporled to the Public Service Commission by FPL. They found their underground systems outperformed their overhead systems in average interruption cjuration and average interruption frequency by B0%. The fundamental design concepts of underground utility systems also create reliability benefits. For example, a typical neighborhood street in Key Biscayne is served by an overhead radial line connected to a 10 Example of Overhead Utilities in Key Biscayne ) ) ) ) ) ) ) ) ) ) ) feeder circuit that usually dead ends without connecting to another feeder circuit. With this type of design, if there is a fault on the radial line all customers connected to the line will be out of service until it is repaired. In an underground system, the line serving the street will be looped between two feeder connection points with an open point in the middle, generally at a transformer, lf a fault occurs, it will only affect a poñion of the looped system. Utility crews responding to the outage can isolate the problem area, restoring service to as much of the loop as possible while keeping the impacted area de-energized. Aesthetics: The Village of Key Biscayne maintains a high standard of visual aesthetics throughout the community, The Zoning and Planning Division and the Village Council are charged with protecting this visual image through a thorough review process for any construction and renovation projects within the Village. The relocation of overhead utilities to an underground location provides an opportunity to enhance the visual aesthetics of the Village and allows greater flexibility for architectural and landscape architectural improvements in areas that were previously restricted by overhead utilities, ln the Spring of 2ü8, Kimley-Horn and Associates, lnc. was selected by the Village to serve as the Engineering Consultant for the undergrounding conversion program. The initial task was the development of an overall master plan to provide a guide for the implementation of the program. Project Goals A driving force behind developing a master plan is to balance and manage potentially competing priorities such as cost, pro¡ect duration, traffic impacts, other capital improvement needs, etc., for this ambitious project, The goals and objectives of the master planning process are as follows: Collection of data related to existing utility infrastructure throughout the Village West Mclntyre Street between Glendridge Road and Woodcrest Road J KimleyDHorn 11 2,0 INTRODUCTION AND PROJECT GOALS VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Collection of data related to planned, major construction projects within the Village Development of design criteria to be followed throughout the duration of the undergrounding program Development of an implementation plan for new underground facilities to serve as a guide for the future detailed design phases ldentification of infrastructure projects that could be constructed concurrently with the undergrounding program to take advantage of restoration cost sharing Development of a sequencing and phasing plan that identifies both the phase area limits and a conceptual schedule of activities for each of those phases Development of a traffic management plan that coordinates the undergrounding activities with other known significant construction projects to reduce traffic impacts during the implementation process Development of a conceptual opinion of probable construction cost for the program Coordination with key project stakeholders to develop the master plan Assessment of the risks associated with the undergrounding program along with risk mitigation strategies Performance of public outreach to inform the community about the undergrounding program The following sections of this master plan will describe each one of these goals in greater detail along with our recommendations for implementation of the program. I ¡ I 12 A fountain view at Harbor Drive and W Mashta Drive 2.0 INTRODUCTION AND PROJECT GOALS a 1.l 'l,l .l .l .) ) .) -) 'l -) ') -).l ') ) ) ) ) ) ) ) ) ) -)J ) *) J J J \J J J J J J J J J 13KimleyDHorn G+r... B"F i h ter 3 EXISTING UTILITY SYSTEM OVERVIEW The Village of Key Biscayne is predominantly served with electric and communications services through a network of overhead wires mounted to wood or concrete poles. It is estimated there are approximately 16 pole-miles of overhead infrastructure within the Village limits. A pole-mile is defined as the linear distance in miles along a set of utility poles, regardless of how many wires, cables, or equipment are attached to those poles. This estimate is based primarily on: . information conveyed by FPL r maps that were obtained from FPL, AT&T, and Comcast . scaled measurements made from those maps . field observations Based on our knowledge of the Village and our field observations, Kimley-Horn is confident this is the most reliable estimate of total overhead infrastructure. The majority of poles observed in the Village support both electrical and communications infrastructure. There are a few poles that support only electrical infrastructure. The overhead utility infrastructure is often located in the right-of-way of the major Village roadways, in rear yard easements, and/or rear alleys between street blocks. The preference is to relocate these lines to the front street right-otway for the following reasons: The rear easement is not accessible by utility maintenance vehicles, which creates problems with wire and equipment installation and maintenance. Utility providers now require truck access to new equipment installations, so rear easemenValley installation will only be allowed if the equipment can be accessed by truck. The Village would like to abandon the rear easements in cases where no other utilities remain in the rear easement after the overhead to underground conversion. There is currently a combination of electric and communications in the rear easements Not all of these are present in every easement on every pole. Existing overhead transformers (left) and capacitor bank (right) t KimleyDHorn 15 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN r Dr 7.ooo (¡îvo- O( Cranwood Dr Greenwood Dr Redwood Ln Palmwood Ln Beeèhwood I 9¡ ô a, :CL Cìc 7 CL Þ D) ô ôv CL o¡¡:.6úr!t) vct Dr Dr w Legend O Utility Pole o Utility Pole Wth Light - FPL Underground - Overhead Utilities !o o Dr îV N 0 375 750 1,500wE o Feet S I 16 OVERHEAD/UNDERGROUND UTILITIES MAP 3,0 EXISTING UTILITY SYSTEM OVERVIEW Þs Q- N Ît r0 Êo! DrU hüa Lesend - N 0 475 950 w E+ S 1,900 Feet -FPL Underground - Overhead Util¡t¡es Direct Overhead lndirect Overhead Direct Underground -l-at rt lll VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN DIRECT/INDIRECT SERVICE MAP Kimley,)Horn 17 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN 3.2 Overhead lnfrastructure - Florida Power & Light There are some areas of complete underground electrical infrastructure within the Village, including feeder and primary duct banks, ln 1971 , significant underground infrastructure was installed to feed the east side of the Village. The resorl and condo buildings are fed via underground duct to vault rooms that house transformers and switches. ln more recent years Oape l-lorida was undergrounded with old technology, including below gratJe lranslorrrrer vaults. Tlrese vaults lruusetj llre ultj "uan" slyle transformers, More recently, the Harbor Point area (including W. Matheson Drive and Bay Lane)was convefted to underground. ln some cases, service drops are buried underground from the primary pole line to the home, however, there are still a significant number of aerial service drops to both residential and commercial buildings within the Village. The following table provides general information related to approximate quantities that make up the FPL power grid within the Village: 3.3 Overhead lnfrastructure - Comcast Comcast provides the Village with cable television and communications service NA throush overhead backbone fiber optic lines COMCAST on the west side and a mix of overhead and underground fiber optic lines on the east side, which then transition to coaxial service lines to the buildings, Based on maps provided by Comcast, meetings with Comcast representatives, and observations made by Kimley-Horn, the network originates outside north of the Village municipal limits and is fed by one main fiber optic cable that runs south on Crandon Boulevard through Virginia Key to the Village. This Electrical service is provided to the Village through a redundant subaqueous Biscayne Bay trarrsrnissir,ln lirre crossirrg frorn tlre rnainland beneath the Rickenbacl<er Causeway Bridge and the Mangrove Preserve that feeds an existing FPL substation on the nofth side of the Village. This substation feeds the Village distribulion grid comprised of feeder lines, radial primary taps, secondary services, and individual customer drops. As discussed in Section 3.'1, there are approximately 16 pole-miles of overhead electrical infrastructure. The grid is fed by seven main distribution cables originating from the substation. These main distribution cables effectively break the island up into seven service areas based on the total load capacity of each cable. The service areas are all interconnected through a series of switches that provide isolation in the event there is a problem with any specific cable. To better understand how power is delivered to individual homes and businesses, the following is a brief overview of the various components of the existing electrical system within the Village. Electrical power enters the Village from the substation through one of the seven main feeder cables described above. These distribution feeders then branch off to subsequent distribution feeder wires within each of the seven distribution service areas. Each service area is interconnected with aerial switches that provide system isolation and redundancy so all the feeder wires essentially work together to provide power to the Village. Many of the Village's feeder wires exist underground and head east on Ocean Lane Drive to feed the eastern neighborhoods and high-density resods and condos. Two others, one overhead and one underground, feed the single-family neighborhood on the west side of the Village. Branching from these feeder wires are the primary distribution wires. These wires are generally those wires that are located in the rear yard easements. The primary wires are connected to the overhead transformers that reduce the voltage to a level that is required by the customer. Secondary service cables then run from the transformer to a service drop, where the wires run down the poles and transition to an underground service, or run aerially, to the meter location. FPL Number of Utility Poles 701 Approx Length of Overhead Wire 16 miles 12 milesApprox Length of Underground Wire 343Number of Overhead Transformers Number of At-Grade Transformers 211 Number of Overhead Switches 41 Number of Capicator Banks 13 Table 3-1 - FPL Power System Information 18 ) line then jogs west and lurns south down the Fernwood Road corridor. From that corridor moving south il generally branches out to the east and the west to feed the various optical nodes. To better understand how cable television is delivered to individual homes and businesses, fhe following is a brief overview of the various components of the existing cable television and communicafi'ons sysfem fhaf exafs within the Village. Cable television and communications service enters the Village through the main fiber optic cable described above. This cable then branches off to subsequent fiber optic cables that serve individual fiber nodes providing service to many distinct service areas throughout the Village. The fiber optlc cables that serve these nodes exists on the main nodh-south arlerial road, such as Fernwood Road. The nodes provide a transition from fiber optic service to coaxial cable service. Branching from these nodes are the main coaxial distribution cables. The coaxial distribution cables are routed to numerous amplifiers, aerial taps and ground mounted pedestals that provide the individual coaxial services to the customers, The main coaxial distribution cables and individual service cables are generally those wires that are located in the rear yard easements although they are also co-located with the fiber optic cable on some of the overhead lines, The following table provides general approximate information related to Comcast's network within the Village based on maps provided by Comcast and observations made by Kimley-Horn: Length of Overhead Fiber Trunk Lines 3.0 EXISTING UTILITY SYSTEM OVERVIEW 3.4 Overhead lnfrastructure - AT&T AT&T provides the Village with telephone and communications service through a mix of overhead and underground backbone copper trunk lines that then transition to service lines to the building. AT&T does not keep records of the total length of cable they have installed in the Village. The system is very mature and mosi of it was constructed in the early 1960's, The network is fed by one main copper feed. Similar to Comcast, the one main feed is an underground duct bank that originates north of the Village's nofthern municipal limits. Through a series of manholes, this underground duct continues south along Crandon Boulevard with a secondary route down Fernwood Road. These ducts then converge on AT&T's main distribution building on Westwood Drive. lt then heads west on Westwood to feed the southern portion of the Village. From this corridor moving south lhen west, lines generally branch out east and west and then nodh and south to feed the Village. To better understand how telephone service is delivered to individualhomes and businesses, the following is a brief overview of the various components of the existing telephone and communications sysfem fhaf ex¡bfs within the Village. Telephone and communications service enters the Village through one main copper cables described above. This cable then branches off to subsequent copper cables that serve a network of Service Area lnterface (SAl) cabinets and Controlled Environment Vaults (CEV) that provide service to many distincl service areas throughout the Village. A significant por"tion of the main trunk line is already underground with radial splices occurring in manholes along the route. Many of the radials then transition to overhead locations to serve area customers. The copper cable main lines are routed to numerous aerial taps and ground mounled pedestals that serve as the tapping point for individual copper services to lhe customers. ÆþT f ) ) ) ) ) ) J ) ) ,) J J .J J .) J J J J J 9 miles Length of Overhead Coaxial Trunk Lines 16 miles Length of Underground Fiber Trunk Lines 2 miles Length of Underground CoaxialTrunk Lines 13 miles Number of Fiber Nodes 18 Number of Power Supplies 20 Table 3-2 - Comcast Network lnformation KimleyDHorn 19 ì, ,.r -Tú-. .ß;,w .1 ".,.tñìff f" ùb"1a È r: "] -, iìô"'.: !.,]- 1 V : l I I I l t ä : ÉIi ¡ 2t I apter 4 ì ) ) ) ) ) ) i DATA COLLECTION To develop a master plan that considers the unique aspects of the Village, it is important to gather information related to zoning and land use designations, generaltopography and soils, and the types of underground infrastructure that exist, as well as the plans for fulure infrastructure improvements in place at the time of this master planning effort. Each of these categories plays a role in how the overall program will be executed. The results of this data collection process are presented in the following sections. 4.1 Zoning and Land Use The Village consists of commercial, office, single-family residential, educational, recreational, multi-family residential, government, and vacant land uses. There are no industrial areas in the Village. The zoning map with the zoning designations for the Village are presented on the following pages. It is important to understand the relationship that the zoning districts have with the execution of the project. The needs and priorities of the commercial community are different than those found in the residential community. Therefore, the design must consider these differences so that specific requirements are clearly communicated to the construction team, An example would be the daily timing of impacts to private property. ln general, the residential property owner will likely desire impacts to their properly (such as the brief service disruption that occurs when swapping the electric and communications services from overhead to underground) be timed during the middle of the day when they are traditionally away. Conversely, the commercial property owner will likely desire that service disruptions occur after hours to avoid business impacts, 4.2 Topography and Soils lnformation related to topography and soils was collected throughout the Village from available online sources including the United States Department of Agriculture (USDA) Natural Resource Conservation Service (NRCS). The existing topography and so/s maps that were obtained are presented on the following pages after the Zoning Map. The soils map represents the general soil classes expected to be found in the Village. Soil classifications provide insight into drainage characteristics, expected distribution and extent, typical vegetation, and how coarse or fine the soil is in various locations. The primary purpose of gathering this information is to gain an understanding of the various soil types that could be encountered and how those soils may impact design and construction. For example, if a dense rock stratum exists in various locations around the Village, installation of underground utilities within this layer generally requires specialty excavation and boring equipment to achieve an acceptable rate of construction productivity. Having general knowledge of where the rock stratum may be encountered allows for proper planning related to number of construction crews and types of equipment required for the selected contractor to achieve the Village's schedule objectives. ,) ) ) ,l ) ) ) ) J KimleyDHorn 21 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN Lesend - MunicipalZoning Commercial - Low lntensity Grand Bay Hotel Resort lnstitutional lnterlm Or Government Use lsland Residential Key Colony Multi-Family High Density Residential Multi-Family Low Density Residential Multi-Family Medium Density Residential Ocean Club Office - Low lntensity Parkside Residential Private Club Public Recreation & Open Spaces Mllage Estate Village Residential lnstitutional ,$'*' ¡lId,I \3NE D¡ Oceao g{ qqoodcre st Ln I4^css Dr I Ðj€ o áoGô o 7 l¡ 'Tlo:t o;ô- 7À 'lrl I l Sbnest¿ Dr. Þ 0)i gr-ôl n o^-Q¿ 0a Iô d o.Io fol".'' ü Cì!):.útto ê¡av CL I ¡) áôv o- Dr Cranwood Dr o vê Hotel Resortto IoôI G¡ Greenwood Dr ( .v$ a 5r! €Jr W Heather Dr E Heather Redwood Ln W Palmwood Beechwood Dr Þq a)I s Þq Þooì 4)ò¡ Ë1 I vç cfi Lno ldt oW Matheson Dr 3oo ''ı rÉIA _t to oE rËL U Galen Dr{'W Mcintyre St Lô o (ú AJIo {IIlúI lSunset Crr W Enid Dr Sunrise Dr Harbor Cir i J ELóì W Enid Dr E Enid Dr Wood Dr .ô û 'Y¡!r/ H rì aÍ. 7 E N .€lub-Þr., rÞ0 o!) ar6 ol.v.-.%o"r. Westwood p" Rd {oooônô 6ì o ô 'li $ tn^ ,o^ é/6 '1o \ !o rú 0)go l Crrró <ÒVillage Residential Ocean ClubîøaÈ W Mashta Dr '¡ 5 G/iió. pil lsland Dr -SEaviêw Dr':. ' 'l+Q^. a"^ Multi-Family High Density ResidentialKnollwood Dr Çrapetree Dr N o +0 375 750 1,500 CaPe Florida Dr rw E Feet S Office - Low lntensity Key Colony Open Spaces Public Recreation & Parkside Residential Multi-Family Medium Density Residential Commercial - Low lntensity lsland Residential Village Estate 22 ZONING MAP 4.0 DATA COLLECTION i.l À ú E r Dr Land Use !Ìffi Single-Famil¡ High DensiÇ Beaches. CoasalWater (Bay Communications County Operated Parks Cultural Governmental/Public Administration Hospitals and Nursing Homes Houses ofWorship and Religious lnland water bodies Marina complexes Multi-Famil¡ High Density Mu lti-Family, Low-Density Municipal Operated Parks Nature Preserves and Protected Areas Office Building Private Drives Private Recreational Facilities Private Schools Public Schools Remaining BayWaters (Excluding Ocean) Remaining OceanWaters (Excluding Bay) Sales and Services Shopping Centers (Regional and Community) Single-Famil¡ Low-Density Single-Family, Med.-Density Street right-of-way and ut¡lity easements i -l Streets and Roads Transi ent- Res identi al (HoteLMotel) Two-Family (Duplexes) . ,. Vacant Government' ' owned or controtled. ¡ ¿ e Yacant, Non- Protected,r t' Privately-owned [-__lWater Supply Plants 0 4V,5 950 lr,900 Fæe't S VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN LAND USE MAP KimleyDHorn 23 Leqend - ¡¡-e -0I ls¡30 Il Il6ffit3l J2 I lTtf 32 13 Il8E33 14 I lel-34 Is ¡20n3s I_I -7 f22 18 I23 re -24I r0 I2s Ill 126 -t2 J27 Ir3 I28 I 14 fze N w E 0 475 950 F,eet S 4. ': I VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN 24 TOPOGRAPHIC MAP \\fÈ 4.0 DATA COLLECTION Beaches StAugustine sand gl L o¡Ll!I 7 Lesend - Soils ; rBeaches , Canaveral Sand ; 'Kesson muck, tidal rSt. Augustine sand Urban Land Waters of theAtlantic Ocean oc&î \3ne Dr ."ooo' ^'¡' "tt""'¡oodcrest Ln Ió^"r, D" 1- Þ 3t o I oôôao ô 7o. 'floI {o ovo Sonesta Dr o^'aè o Io rd{]g o C.o Þ¡ úúo P a .Ú> Ð9ôÐ ôã'{o1""' Cranwood Dr Cl vo- {o to ,vs 0) €(! dJ ç Greenwood Dr W Heatrer Dr 7 CL nctUrban Land€t füI E Heather Dr I Redwood Ln ús nt ú Cir TurtleWa,ust ot v<\ c¡\ W Palmwood Ln c øII-dì Þc Þ 0 Waters of the Atlantic Ocean Beechwood Dr Þooì a) Òo!q ,*wv¡-g Canaveral Sand \^/ Matheson Dr a) W l,,tcintyre St -ë!oo 3 ü(É t Galen Dr q*"W Mcintyre St !o ! ı ! (!L U o l!q)g o to¡Ir!¡ Sunset C¡¡ Harbor Cir W Enid Dr W Enid Dr Sunrise DrcJ E ! (ÉÌ W Enid Dr E Enid Dr E Wood Dr soHaîó o $ ô It {oo+. oô ¿t G¿ -o oe <Ò {ooêô o N club Dr Yu.'9o"," \ /estvvood rÞ ô oa o tOo 4)-g rü E(! È¡ Rd Lô l! {J o t Io ,o" fo (a(e V¡ua Þr MasYt@ Dr W Mashta Dr Lfl 0) l!J s Club ¡ò oç lsland Dr +"u*'i::. to^ $u^. 1o Q{ ob.o rnô$Çrapetree Dr o^ Îv ¡7¿s4à o N+oì- CaPe Florida Dr 0 375 750 1,500ìù/E Feet S Kesson muck, tidal VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN SOILS MAP Kimley>)Horn 25 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN A review of the soils maps reveal that the Village of Key Biscayne is underlain by two distinct soil classifications: Canaveral Sand Complex Urban Land Complex Urban Land Complex is not a soil type, but rather an area that is unable to be accurately classified into a soll type due to the amount of existing development. This leaves Canaveral Sand as the only distinct type of soil recorded in the Village. The Canaveral series is a deep, poorly- to moderately-drained soilwith sand and shell fragments found throughout. The soil can be found along the coast on low dune like ridges (National Cooperative Soil Survey, 2A14) On the island, the Canaveral series is found in a few pockets near the center of the Village. This soil depicts marine environments with sand and shell deposits found throughout. Major rock material is not identified in the Village and during conduit construction this is inrportant for employing the proper machinery and methods. Because the classification of soils identified by NRCS maps for the Village is general in nature, we recommend that soil testing be conducted throughout the phase areas during design to better define the local soil characteristics. 4.3 Existing Utility lnfrastructure and Future lnfrastructure Planned lmprovements To develop a master plan for this project, it is important to understand the existing ulility infrastructure that will remain in service during the implementation process and remain after the completion of the program. lt is also important to identify other significant construction projects that may occur during the implementation phase of the program so that work can practically be coordinated, lf these projects are identified ahead of time, their impacts can be limited to the extent possible. Kimley-Horn coordinated with the stakeholders listed below to obtain readily available information regarding the existing utility infrastructure within or near Village limits: Village of Key Biscayne Miami-Dade County Miami-Dade Water and Sewer Department AmeriGas American Traffic Solutions Hotwire Communications Florida Power & Lrght (l-PL) AT&T Comcast A description of the type of data collected from each of these stakeholders, as well as how it impacts the undergrounding program, follows below. 4.3.1 Village of Key Biscayne The Village of Key Biscayne provided atlas level data of their infrastructure to Kimley-Horn for review. The Village owns and maintains the following underground infrastructure that will need to remain after the completion of the program and remain in service during the implementation of the program: Stormwater collection and transmission Electrical street lighting The consultant team coordinated with representatives from the Village of Key Biscayne Manager's office, as well as Public Works regarding proposed infrastructure projects planned throughout the lsland. The Village provided project information for its proposed Capital lmprovements Program (ClP). Based on information provided, there are proposed projects throughout the Village. These projects can be generally categorized as the following types: . Drainageimprovements . Stormwater pump station improvements . Street lighting improvements . Roadway improvements . Landscapeimprovements . Recreationalprojects ¡ I 26 4.0 DATA COLLECTION Lesend - or Plz I(! o O A Traffìc Calming Landscape I mprovements Light lmprovements (2018 Project) Safe Routes to School lmprovements (2019 Project) Traffìc Calming Streetscape LandscapeArea lmpacted Roads Stormwater lmprovements (Prolected 2020 Start for Tier 2 lmprovements) I a AA ffi.ai a ói $P1""- I O ii {iIó.ess Dr c oa ID1Ê AA Sonesta Þr Ct\ {$fto o fi!):.66o 9la I 0¡ v CL Þê Ða 9.ô o oôo ÈCranwoodCl 7o-I Greenwood Dr v CL o !oo¡ ãÈ TurtleWalk v$ o"ì g å,u W Matheson Dro Beechwood Dr 0{ Gr"nd 9d W McÌr¡-,tyre It Galen Dr O qç t3Il!¡ I Cir o il h.,ou---JDrf, o Iô 0).¡ra 9 Rd Lô (t q, uo Dr eht6 <ô <ô Masng Dr a s crrb '. ¡'¿ *oa sEavÉ.ìv Dr ¡ lsland Dr t";" oô^ o{ Knollwooò %roo % Çrapetree Dr a Q{+a,^... o o ı^"9.ss$N O oóaCaPe Florida Dr0 450 900 1,800 a V/E a Feet o S I VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN CAPTTAL PROJECTS MAP Kimley>)Horn 27 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN The capital improvements projects (ClP) projects are funded through generalfunds incorporated into the annual budget. The recreational projects including field improvements and sports lighting will move forward independently of the Village's proposed utility undergrounding plan. Street light improvements are ongoing but a large portion of the existing lighting will be affected by the undergrounding and will be incorporated into the u nderg roundi ng pro¡ect. Roadway lm provements l ncl ucle lraffic ca l m i nO measures and sidewalks may also be included in the undergrounding program. ln recent years the Village hired a consultant to prepare a master plan for the implementation of the Village's drainage inrprovements, wlrich includes upgrades to stormwater pump stations and gravity drainage wells. Because the improvements proposed by this drainage master plan are widespread, Kimley-Horn has been asked to incorporate these improvements into the undergrounding master plan to realize efficiencies in constructing them at the same time. Some of the benefits of performing projects concurrently include: increased scheduling coordination, reduction of long term traffic impacts, and cost savings resulting from shared restoration costs. The stormwater master plan breaks down improvements into two tiers. Tier'1 includes implementation of backflow preventers on stormwater outfalls to reduce the tidal effects on low lying areas. This portion of the stormwater master plan has been completed. Tier 2 is a much more extensive undertaking lhat includes a $24-million plan of improvements. Although the Village has setup a stormwater enterprise to pay for drainage improvements, the Village currently does not have the budget to incorporate all the improvements identified in this stormwater master plan. The Village has recently hired a financial consultant to identify and establish the necessary fees to pay for these improvements. To spread the cost of these improvements over the long term, the stormwater master plan establishes a 1O-year phased completion schedule. Although this plan extends beyond the estimated timeframe of the underground conversion program, the Village may elect to accelerate these improvements to share costs and avoid extending impacts io the Village residents. A map of the drainage basin areas anticipated to receive improvements has been created to graphically describe the improvement locations and anticipated construction years. This map can be seen on the following page. 4.3.3 Miami-Dade County Public Works Mianri-Dade County's consultant, High Tech Locatirrg, provided allas level data for underground street light and traffic signal systems present within the Village. Although Crandon Boulevard is listed as a state highway, the County manages and maintains street lights arrd traffic sigrrals on Crandon Boulevard within the Village. The County also maintains school flashers on Harbor Drive for St. Agnes School. The County currently has no capital projects planned for Crandon Boulevard. 4.3.4 Miami-Dade Water and Sewer Department Mianri-Dade Courrty Water and Sewer Department provided atlas level GIS data for the water distribution and sanitary sewer systems within tlre Village, The County provides the Village with drinking water and sanitary sewer services under an inter-local agreement. Provided with the GIS data was information relaied to the materialtype of individual segments of the water main system. This will help identify opportunities to replace watermains that have exceeded their useful life during the implementation of the undergrounding program so work can be properly coordinated. The County does not currently have any organized program for the systematic replacement of these aged watermains, so replacement is expected to be performed on an oppodunistic basis. The County has no plans for targeted long term watermain replacement that could be accelerated to be accomplished during the undergrounding program, However, Village staff expressed interest in replacing all existing asbestos cement (AC)water main pipe. Kimley-Horn will identify these segments to be considered for inclusion in the undergrounding program. It is important to note that the County's data included water mains that were identified as "unknown" material. During the design phase, in-field investigation will take place to ensure these water mains are appropriately categorized and included in ihe scope of improvements as necessary. ¡ 28 4.0 DATA COLLECTION Leqend - fl]ProblemAreas (EAC) Phase I Phase 2 i.l'.'i Phase 3 : Phase4 it' I l . -r-- -j MqÞ$€ri.. DÉ N'+0 375 750 1,500 E Feet s VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN STORMWATER MASTER PLAN - PROBLEM AREA MAP KimleyDHorn 29 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN Buttonwood W Heathe =5 c, (tÈ E Redwood W Palmwood ooì E?v Beechwoodc rBay G¡and Dr Galeno Mcintyre St W Enid i o¡ I r- _$p¡>o.. i . Sunrise o cl E(nI Cu WoodEnid Lesend -- Non-Asbestos Pipe Material, Diameter -Asbestos Cement, 12" . ,,-' = Asbestos Cement, I 0" -Asbestos Cemeng 8" -Asbestos Cemeng 6" -Asbestos Cement,4" Asbestos Cement,3" -Asbestos Cement,2" -ootLN fo. Þ 9¡a Ê. W Matheson Dr Su nset Harbor Dr N Club Io s I rËoo J .o ã U ll c¡ o Dr Mashta Dr Club Rd SEaview Dr Dr Knollwood Dr N CaPe Florida+0 450 900 1,800 w E Feet S I Cape Florida Park Blvd 30 WATER LINESASBESTOS CEMENT PIPE MAP 4.0 DATA COLLECTION cr Legend cIo lz -\lt/¿fs¡ li¡ss Pipe Material Diameter Unknown, 12" -Unknown, 10" -UnknOWn, 8" e Unknown, 6" -ll¡ft¡g1¡y¡, l" Lô Su E ID ¡¡ sô c nl tU quó ç rl(nol N ôÞ ÊGaPerElor'id w +E 0 375 750 1,500 Feet S I VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN WATER LINES UNKNOWN MATERIAL PIPE MAP Kimley>)Horn 31 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN 4.3.5 AmeriGas AmeriGas is a private service provider of propane, also known as liquified petroleum gas (LP-gas). ln a residential capacity, propane is used to fuel home appliances including furnaces, water heaters, air conditioners, outdoor grills, range tops, and backup generators among others. AmeriGas provided Kimley-Horn with a database of lheir customers within the Village. This information will not significantly influence the master plan, but will be useful during design and construction to avoid danraging underground tanks while trenching on private property to service points. 4.3.6 American Traffic Solutions American Traffic Solutions (ATS) is a private service provider of smaft transportation solutions. Within the Village ATS provides red light cameras along Crandon Boulevard at Harbor Drive, Key Colony, and W. Mclntyre Street. ATS provided Kimley-Horn with record drawings and informaiion related to their systems. This information will not significantly influence the master plan but will be critical during design and construction to avoid dar-naging their lacilities. 4.3.7 Hotwire Communications Hotwire provided Kimley-Horn with atlas level data of the cable television/ communications distribution system within the Village, as well as detailed record drawings and information related to their system, Hotwire's existing infrastructure is entirely underground, They are also currently installing additional conduit within the Village to serve several new customers. Those record drawings are forthcoming, Maps of Hotwire's existing network are t-tot itrcluded in tlris t'¡-raste¡ plar'r docurrrent to protect tlre confitjerrtiality ol this information. 4.3.8 Florida Power & Light FPL allowed Kimley-Horn to view atlas level data of the Village's electrical distribution system. Because much of the east side of the Village is already underground, FPL was able to provide record drawings of that underground infrastructure. Maps of FPL's existing electrical system are not included in this master plan document to protect the confidenliality of this intormation. 1 tF i ill -,nllìhIìlr 32 Existing multifamily rear service FPL transformer in Key Biscayne 4.3.9 AT&T AT&ï provided Kimley-Horn with atlas level data of the telephone/ communications distribution system within the Village, as well as detailed record drawings and information related to their system. Much of the underground trunk line system will need to remain in service during the implementation of the program and will need to remain after completion of the program. Maps of AT&T's existing network are not included in this master plan document to protect the confidentiality of this information. 4,3.10 Comcast Comcast provided Kimley-Horn with atlas level data of the cable television/ communications distribution system within the Village. Detailed record drawings and information related to their system was not available according to Comcast. Maps of Comcast's existing network are not included in this master plan document to protect the confidentiality of this information. 4.0 DATA COLLECTION Existing Comcast aerial node Kimley>)Horn Existing Comcast aerial node power supply 33 I t; t, .t '1 ¡l-I ) ) ) ) ) ) ) ) ) ) ) apter 5 DESIGN DESIG TN CRITERIA AND CONCEPTUAI- DESCR¡PTION ) ) ) ) ) ) ) ) .l Through a series of meetings with the Village, FPL, AT&I Comcast, and other stakeholder utilities, Kimley-Horn has assembled general guidelines for design criteria to be used throughout the implementation of the undergrounding program. These guidelines are not intended to be all inclusive, or the only criteria to be followed during the design and construction of the overhead to underground conversion improvements, They are intended as guidance only for the design of the physical location and placement of conduit and equipment and do not govern the detailed electrical or communications network design that will be performed by FPL, AT&T, and Comcast. This criterion is intended to be used as guidelines during the implementation of the program so consistency in design and construction can be realized over the life of the program. The criteria are based on the assumption that all of the overhead utilities in the Village will be converted to an underground location. They do not contain any criteria for a hybrid system conversion that consists of padially overhead and partially underground distribution components, A summary of this criteria and conceptual design follows below. 5,1 General The following codes and standards, as applicable, shall govern the design of the improvements: . Village of Key Biscayne Code of Ordinances . Standards Applicable to Public Right-of-Ways and Easements Within the Village of Key Biscayne . Miami-Dade County Code of Ordinances . Florida Department of Transporlation Manual of Uniform Minimum Standards for Design, Construction and Maintenance for Streets and Highways (commonly known as the "Florida Greenbook"), latest edition . Florida Deparlment of Transportation Design Standards . Florida Department of Tiansportation Standard Specifications for Road and Bridge Construction, latest edition , Florida Building Code, latest edition . National Electric Code (NEC), latest edition . FPL Distribution System Standards, latest edition . AT&T and Comcast System Standards, as applicable There are some unique characteristics to the Village that also influence the design criteria for the program. These are described in greater detail in the following section, Development of the Village began in the early '1800s, however, it wasn't until the late 1940's where we start seeing official plats recorded and right-ofway widths start to develop, Typical of development during this era is the prevalent use of narrow right-oËways for public streets and utilities. This creates unique issues for the undergrounding program. Generally, it is desirable to install underground infrastructure on a roadside shoulder versus under pavement. This allows for a simplified installation at a lower cost than utilities installed under pavement. While some areas of the Village have wide right-of-way with plenty of shoulder area to work in, some areas of the Village are fully developed in that parallel parking, curb, and streetscape have been installed that effectively eliminates any swale or shoulder area. ln areas that do have a small amount of roadside shoulder, J Kimley)>Horn 35 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN this area in some cases has been completely claimed by the adjacent propefty owners with the inslallation of extensive landscaping, and other such improvements. While the Village could legally reclaim this right-of- way for their use, this is not considered an option as it would negatively alter the visual aesthetic and character of the Village, not to mention create tension between property owners and the Village, Therefore, installation of new utility facilities nlusl lre irr l"lre puLrliu riglr[-ul"-way wlterr feasit-rle, untJer pavement, or in utility easement areas, Typical residential properties not located directly on either the ocean or lntracoastalWateru,ray generally have a 5-foot wide platted utility easement in the rear or side of their property. Mashta lsland and Cape Florida have 6-foot-wide platted easements. This easement is generally adjacent to an identically sized easement on the neighboring property thereby creating an effectively 1O-foot and 12-foot-wide easement lt is within this easement where rearyard overhead utilities currently reside. Unfortunately, this rear yard easement cannot be used for the new underground electrical and communications facilities because tlre itrdividual uLiliLy owrlers carrnr-rt properly access or maintain infrastructure installed in these locations. For these facilities to be converted underground, they must be relocated to a front street location in the right-of-way or in an easement accessible directly from the right-of-way, This does provide a benefit to the landowner with a 5 or 6-foot easement on the rear or side of their property. If that easement is no longer needed by any utilities after the conversion process is complete, it may be abandoned and the properly owner will gain back that porlion of land with no encumbrances that the easement once held. 5,2 Village of Key Biscayne As discussed in Section 4 of this master plan, the Village is responsible for the operation and maintenance of various types of infrastructure within the Village. The design criteria presented below shall govern improvements related specifically to undergrounding. Any impacts or improvements to other infrastructure shall be governed by the design criteria already established lor those elements by the Village of Key Biscayne. A summary of recommended specific undergrounding design criteria as it relates to Village owned and operated infrastructure is summarized below. 5.2.1 Village Owned Conduit . Conduit to be installed for Village purposes should be HDPE or PVC suitable for installation by either Horizontal Directional Drilling (HDD) or open cut methods. , To achieve cost savings related to joint trenching, conduit routes fnr ftfure commr¡nications shoLrld follow the ror-rtes of the conduit being installed as part of the undergrounding program to the greatest extent practical. ' Place pullboxes at junctions and at intervals sufficient to allow pulling future cabling. . Locate pullboxes in the road right-of-way, but off the roadway travel surface to the greatest extent practical. . Pullboxes should be provided with electronic markers and/or have GPS data recorded for future locating purposes. 5.2.2 Village Street l-ighting The undergrounding project will impact a significant number of street lights within the Village. The impacted street lights consist of those currently mounted to overhead utility poles. When these poles are removed, the street lights will be taken down with them. For this reason, these impacted street lights will need to be replaced. The Village is actively implementing a Village wide lighting program. New street lights have already been installed on Harbor Drive and W. Mashta Drive. Contracts are currently being finalized with a contractor for installation of new street lighting down Fernwood Road. The approved lighting fixtures within the west single-family neighborhood are a GE LED post top light identified as Avery Streetdreams. Olher areas of the Village including the Crandon corridor, the multi-family neighborhood between Galen and E. Enid, and Sonesta Drive use different distinct lighting. As we move into a detailed design phase, specific types of lighting will be determined for each area. As shown on the impacted street lighting map on page 38, some areas have no existing street lights or the spacing of the impacted lights is not generally regular. This indicates the lighting levels within a particular area are non-existent, may be less than a desired illumination level, or may 36 I Existing FPL-owned street lights not be uniform, During the design of each pro1ect phase, we recommend discussions with the Village to determine if any additional street lighting is desired to be installed concurrently with the undergrounding project. It is estimated that 1 I B street lights will be impacted by this program and will need to be replaced. A map af their locations is found on the following page.Forly (a0) street lights are currently being installed by the Village as parl of their separate lighting program. lt is also estimated that a minimum of 41 street lights would be required in the areas of the Village currently without lighting. A photometric plan would be required to confirm that quantity. 5.0 DESIGN CRITERIA AND CONCEPTUAL DESIGN DESCRIPTION Existing Village-owned custom street light Additionally, the Village may consider installing FPL standard lighting as a cost-savings measure. FPL currently administers a street lighting program where they willfurnish and install street lighting. For the standard lighting options, there is a capital cost of approximately $1,200 per pole for the installation, but the Village would be required to enter into an FPL Lighting Agreement that would require the Village to pay a monthly maintenance fee and electrical service charges to FPL. A significant drawback to the FPL standard lighting options is they do not have the same aesthetics as the Village standard lighting and would need approval to be installed anywhere in the Village. A premium lighting KimleyDHorn 37 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN Legend O lmpacted Street Lights I Proposed Street Lights olpooo I o.oL^l!(, T O."Ê(' l2ne Dr I OC o .oI "." """t I I U'¡oodcræst Ln,- (:r ?^urr6, tå Ç¡.n*ooa Or$ 7.ooÈ år ,À o Sonesta Dr \c\ ¡ooil r.¡P' r rù"Tfi' IRu¿foo¿ l-n I o È¡:. rEot¡ {Þ ÈE ã' 0I Iô Ê(t o o r Greenwood Dr ¡ Cìrå Ô) rå o'\o.ôt{!¡w o rùe6oeeo6 o co c CO vor, 3. .e gea?ter D! v CL I ,vY Dr ao.9Jg tlt Cir TurtleWalk ¡ù-È WfPalmwood Ln ø Èt Beee.lwood¡,Dr å ú Sc CÞ{r o ! ã 0vo <fì g)¡ s, -È(o oì 0) ö0 .p CC o €tt 0).t(, wv W Matheson Dr c Grandoo q& Galen Dr !o EîtoUo 3¡r rü¿ Sgnseîer e W Enido Har6àr Cir u O C CHar¿o f' I D¡. Sunrise Dr C :o o C t, rÉ! U oc , o E E Enid Dr Wood Dr ro N ctub Dr cg ô€-o s 0).v.J @oÞ o Lo (t(, Uo C c U QW M8hta Df o îo o o o o tâ'o o (ate V¡tt" Þr, M.rtn@Db o C OC Io o.Y fitJ S Club Rðoo þ: (^aÙ' €t"' QL """^"-o ^t*Qc c c o lsland Dr +9^-a*Knollwood Dr Grapetree Dr N "%o +Þr- CaPe Florida Dr 0 375 750 1,500 a)w E Feet s - 38 IMPACTED STREET LIGHT MAP package is also available from FPL, but these increase the monthly fixture fees. The FPL premium lights are more decoralive and are somewhat similar to the Village standard street lights, but would still require Village approval. Kimley-Horn was able to the review the Village's current RFP submittal to perform an analysis of the costs related to the FPL premium lighting versus the Village owned lighting. Kimley-Horn found there is a $1,200 per pole initial capital costs to installthe FPL premium lighting, as well as a monthly cost per pole that includes maintenance and energy usage and fixture, pole, and wire fees. Estimates received from FPL for poles and fixtures that resemble the Village's custom poles are approximately $SZ per pole per month. With an approximate installation cost for custom lights around $8,600 per pole (not including maintenance and energy costs), it would take almost 12 years of FPL monthly fees to reach the initial capital cost of the custom pole. 5.2.3 Equipment Placement . Equipment shall be located to meet the clear zone requirements contained in lhe Florida Depadment of Transportation Design Manual, Chapter 215, andlhe Florida Greenbook, as applicable ' Within urban curb or curb and gutter roadway corridors, equipment shall be placed according to the Florida Depafiment of Transportation P/ans Preparation Manual, Volume 1 , Chapter 4,2.4 - Lateral Offsets. Transportation Design for Livable Communities criteria shall be applied for applicable roadway corridors. . This criterion is applicable for both Village and County controlled right-of-way. 2.4 Right-of-Way Restoration . Right-of-way restoration shall meet current Zoning and Land Development Regulations applicable to Public Right-of-Way and Easements within ihe Village of Key Biscayne for roadway pavements, drainage, curbing, and sidewalks. ' Sanitary sewer restoration, where impacted, shall meet current Standards Applicable to Public Right-otWay and Easements Within the Village of Key Biscayne, 5.0 DESIGN CRITERIA AND CONCEPTUAL DESIGN DESCRIPTION Where no standard exists, Miami-Dade County and FDOT standard specifications shall be used to the greatest extent applicable. Landscaping outside of easements and right-of-way impacted by any improvements shall be restored to an equal or better condition than existed prior to commencement of the work, 5,2.5 Village Policy Recommendations Easement acquisition will be required in every phase during the implementation of this program. This process can be challenging and time consuming. lt is recommended that the Village as a matter of policy consider requiring the dedication of a front and/or side yard easement be dedicated for utility use on any property that wishes to obtain a building permit for a significant renovation or new build pro.¡ect. Access to such easements will help facilitate lhe program during future phases. For properties that are undergoing exlensive upgrades or renovations, il is recommended that electric and communications conduits be installed to a front street location for future use by the undergrounding program to connect the home/business to the new underground infrastructure when it is installed. This will eliminate the need for trenching or boring from the front street to the meter location in the future. 5.3 Franchise Utilities Kimley-Horn held design workshops with FPL, AT&T, and Comcast staff for the purposes of reviewing design requirements for the proposed underground infrastructure, The following summaries describe the results of those design workshops. Because FPL, AT&T, and Comcast consider the locations of their significant electrical and communications infrastructure elements confidential, any maps or schematics that were developed as a result of this process are not contained within this master plan document. 5.3.1 Florida Power & Light The layout and design of overhead electric infrastructure is different in nature than underground electric infrastructure. The Village's current overhead system can be generally described as a series oi main overhead feeder lines with radial distribution lines that are connected to 5 KimleyDHorn 39 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN the feeder lines with fused switches, The feeder lines are interconnected to provide redundancy, but generally the radial distribution lines are not interconnected. Conversely, an underground system will have interconnected feeder lines and distribution lines. This enhances reliability of the system as it provides multiple feed sources as opposed to a radial system that provides only one electric feed source. ln general, there is very little choice in the type of equipment that is installed when pedorming an underground conversion project. All of the equipment and materials that are installed are provided by FPL so they are consistent with their electrical distribution standards. This is done in an effort to maintain system consistency and cost efficiency in both installation and maintenance. That being the case, there are now two equipment aspects of the design where the municipality can make a preference decision. Two types of switch cabinets can be provided by FPL based on preference or circumstance; the standard .PME' switch cabinet or the "Vista" switch cabinet. The standard PME switch cabinet is the cabinet that is deployed most commonly in the FPL electrical distribution system. The Vista cabinet has a slightly smaller footprint, is shorler, and only requires eight feet of clearance on one side of the cabinet and 3 feet on ihe sides and rear rather than all sides like the standard switch. This offers some unique advantages when the equipment is required to be placed in tight spaces or there is an aesthetic requirement that dictates the smaller cabinel. The Vista cabinet is also hermetically sealed to prevent water intrusion. A significant drawback of the Vista switch cabinet is that it costs approximately $60,000 more than a standard switch cabinet. For this reason, our opinion of cost has separated the added cost of installing Vista cabinets so the Village can contemplate the level of investment that makes sense, ln reality, due to space constraints, some Vista cabinets may be required regardless of the desire for resiliency. Two types of concrete pads for transformers can also be provided by FPL based on preference. One of the major concerns of the Village is the consistent flooding of low lying areas. When transformers are flooded, FPL cannot service them until the water recedes. FPL now offers the choice of the standard 6" concrete transformer pad, two 6" pads stacked, or a24" concrete pad, which will raise the translormer an additional '18" above grade. With concerns about sea level rise and potential for storm surge from hurricanes, the additional cost of concrete for the taller pads may be warranted in low lying areas. FPL will perform the electrical design for the program followed by Kimley-Horn developing the supplemental conduit plans to aid the Village's contractor in installing the conduit for the project. FPL has communicated the following general guidelines related to the design of the improvements. All FPL electric infrastruciure shall be designed and consiructed in accordance with the FPL Distribution System Standards, latest edition. All electrical design decisions will ultimately be made and/ar approved by FPL, ln general, overhead electrical infrastructure localed in rear easements will be relocated to a front street location. There is an exception, such as the multifamily buildings on Galen, Sunrise, and E Enid Drives, where the buildings are served from existing transformers at the rear of the building. As long as FPL has access { I I I 40 FPL PME switch cabinet FPL Vista switch cabinet oÀIE ïx. OR SWTCH SEÉ NOIES IA & 18 'lA ¿, 1B SEE NOÎE 2 BUSHES FRoM IRANSFORMERS lS Mscs #ı48-560-101. CONCRETE 5. PLAN cF APPROVEOI RJ. SATESKY irRE---ıiñFiOn¡srw¡nO¡-mi¡æn¡¡ı-M OPRTOilS swCES oRlolMÎon. C.lU FOR OH & UG DISTRIBIIflON SYSTEM SÎANDARDS DRAtÌ¡l Bl: Pîl NO SCáLE 18. PADMOUNTED TRANSFORMERS REQUIRE 3' MIN. CLEARANCE ON EACH SIDE A¡,lD BAOK AND 8' CLEARANCE IN THE FRONT, 2. FRONT ACCESS CLEAMNCE SHOULD 8E 8' FOR ALL EOUIPMENT. ,,ET.ECTRIC EQUIPMENÍ _ KEEP OIJT. DECAL THAT SHOWS THE MINIMUM SEPARÀ'IION DISIANCES FOR NOTES: 1À PADMOUNTED SI^TTCHES AND CAPACIÎOR BANKS REQUIRE 8, MIN. CLÊARANCE ON ALL SIDES. t{oT sTtcK OPERATION PL I FPL transformer clearance requirements to the transformers and conduit via private drives, these overhead lines may be undergrounded within existing easements and transformers may remain at the rear of the buildings. The Village is served by two overhead and five underground separate main feeders from ihe substation that serve specific areas of the Village based on electrical load and capacity of the main feeder. Main feeders will not be replaced or upgraded so service areas within ihe Village will remain the same. All electrical equipment and materials to be owned and maintained by FPL at the conclusion of the project and shall be provided by FPL. Contractors installing FPL infrastructure must be pre-approved by FPL. Switch cabinets will be required at each of the two main overhead feeder landing poinis in the Village. Switch cabinets will also be required to separate underground distribulion transformer loops. Forty-one overhead switches exist today. FPL has stated that number will be reduced. To the extent practical, standard switch cabinets are to be used, Vista style switch cabinets can be used as circumstances may require or as requested by the Village as previously noted. 5.0 DESIGN CRITERIA AND CONCEPTUAL DESIGN DESCRIPTION Existing three-phase pad-mounted transformer in Key Biscayne At least one capacitor bank will be required within the service area of each feeder. This yields a iotal of seven The capacitor bank must be located within i 00 feet of a switch cabinet. FPL prefers 10'x10' easements for single phase transformers, Open Delta Bank Transformers require a '13'x10' easement. Three- phase transformers require anywhere from 10'x10' lo 2O'x2O' depending on the load. FPL prefers 24'x24'easements for switch cabinets and capacitor banks. Underground feeder splice boxes require a 7'x22' easement, Underground handhole easements can vary between 5'x5' and 5'x20' depending on the size of the handhole and configuration of the undergrounding wiring. Actual easement dimensions and configurations may vary depending on the specific situation, field conditions, and types of equipment to be installed. Easements must be located adjacent to and accessed from the public right-of-way. I Kimley))Horn 41 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Screeneri FPI transformer Electrical equipment requires 3 feet of clear area on the sides and rear of the equipment and B feet in the front of the equipment for access and maintenance. Standard switch cabinets and capacitors require I feet of clearance on all sides of the cabinet. Existing handholes connected to existing electrical services to the building/facility may be reused if they are located near the front street. Conductor may need to be replaced depending on the load. Existing handholes located at the rear of the properly will not be allowed to be reused if the service is being converted from the rear to the front of the lot. This is for safety, maintenance, and to prevent unauthorized connections. New conduit will be installed between the transformer and the facility service entrance or existing handhole, as applicable, to contain the service or secondary service cable. Facility service entrances shall meet current NEC standards for connection to the new underground system. Overhead facility services will be converted to an underground location. This may require replacement of the service entrance if the meter can cannot accommodate new underground conductors. Overhead weather heads will be abandoned in place. a ¡Electrical equipment shall be located so it can be accessed easily by truck. Transformers will be located based on electrical loading requirenrents, For exarrrple, a horl.re willr a large electrical service may need a single dedicated transformer, Conversely, homes with smaller electrical services may be able to share a single transformer Transformers should be located on one side of the street to the extent practical. Transformers shall be the "low profile" style to the extent practical. ln certain situations, such as three phase services and large services requiring service greater than 75kVA, a "regular" style transformer shall be used, Concrete transformer pads shall be 6" in height unless lhe 24" pads are otherwise requested by the Village or circumstances require their use. To plan for the improvements required to implement the underground conversion of electric utilities in the Village, Kimley-Horn met with FPL on numerous occasions to discuss proposed routing for new underground feeders, main feeder switches, and capacitors. The existing subaqueous transmission line under Biscayne Bay from the mainland to the eubstation will remain as is. The existing underground feeders leaving the substation into the Village will be reused and their respective service areas will remain generally the same based on electrical loading demands. To minimize the cost to transition back to the existing overhead system and minimize disruption to the residents, phase boundaries were determined at Iocations that would encompass the entirety of the adjacent right-of-way and only impact residents through one phase of construction. Additionally, phase lines were selected where existing poles are located or where temporary transition poles could be minimized and set to allow for clean transltions between phases. 42 f Existing AT&T cabinets and electrical service in Key Biscayne Upgrades will be built into the design that include new feeder ties and looping that will provide enhanced reliability to the Village. Kimley-Horn's recommendation to the Village is to allow these upgrades to be constructed, but at no additional cost to the Village since Key Biscayne should not subsidize system improvements desired by FPL, Costs related to upgrades should be clearly identified during the development of the Binding Cost Estimates for each phase so these costs can be credited along with the applicable Government Adjustment Factor (GAÐ Waiver. 5.0 DESIGN CRITERIA AND CONCEPTUAL DESIGN DESCRIPTION 5.3.2 AT&T AT&T provides communications service to the Village through a network of copper cables. Much of the trunk line already exists in an underground location to their distribution center on Westwood Drive. Distribution of service is accomplished to most homes and businesses through underground to overhead transitions at the overhead radial line locations. AT&T intends to continue service to the Village through a copper system. They indicated they have plans to upgrade to fiber service in the future but they are not prepared to make this conversion in conjunction with the undergrounding program. AT&T will per-form the communications network design for the program with Kimley-Horn developing the supplemental conduit plans to aid the Village's contractor in installing the conduit for the pro¡ecl, AT&T has communicated the following general guidelines related to the design of the improvemenls. Main underground trunklines and equipment shall remain in service (including exisling SAls and CEVs) The existing underground trunk line shall be reused. Dislribution of service will be converted io underground through connection to the trunk line at existing irunk line manhole locations Service pedestals will generally be installed in the public rlght- of-way or the same easement as the electrical equipment. These pedestals will then provide communications service to ihe individualfacilities. For pedestals not sharing an easement with FPL equipment, AT&T prefers a 5'x5' easement. AT&T prefers major equipment easements io be 10'x10' for their future fiber equipment needs Equipment may be located in the right-of-way if sufficient clear zone requiremenls are met Pedestals require one foot of clear distance around all sides for access and maintenance Pullboxes will be required at regular intervals to facilitate cable pulling and slack cable storage, AT&T prefers 24"x36" and 30"x48" pullboxes. Pullboxes are to be located outside of the roadway surface. When required, pullboxes can be placed in the paved surface and in this case, will be required to be H-20 load rated. KimleyDHorn 43 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Çetn Existing AT&T and Comcast pedestals in Key Biscayne Conduit will be prov¡ded for service cable between the pedestal and the facility to be served, Conduit and pullboxes are to be NEC compliant for communications service and conduit shall be gray in color. Equipment and cabling will be provided and installed by AT&T. Conduit and pullboxes will be furnished and installed by the Village's contractor. lnitially, AT&T plans to design a like-for-like coax¡al based network conversion. This being the case, they plan on reus¡ng all of their existing ground level Service Area lnterface (SAl) cabinets ihat are found throughout the Village, ln the future, AT&T has reported that they are budgeting to install a fiber optic system overlay. To implement this upgraded system, AT&T will require new Fiber Distribution Cabinets (PFP) and easements throughout the Vitlage, ln a recent meeting, AT&T indicated they are open to the oppor-tunity the underground pro¡ect provides to install a Fiber to the Premises (FfTP) network. At the time of this master plan AT&T was not under contract by the Village to prepare detailed design plans, therefore AT&T representatives could only speak in generalities about the infrastructure necessary for a "like for like" conversion or a FTTP conversion. ln most cases, PFP cabinets will be located near existing SAI cabinets or near an existing controlled environment vault (CEV). lt should be noted that many seruice pedestals, below-grade vaults, and handholes will be required for the overhead to underground conversion, but this equipment is not considered significant. Locations for all equipment elements will be determined during the detailed design for each phase. AT&T noted the copper system pedestals are different than the fiber system pedestals. Easements should provide space for both copper and fiber pedestals since the fiber pedestal will need to be installed and made operational prior to the removal of the copper pedestal during the future fiber overlay program, Although the Village has expressed a desire to upgrade to FTTP, and this may be the more cost-effective approach to an AT&T conversion, this upgrade does not come without its challenges, AT&T sells Legacy services to residents and businesses that presently have no equivalent for with a 44 5.0 DESIGN CRITERIA AND CONCEPTUAL DESIGN DESCRIPTION ) ) ) j fiber network. To avoid an additional cost to convert "like for like" services plus FTTP services, AT&T will need to convince all its Legacy customers to discontinue their old services and upgrade to a newer technology. Additionally, AT&T sells its Legacy services to third party resellers who may be unwilling to pañ with their ongoing customer contracts. This issue also prevents pole removal since FPL would then top poles and AT&T would be responsible for removal at an additional cost to the program. AT&T engineers and planners are aware of these issues and are working internally to facilitate an FTTP upgrade. UntilAT&T's contractual issues are resolved, this master plan contemplates the implementalion of a "like for like" overhead to underground conversion. 5.3.3 Comcast Comcast provides communications service to the Village through a network of fiber optic and coaxial cables, The fiber optic trunk line exists in an aerial pole to pole location. Distribution to most homes and businesses is through overhead to underground transitions at the overhead radial line locations. Comcast has offered to upgrade their service to the Village through installation of a FTTP system. However, the cost of this upgrade would have to be borne by the Village. Therefore, this master plan coniemplates installation of a "like for like" fiber optic/coaxial cable system similar to the current one, except all cabling would be underground. Comcast will be performing the communications network design for the program with Kimley-Horn developing the supplemental conduit plans to aid the Village's contractor for installing the conduit necessary for the Comcast network. Comcast has provided the following general guidelines related to the design of the improvements. Main underground fiber optic trunk lines and power source equipment can be reused if practical. Reuse of power sources shall be evaluated during the design phase since this will require a power source to serve both the new network and existing network during the cut over phase. This may overload the power source if sufficient power is not available to serve both networks simultaneously. One fiber node can accommodate a maximum of 256 connections. Fiber node service areas should be designed with less than 256 connections to provide room for future growth. Each fiber node location is suppoded by three pieces of equipment: 1. a power supply cabinet, 2. a Virtual Hub (VHub) Node Housing, 3. a LocalConvergence Point (LCP) that serves as the Fiber Distribution Hub (FDH). For a hybrid fiber/ coaxialsystem, the LCP would not be used. Comcast prefers that the power supply, VHub, and LCP are located in a common 10'x10' easement. This equipment can also be located in the public right-of-way as long as the required roadway clearances are met. The power supply can be separated from the LCP and VHub by a maximum of 800 feet. Howeve¡ separating the equipment increases cost due to the additional conduit required to connect all three pieces of equipment. The power supply cabinet requires a 120V single phase metered service from FPL. Existing pad-mounted transformer with communications pedestals in the background ) ) ) ) ) ) .) .,} J Kimley))Horn 45 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Multiple VHubs and LCPs can be served by a single power supply and located in a common easement. In locations with multiple VHubs, an easement larger than 10'x10' may be required. Cables containing greater than 96 fiber strands will require 24"x36" vaults. Cables containing less than g6 strands can be accommodated in 17"x30" vaults, Higher fiber count cables will be found generally closer to node locations, Fiber counts reduce as the strands radiate from the nodes in the service areas. Vaults are to be located off of the roadway. Service pedestals are not required in areas served with 24"x36" vaults. All service connections can be made direcily from the vault. Service pedestals and vaults will be installed generally in the same easement as the electrical equipment. They can also be installed in the public right-of-way as long as the required roadway clearances are met. These pedestals and vaults willthen provide communications service to the individual facilities. For pedestals not sharing an easement with FPL equipment, Comcast prefers a 5'x5' easement. Existing underground AT&T conrmunications rnanhole arrd pad rrourrted pedesl"al irr Key Biscayrre I A fiber optic service pedesial or vault can serve up io four homes. Conduit is required from the pedestalto the service point at the home if a fiber optic system is installed. Conduit is required for coaxial service cable to the home. A coaxial cable service pedestal can serve up to eight homes but Comcast prefers to design for approximately four homes. Coaxial cable service lengths should be kept under 150 feet in length. Equipment may bc locatcd in thc right of way if sufficicnt clcar zone requirements are met (FDOT or AASHTO, as applicable). Pedestals require one foot of clear distance around all sides for access and maintenance. Pullboxes will be required at regular intervals to facilitate cable pulling and slack cable storage if long runs exist between service vaults/pedestals. Conduit and pullboxes are to be NEC compliant for communications service and orange conduit shall be used. Equipment, integrated pedestal vaults, and cabling will be provided and installed by Comcast. Conduit and pullboxes will be furnished and installed by the Village's contractor. I 46 Existing underground electrìcal pull boxes and communications pedestals in Key Biscayne lnitially, Comcast plans to design a "like-for-like" coaxial-based network conversion. Comcast indicated they would like to provision for future expansion and potentially offer a FTTP network. This would be an upgrade to the existing Fiber to the Node (Fl-lN) network currently in place. However, Comcast stated that the additional cosl related to this upgrade would need to be borne by the Village. This being the case, this master plan contemplates that a "like for like" fiber/coaxial system (fT-fN network) will be deployed for the undergrounding program. At the time of the Master Plan process, Comcast was not under contract by the Village to prepare detailed design plans, therefore Comcast representatives could only speak in generalities about lhe infrastructure necessary for a "like for like" conversion or a FTTP conversion. Comcast indicated it would be ideal for the phasing to start on the south end of the Village and work north. ln that sequence, the existing node boundaries would be maíntained to the greatesl extent possible. Each fiber node 5.0 DESIGN CRITERIA AND CONCEPTUAL DESIGN DESCRIPTION service area is designed to serve up to a maximum of 256 individual connections. lt should be noted that many service pedestals and below grade vaults and hand holes will be required for the overhead to underground conversion but this equipment is not considered signilicant. Locations for all equipment elements will be determined during the detailed design for each phase. 5.3.4 Wireless Technology - Smart Poles There were previous discussions at Village Underground Utility Task Force meetings regarding the opportunity to deploy "Smart Pole" technology in conjunction with the undergrounding project to bolster wireless service. These poles could also serve as low visual impact antenna for future 5G wireless technologies and/or Village wide WiFi service. Kimley-Horn held a meeting with a representative from Hotwire Communications who was invited to address the UUTF regarding the deployment of a Fiber communications network and Smart Poles throughout the Village. However, any of the communications providers within the Village could assist with the implementation of this technology. To take full advantage of the Smafi Pole technology a fiber communications backbone would be required. For the purposes of this master plan, the term "Smart Pole" will refer to a street light pole fitted with antennas for cellular and/or WiFi devices. Smart Poles have been deployed in many markets throughout the U.S. lo develop a distribuied antenna system (DAS)to improve cellular service, They have also been utilized to expand WiFi in public places and to enable coverage for municipalfunctions, supporling data needs of public safety, public works, transporlation and information technology. DAS network antennas are generally installed at lower elevations lhan traditional antennas found on cell towers, DAS infrastructure is also generally lower power and intended to serve a smaller geographic area. They are popular in dense urban areas where traditional cell towers are unfeasible to develop. There are numerous DAS technologies and they are generally specific lo the telecommunication provider. ln general, the lower the antenna height the higher the density of poles required to cover a given area. Kimley))Horn 47 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Kimley-Horn reviewed the Village's Code of Ordinances related to Communicalion Towers and noted that towers are a permitted use on . allVillage-ownedproperiy . GU; Government Use District and within the Village's RM-30 . High Density Multiple Family District . HR; Hotel Resorl District . PUD; Planned Unit Development Districts, provided approval is granted by the Village Council. This excludes many of the residential zoning districts in Village where Smart Pole technology could be deployed. Kimley-Horn's recommendation is the Village review the zoning code and consider modifications to regulations for a Smart Pole DASÂlViFi network deployment throughout the Village, This could include specilic regulations for permitted locations, aeslhetics, height restrictions, etc. This would provide better guidance to the cellular industry regarding how they could successfully deploy such a nelwork within the Village. lt may also supporl and expand opporlunilies for public-private partnerships (PPP) between the Village and providers interested in providing wired and wireless broadband services in the Village, Kimley-Horn fufther recommends that any costs related to deployment of a Smart Pole DAS network be borne completely by the cellular industry and/or broadband providers. lt is also recommended the Village only install Smart Poles in conjunction wiih their street lighting program if a wirclcss industry partncr idcntifies the exact location of where the poles should be installed along with the capital to perform such installation. The Village should not undertake Smart Pole installation without a wireless industry partner because the individual wireless carrier desired locations, equipment, and height requirements are highly variable and specific, and cannot be reasonably predicted, 48 Existing FPL aerial switch FPL feeder splice box 5.0 DESIGN CRITERIA AND CONCEPTUAL DESIGN DESCRIPTION il ,.1 ,.\ \ ) ) ) ) ) ) ) ) I ) l ) I ) ) ) ) j ) i ) ) ) ) ) ) ) .) ..) .J 49Kimley>)Horn 01 i i•� .tea,• _ :,a�;�• - `111111 4 9 ••••••••••••••••••••••••••••••••••••••••••. .-l I \ I ) h apter 6 PHASING AND SEQUENCING Through a series of meetings with the Village, FPL, AT&T, Comcast, and other stakeholder utilities, Kimley-Horn has developed a recommended phasing and sequencing plan for the implementation of the undergrounding program that incorporates many different factors specific to Key Biscayne. These recommendations are intended to serve as guidance during the design and construction of the overhead to underground conversion improvements. This is a lengthy implementation process, therefore these recommendations should be reviewed so adjustments can be made as may be required, These include accounting for changes in technology, various utility and stakeholder requirements, Village priorities, and changes with other capital projects that may influence the implementation of the undergrounding program in the future. safe, reasonable, and reliable manner. Part of this regulatory authority includes the approval of the tariff that sets the rules and regulations FPL operates under in providing electrical service. The tariff document sets forth specific rules for the conversion of facilities from overhead to underground locations. When local governments apply to FPL to have overhead facilities converted to underground locations, they can qualify for a GovernmentalAdjustment Factor Waiver (GAF Waiver) if the conversion prolect meets certain criteria. The GAF Waiver essentially provides lor a 25o/o discount of the Contribution ln Aid of Construction (CIAC) that is required to be paid to FPL by the local government applicant to perform the conversion. That amount is calculated using the formula defined in section 12.1 in the tariff. ln the latest tariff revision effective February 22,2018, certain elements of the CIAC calculation can be excluded if the applicant intends to convert existing non- hardened feeder facilities to underground feeder facilities, The calculation would exclude the cost to remove the existing overhead feeder facilities and the net book value of those feeder facilities. ln turn, however, the applicant does not get credit for the estimated salvage value of the existing overhead facilities to be removed. Despite that, the revision typically results in a lower CIAC to be paid by the applicant. One criteria that is important to consider when developing an undergrounding phasing plan is that the conversion must include a minimum of three pole line miles or approximately 200 detached dwelling units within a contiguous or closely proximate geographic area to qualify for the GAF Waiver. lf the conversion program is to be phased, these minimums may be met over, at most, three phases, and each phase must begin within one year from completion of the previous phase, The Village's 6.1 Phase Limit Development To develop the phase limits for the project, several factors need to be considered. These factors included the following: . FPL tariff requirements . Physical size of the Individual phase . Electric and communication utility system technical requirements . Cost efficlency These factors and their influence on the development of the recommended phasing limits of the program are described in greater detail in this section, 6,1.1 FPL Tariff Requirements The Florida Public Service Commission exercises regulatory authority over FPL to ensure that consumers receive their electric service in a ) ) J .) J Kimley>)Horn 51 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES _ MASTER PLAN undergrounding program of implementation as recommended in this master plan meets the criteria to qualify for the GAF Waiver. Physical Size of the Individual Phase While the FPL tariff contains minimum prolect size requirements to be eligible for the GAF Waiver, the individual phase area should not be excessively large for several reasons: Multiple phases also provide the opportunity for the Village to better control the flow of funds to both the utility companies and the contractor constructing the work. The utility companies require upfront payment of their construction costs. lf the entire Village were to be designed and constructed at one time, significant costs would be incurred very early in the process for matedds and equipment that may not be installed for severalyears. The amount of work performed within a given time period needs to be manageable not only for the Village's contractoç consultants, and staff, but also for the utility companies. There are operations that must be perlormed by FPL, AT&I and Comcast so their scopes of work for both design and construction are feasible to complete within the given timeframe. Sufficient lime must be provided in between the construction starl times of sequential phases to allow for design, permitting, contractor procurement, and easement acquisition activities. Design activities are performed by the Village and the utility companies as a joint effort for each phase. Breaking up the design into multiple phases allows the initial phases to go to construction earlier while the balance of the program phases can continue in design, This overlap of design and construction creates schedule compression to allow the overall program to be completed in an expedited manner. Breaking the project up into multiple components provides for enhanced competition amongst the contracting community to perform the work. Breaking up the total program cost into phases reduces the bonding capacity required for qualified contractors who may choose to pursue the individual projects, This allows the pool of bidders to remain high, which fosters competitive pricing. Multiple phases reduce the dsk a single contractor fails to execute the work of a single large phase. Contractor failure introduces risks to both project schedule and costs related to delays, re-work, re- mobilization activities, and potential litigation. Community impacts due to the construction must be considered in selecting a project size. Each construction phase duration is anticipated to be 1 8Io 24 months. lt has been our experience that durations longer than this can cause strain within the affected community due to traffic impacts, noise, and other construction-related impacts. We have found that confining activities in a relatively small area are desired and better tolerated by the community than large scale activities that impact a large geographic area. 6.1.2 Electric and Communication Utility System Technical Requirements There are also technical requirements that must be considered when setting the phase area limits for an undergrounding conversion program For this program, Kimley-Horn held a workshop with FPL, AT&T, and Comcast to review technical issues and mutually agree upon specific phasing limits, For the most part, the utility companies were willing to accommodate the phasing as it is proposed. FPL and AT&T were relatively flexible with where the phase line limits were to be located. FPL's recommendation was to ensure that three-phase service was provided in each of the phases to loop existing feeders. AT&T was concerned if we skip areas to minimize disruption, additional plans may be needed to bridge over an area to be constructed in a later phase, Comcast had the least flexibility because of the way their fiber optic nodes provide communications service to a very specific area. Changing an existing node boundary requires a significant amount of device programming that can both increase cost and create a higher level of customer disruption during the reprogramming process. To the greatest extent practical, Comcast recommended our phasing work proceed from the South end of the Village to the North end because that is how their fiber trunk line is currently routed. ln any case, temporary facilities may be necessary for each of the utilities to implement the recommended phasing, t 52 6.0 PHASING AND SEQUENCING Legend o Potential Transition Pole Location (Make- Ready Pole) Phase I Phase 2 Phase 3 Phase 4 2 'oø:ô Or Ê ,7o 'ttô¡:- {ooo u! ßL: .v$ efli ,-Ë€ã9 ,3. 'nô^ ., o' G."rd 9â{" WiM.itheion. Dr i..r' ' tt ,f- ,r.r"ì9 d1ì:. Harbor Cir W Èîc !, ı o! lnuú W Enid.W'Enid.Dr ' (Éru. Uo,; N club.Dr'@.o:cir H. Iôtìr! 3 \1"6 I c,(^ ClË w."en¡¿' Þ fw..,*ooo o, f'/2 o'Q.o 'dale Rd q ôú af,âo Drô Har6 j i s.9'ä &^)"n ,ro / ôl ı' a È 0q,o E E¡¡d 9r Lo 0)!Y rü /e ;s*d: Pt '(-a4e hüa ô¡! o d J I Mash.faJ W MashÊa.Dr s êiu¡.Rd ct%lslandiD¡r Grapetree Dr oà lV ,l¿sáe Qr :Ò.' N CaPe.FIoriila' V/+E 0 475 950 1,900 Feet S VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN OVERALL PHASING MAP Kimley>)Horn 53 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN 6.1.3 Cost Efficiency As with any project of this magnitude, there is a high priority placed on cost control, Effective cost control begins during the planning process. From an electrical perspective, phase lines were set to allow the reuse of as much existing underground infrastructure as possible. For example: ürandon Boulevard is a natural boundary because the east side and the west side are linked with underground facilities, therefore they can be reused and electric and communications cables can remain in service without the need for replacement in this program. An underground link to Mashta Island and the mainland also exists, but FPL stated additional conduit will be required to implement an underground system. The existing poles on either side of the bridge can also provide temporary transition points, as they do today. Underground feeder lines in phases 2 and 3 can also be reused to serve proposed facilities for those areas without the need to replace them. To reduce the costs, we also took advantage of locating phase limits where the existing infrastructure lends itself to providing the fewest transition points throughout the Village. For example, phase lines are defined where north-south feeders are the only overhead lines that will require transition poles. By placing a phase limit at these locations, existing radial lines can remain intact in their entirety, minimizing the number of temporary transition poles and equipment that are required, thus reducing cost. Since these transition points are temporary but necessary for the continued provision of power to the community, it is important the number of transitions be reduced to the minimum required. The phasing map prepared for this program includes locations of potential temporary transition poles. 6.2 Sequenc¡ng Recommendations While the limits of each individual phase were defined, the sequence in which they are to be constructed was also considered. This master plan's sequencing recommendations for the undergrounding program, along with sequencing of additional planned projects (i.e., capital projects, watermain replacement, etc.), are graphically depicted on the sequencing maps beginning on page 57 of this master plan. To develop the recommended sequence for the program, several factors needed to be considered. These factors included the following: . Major work programs . Traffic impacts . Cost efficiency . Schedule efficiency The above factors and their influence on the development of the recommended sequencing of the program are described in greater detail below. 6.2.1 Major Work Programs As discussed in the Data Collection section of this master plan, there are several major work programs either planned or will be underway during the undergrounding program, There is a need to coordinate these major work programs with the undergrounding program to minimize community impacts to the extent practical. Major work programs in addition to undergrounding consist of the following: Village of Key Biscayne Capital lmprovement Program Village of Key Biscayne Beach Renourishment Program Miami Dade Water and Sewer Department Watermain Replacement Village of Key Biscayne Gapital lmprovement Program There are several projects contained in the Village of Key Biscayne's Capital lmprovement Program or long-term master plans that must be considered. Many of these have not yet been funded, but the Village is interested in bundling them to be constructed within the undergrounding program. There is also a desire to construct capital projects that are funded from alternate sources with the undergrounding program to take advantage of the restoration cost sharing. This is an important consideration when determining which capital projects should be constructed concurrently with the individual undergrounding phases, ¡ 54 ln general, capital projects that are expected to have significant roadway impacts should be constructed in conjunction with the undergrounding program to the greatest extent practical. However, a balance needs io be struck between maximizing projects within the undergrounding project schedule and ovenruhelming the community with construction impacts. Additionally, projects that are required due to public health, safety, and welfare needs should be implemented quickly and not necessarily delayed to coincide with a particular phase of undergrounding, Many of the Villages projects are non-bond funded projects, are relatively small in scope, and/or are located such that roadway impacts are minimal or have a brief schedule duration, Therefore, lhese projects are recommended to be consiructed in accordance with their previously planned programming schedules. Some projects impacted by the undergrounding, such as landscape improvements, traffic calming, sidewalks, and street lighting should be delayed if possible to coincide with the undergrounding schedule, This will allow for additional restoration cost sharing benefits, There is also a recent stormwater master plan that identifies significant improvements but lacks funding at this time. Projects identified in this plan are to be funded by the Stormwater Enterprise Fund, however, ihat fund !s inadequately funded. The Village recently engaged a financial consultant to develop new rates to begin to fund these projects over the long term. lf financing permits, it would be extremely advantageous to per-form these stormwater improvements during the undergrounding program, thus cost sharing restoration efforts. This would also decrease the impact to the residents in the long term. ln our experience, most resident complaints come from people who live in areas impacted by undergrounding and capital projects at the same time. Provided the funding enables these improvements and the resident impact is managed properly, this master plan recommends that these infrastructure projects be constructed in conjunctlon with each undergrounding phase. Village of Key Biscayne Beach Renourishment Program The Village conducts an ongoing Shore Protection program to protect the coastline. While there are several projects anticipated within this program that will occur during the span of the undergrounding project, we do not 6,0 PHASING AND SEQUENCING anticipale much coordination will be required between the programs, since the beach renourishment project is not in areas undergrounding work will not be performed. Beach renourishment projects that involve truck hauls should be coordinated to reduce the impacts of additional traffic volume through the work zone. Miami-Dade Water and Sewer Department Watermain Replacement As discussed in the Data Collection section of this master plan, Miami- Dade Water and Sewer Department (WASD) does not currently have a formalized program for watermain replacement within the Village. However, at the request of the Village, they are willing to entertain the opportunity to replace aged watermains during each phase of the undergrounding program, There is currently no budget available to perform this work, however, WASD will review the Village's proposal of replacement and consider adding it to the budget for the next fiscal year. This master plan's recommendation is to focus on the known watermains consisting of asbestos cement pipe as requested by the Village. There are other watermains identified by WASD as being made of an unknown material. Secondarily, we recommend review of those locations to determine the most cost-effective approach to their replacement. Because physical investigation will be required for these unknown watermains, timing of their replacement may not coincide with the undergrounding program. lf the County does develop a program of watermain replacement during the course of the undergrounding project, additional cost sharing opportunities could be explored through deferral of milling and overlaying activities until both undergrounding and watermain work is completed. 6.2.2 Traffic lmpacts The sequencing recommendations for this program are also influenced by the desire to reduce traffic impacts to the highest degree possible. A detailed discussion regarding an overalltraffic management plan is discussed elsewhere in this master plan but on a grander scale, the beginning of a mitigation plan for traffic impacts begins with sequencing individual phases. ) ) ) -) -) KimleyDHorn 55 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Because of how the Village was originally developed and the conflguration of the land mass and roadways, it would be easy to have two adjacent work areas undergoing heavy construction at the same time, impacting a large area of the Village at once. A good deal of consideration and strategy went into developing a sequence that avoided just that. To that end, Kimley-Horn recommends that heavy construction activities do not take place simultaneously in two adjacent phases. For example, as Phase t heavy construction ends, Phase 2 heavy construction can begin, and so on and so forth. Heavy construction refers to the installation of the conduit and equipment pads either by open trenching or directional drilling operations. While heavy construction activities are taking place in Phase 2, less impactful activities can take place in Phase 1 such as equipment installation and demolition of existing facilities. ln this manner, a motorist can avoid roadways experiencing heavy underground construction and will never have to drive through two phases undergoing heavy construction activities at the same time. 6.2.3 Cost Efficiency ln determining the sequence of ihe phases, cost efficiency was also a priority, At the completion of each phase, there will be a transition from the new underground system to the existing overhead system to maintain connectivity of the systems after the de-energized poles are removed, These transilions almost always require the installation of new temporary poles with electric and communication risers. Because these new poles are temporary and will be removed when their location phase is completed, it is important to minimize the number of transitions to the greatest extent possible. ln order to do this, phases should be constructed sequentially so only one side of the phase area would require these transitions. The sequencing this master plan recommends accomplishes this by constructing phases generally starling from the south end of the Village moving towards the norlh. This will also minimize the amounl of temporary facilities the communication utilities need and generally accommodates iheir preferred sequence of conversion. ln addition, compressing ihe schedule as discussed in the following section will reduce costs due to inflation and project general conditions. The sooner the program is complete the less inflation factors into the overall budget, We recommend accomplishing this by overlapping phases wherever possible while avoiding significant traffic impacts to the extent practical. 6.2,4 Schedule Considerations As discussed in the Physical Size of the lndividual Phase section, individual phases were developed considering work that could reasonably be performed in an 18 to 24-month continuous period. To gain schedule efficiency, Kimley-Horn recommends work in adjacent phases overlap each other to avoid waiting until final completion of one phase before beginning work in a subsequent adjacent phase, This recommendation is discussed in further detail in the Overall Program Opinion of Schedule section of this master plan. ln general, this would allow for service conversion work and overhead infrastructure demolition to occur in one phase, while heavy underground work would occur simultaneously in the adjacent phase. ln no case do we recommend heavy underground work be performed simultaneously in adjacent phases. This avoids significant traffic impacts expected if these activities were allowed to occur simultaneously in adjacent phases. Phases in the commercial areas of the Village are anticipated to be more technically challenging from a design and easement acquisition standpoint This is due to the high electrical load demand, limiied right-of-way availability, and urban landscape. Fortunately, the way the commercial property is situated in the Village, we were able to divide the commercially zoned areas into three different phases, effectively reducing the complexity in any one phase. This will allow adequate time for design and easement acquisition for these challenging parcels. 56 FPL capacitor bank 6.0 PHASING AND SEQUENCING Knollwood Dr CaPe Florida W Enid DrW Enid Dr L ô, rd,(, o W Mashta.Dr (a4e þûa Þr, lsland Dr Grapetree Dr J ub Þr tr ID Àr ô Iâ; {oôe o^tuo <ô fo o Cl .ô .o ê. g,ò o Nct Enid. D¡. âù Io |t) ..Y'¡v !ô o I'C S Club 9w åì V- Westwoo¿ p" 1'"d"1" Rd ô c n È Ûooâo çlzIo¡I tË .L o"&î Lane Dr """.""o Of PHASE I ¡oodcrest Ln CONSTRUCTION 2020 Ió¡ess Dr Í 8¡ ! o 2ooÊô o vo 'tlo5 { oo a CL Sonesta Dr o^-\ o tô ¡t a)uo rot""- C/'ô Þ¡ 6Ío!¡avè I Þ Þ¡ f;. Ð CL Cranwood Dr CI c. 9¡o ô{.o lio€Iı¿ ,vc 0) ( Greenwood Dr W Heather Dr ÐÈ v CL d 0) E Heather Dr .es Cir TurtleWa,u4 ot -t:{ 'o .i"ı- -4l' v aoP' .o( o- ê;"" G"rrrd Êâ{ a Galen Dr I Redwood Ln b(l c E\ s Þqvs ^\o W Palmwood Lno rË! aW Matheson Dr Beechwood Dr Þooìo ò0t É, .æ" *+ (, W Mcintyre St w QÛ !¡ a0 o! ËıL Lo trIt c,) o o{ L rú .¿ Sunset €r¡ Harbor Cir Sunrise Dr Mas\¡@ Dr Oç .rf {s'"l:,. %o^ O-.A "%N ır.+0 375 750 1,500wEFeet S VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN PHASE r SEQUENCE OFWORK MAP Kimley)>Horn 57 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN 9lIolt! ln I z O""Êr' \2ne Dr rof PHASE2 st Ln F. CONSTRUCTION Ió.e* D" Í 7ooÈô-.o uo 'tto: {ooo aa %uu 2022 ¡¡)f, 0 Sonesta Dr .¡o't"' <,\ô Eúrto e Ð c). f D¡ôjt ô v o- Þ B 1}. oi Io Cranwood Dr o ¡.o .vo l) Greenwood Dr 7ô-vô.sdl) Þq ¡x Cir T¡¡rtlgWalkfY.9!f." ?opo o( vo (f\ w øI _dìnDrBeechwood. Dr Þooì 0)qo q 'Fw"t,l(,Grun.d 9â{ Galen ÞrVf W Mcintyre St :o ı o! rËLu Lô d qJ Uo Sunset C¡¡ Harbor Cir W Enid Dr W Enid Dr Sunrise DrcJ EL lËì W Enid Dr f't Io o.Y G N club DrHar¿ oì.t ã. 7 o +- 'qz'1o oe <Ò 7.. %o"r \^/estì /ood Dr ãB9Èôôt ìií o.lûqóO6u o Ert¡, eRd !o (t c) o q% <. Mas\¡@ Dr W Mashta Dr (¿ke hUa Ò¡ Io o r!J S Club Rô <,lsland Dr -*û{o' "t";: |un- ?o o^ Knollwood Dr Çrapetree Dr Ô^ Îv ,|¿sôgNt'+ô¡ CaPe Florida Dr03757501,500 E Feet S 58 PHASE 2 SEQUENCE OFWORK MAP //riílirt' 6.0 PHASING AND SEOUENCING N clyb Dr i:'.- ;Eio :r¡^ Li C¡, ; O¡.rE"uó nl <og' o,.,.,"j i i S qu¡ ßò i ;i .l I Lo fiti o,uo' ':ì, ,,;,, r.' l i' 'r, i 1i " Çrapetree Dr ¡ rl ,l',,i iìl '.' I rìr ! ii : ' rr ,".'i,, Galen Dr.1' '¡ i' itt,. . L;: {ì:1.:¡ lir¡ii Sunrise. Dr i,.,iiì,,1:!,i ':iiliii ,ì¡r:ìì¡: E'Enid Dr E'Wood Dr rj') 10 ; .o).t.:¡_d !\, ,i!. L.ôÌ liii:i í,).Yrt ti 'I t' 1¿a vîua D¡ 1. caPe itor¡da Dr t. I ,'' ofWY.l .l :, 9 "'.o McinÇre St f ' . )rii, ! :; :ı:i WEnidD"'-'5'' i,trtd Dr,ut t t i i' IL...:,]i 6l I I.j Knollwood Dr i 1l r '! ': i. lsland Dr 7ooÈal o vo o. Êsuo Þooì a) à0 Ëw:. !i;lr!!lr.¡i, ij ,: i:ii!i.liW Enid {oooô ô Iø +l,^. 4o^'o W Mcintyre St !ô Westwoo¿ O. Rd W Mashta Dr: 5 c Ef Redwood'Ln W Palmwood Ln Beechwood Dr .o ooI'Ê W Enid Dr Ftn Har4 Í !ø$'7 z'o^ or" uon <o oÞ"% a t ',.' v$Ag"' W Matheson Dr {' Sunset Crb Haråor Ci¡, "rï::" CONSTRUCTION *troo Feet r,o( ¡tL rt¡ 1,500 PHASE 3 2023 Flas\¡@ Di 7503750 E N+ s w ) ) ) ) ) ) ) ) ) l ) ) ) ) ) ) ) ) ) VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN 59KimleyDHorn PHASE 3 SEQUENCE OFWORK MAP ) VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILIT¡ES UNDERGROUNDING MASTER PLAN çlz! o¡tIdI o""Êr' tane Dr PHASE 4 ""J r¡{oodcrest Ln CONSTRUCTION Ió^ess Dr f 9¡ 3! oa 7ooè o âv CL 'no: { oo Fè Sonesta Dr çtrÞt e=''* åEä;I;oqir o^tsù on \o c¡l It, o 2024 C. to{"t- Cranwood Dr ç Greenwood Dr W Heaürer Dr o{\of rü¡ f" {no .¡- E Heather Dr ¡:s €ir TurtleWalk s f.p9po o( G"und 9d ,¡Y Dr aoRedwood Ln W Palmwood Ln Beechwood Dr Èqvs c¡r cøILf Èooì a) ào.!É €nüt ,(, t¿) à0ß w+ W Matheson Dr too] Ð fit th \^/ Mcintyre St Galen Dr Qç W Mcintyre St 6 ! ı Êo! ÊrtIu Lô çr!o o (o¡L rn¡ W Enid Dr W Enid Dr Sunrise Dr 5 oL ñtì W Enid Dr E Enid Dr E Wood l)r ro o C N c¡ub Dra 7ooe o^ P.. %d"," Westwoo4 ¡.{ooÈ no ô e o % Iô g r!í,go @rt ¡¡ Rd oruo <Òuo.âo.(a&e V¡tta Þr <ô W Mashta Dr S Çlub Rô lsland Dr +. Q¡4.t*Knollwood Dr Çrapetree Dr N o+ S 0 375 750 1,500 CaPe Florida Dr w E Feet aÍó o )'$ H Harùor Cir Cri Dr os x!!? {r" "%ıþ o¿. Ìv + .r o^ 60 PHASE 4 SEQUENCE OFWORK MAP 6.0 PHASING AND SEOUENCING 1 a '1 I I 1a ,) a .) I ) ') ) 1 ),) I ) o :) ) .) ) J :) .) JJ J J J U J J J J J J ..) -) J 61KimleyDHorn 'tl .¡\ h apter 7 ) j PROJECT DELIVERY METHODS A project delivery method is a system utilized by owners and public agencies to manage how a project will advance from concept to construction. Project delivery refers to the method of assigning risks and responsibilities to an entity for design and construction services and is different from project management, Project delivery methods can be grouped into several basic categories consisting of Design-Bid-Build (DBB), Construction Management at Risk (CMAR), Design-Build (DB), and lntegrated Project Delivery (lPD), which is primarily used in the vertical construction industry. IPD is not commonly applied to the construction of public infrastructure, therefore this master plan willfocus on DBB, CMAR, and DB while only providing a brief description of lPD. > Florida Power & Light (electrical infrastructure); > AT&T (telephone and communications); >> Comcast (cable television and communications). The Village has varying degrees of control over these entities. For example, ihe Village has a great degree of control over the Village design team due to the contractual relationship between these two entities, However, the Village has much less control over FPL, AT&T, and Comcast. These varying degrees of control create an element of risk that must be considered when developing an overall schedule for the project. Scope: The various types of work in a specific phase may also play a role in delivery method recommendations. For example, if a construction phase requires a small number of trades, crews, and manpower to execute the scope of work, il is inherently easier to coordinate these activities between the various contractors. This type of project may be easier to execute through a traditional DBB process. On the other hand, when multiple trades and disciplines, multiple crews, and significant manpower are required to execute the work and significant coordination is required between involved parties to appropriately schedule the activities in order to maintain schedule and budget, CMAR or DB may be more effective project delivery methods. Ultimately, the design documents must provide an appropriate level of detail to properly communicate the prolect requirements to the construction team. This level of detail can vary based on the project delivery method selected. l ) ) ) ì ) ) ) ) ) ) ) ) ) 7.1 Project Delivery Method Selection Factors There are several key factors the Village must consider when choosing a project delivery and contracting strategy to execute the undergrounding prolect. These factors are summarized as follows. Design: The design must meet the needs and vision of the Village For the undergrounding project, the design team is comprised of various entities, including the utility owners who will design and ultimately own their respective infrastructure porlion of the project. These entities include: > Village Design Team (conduit routing, Village owned and mai ntained i nfrastructu re, such as d rainage i m provements, and watermain improvements that will be ultimately owned and maintained by the Miami-Dade Water and Sewer Department); Kimley>)Horn 63 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES _ MASTER PLAN Budget: The Village has not previously established an overall project budget and is considering lssuing bonds to raise the necessary funds to execute the program. To establish budgetary costs and assess the risk of exceeding this budget, this master planning process will develop an opinion of probable cost for the program. This will assist the Village in properly planning to manage this risk. Schedule: The Village places a high priority on schedule since they are in the sights of FPL's storm hardening program, Expediting the execution of the undergrounding program is a high priority. Additionally, disruptions to traffic flow can be extreme causing the roadway level of service to decrease to unacceptable levels, The Village does not have a large seasonal influx of residents that would limit allowable construction times, so disruptive work in the road right-of-ways can be conducted throughout the year, allowing a more efficient construction schedule. With that in mind, the intent would be to be minimize disruption to the community as much as possible. Because the undergrounding program is a multi-year, multi-phase program, significant schedule delays in any one phase may create a domino effect and delay subsequent phases. This would not only extend the program but could also increase prgect costs due to inflation and increased general conditions and labor rates. Therefore, schedule will be given a high priority when considering project delivery methods. Risk Assessment: There are inherent risks in any construction project. However, those risks can multiply when the size, budget, and duration of the project increases. It is important a risk assessment be performed during the planning phase of the pro¡ect so risks can be appropriately understood and allocated amongst the parties involved. ln general, risk should be allocated to the party with the best ability to exercise control over the risk, Each project delivery method assigns risk to the various parties differently. The Village will need to consider the level of risk it is willing to accept when selecting a project delivery method. Staff: The Village's level of expertise and experience with the various dclivcry methods also plays a role in recommending an approprlate prolect delivery method. The Village's ability to manage the project construction in-house can also influence the selection of a project delivery method. For example, a CMAR or DB team can expand to meet the Village's staffing needs and may eliminate the need for the Village to hire additional staff to support the project. The CMAR/DB team can take much of the burden of construction management off the Village staff. Lookirtg al. the NW corrrer of 101 Key Biscayrre Condo from Crandon Boulevard 64 7.2 Overview of Project Delivery Methods The following provides descriptions and a summary of the advantages and disadvantages of the various project delivery methods available to the Village for project execution. 7.2.1 Design-Bid-Build(DBB) Design-Bid-Build is the most common and widely used project delivery method in the United States. The process involves executing the project in three sequential phases: Design, Procurement (Bidding), and Construction. The designer prepares the construction plans and specifications for use in the procurement process. For the Village's undergrounding project, the construction documents will consist of drawings and specifications prepared by Kimley-Horn, FPL, AT&T, and Comcast. The project is then advertísed for public bidding and price proposals are obtained from interested members of the contracting community. The Village is familiar with this process and has standard contracting language developed to execule construction projects using this delivery method. The selection process is usually the lowest responsive and responsible bidder under this delivery method. The contractor who submits the lowest price, has demonstraied it meets the minimum qualifications set forlh in the bid documents, and has properly prepared the bid proposal package per the instructions, will be awarded the project. The following is a summary of the advantages and disadvantages of the DBB pro¡ect delivery method: Advantages: . This method is the most common approach for public owners having to comply with local, state or federal procurement statutes The Village's Procurement depafiment already has standard contracts and guidelines in place to facilitate this method, ' This method is well understood by the Village and has well- established and clearly defined roles for the parties involved. . This method can yield a low upfront cost to construct the project because much of the risk is assumed by the Village and design plans and specificatíons are well defined. 7.0 PROJECT DELIVERY METHODS The Village has a great degree of control over the process due to their control over many elements of the design prior to selection of the contractor. However, the Village exerts less control over the designs prepared by FPL, AT&T, and Comcast or to changes to the design these entities may choose to make after the bidding process. Disadvantages: . The Village generally faces exposure to contractor change orders and claims over changes and unknown field conditions since the Village accepts liability for design in its contract with the contractor. . This approach can create a more adversarial relationship between the involved padies rather than a cooperative one. This can lead to higher costs and longer schedule durations than originally anticipated. . Jhe process may have a longer duration when compared to other delivery methods since all design work must be completed prior to selection and award of a construction contract. ' The absence of a contractor during the design process does not allow for the advantages a contractor may provide through assessment of scheduling and cost ramifications for various elements of the design. . lf the Village uses a fixed price contracting method, the contractor may pursue a lowest-cost approach to completing the project and the Village may receive lower quality work than expected for the price, requiring increased oversight and quality review by the Village and design team. lf the Village uses the unit price bidding and compensation method, the contractor may try to increase the scope to maximize revenue from the contract, costing the Village more than expected. ' The absence of construction input into the project design may limit the opporlunities for building in efficiencies that can reduce the cost and duration of the work, lmpoftant design decisions affecting both the types of materials specified and the means and methods of construction may be made without full consideration from a construction perspective. ) ) Kimley))Horn 65 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN lf the Village chooses to execute capital projects at the same time as the undergrounding program, procurement under this method could lead to some elements of the work being managed by a contractor who is inexperienced in that given discipline. For example, if drainage work needs to be completed only on one street in the project phase area, the undergrounding scope of work wlll far outwelgh the drainage scope of work. This will potentially lead to an electrical contractor being forced to manage a drainage project. That would be highly unusual for the electrical contracting community, This lack of experience could lead to detrimental outcomes for both the drainage and undergrounding scopes of work. This method can require additional Village staff for construction oversight, coordination, and communications, For this project, technological and programmatic obsolescence could become a problem since this is a very large, long lasting pro¡ect. This is mitigated somewhat by constructing the project in phases. However, changing technologies and the deployment of technology by FPL, AT&T, and/or Comcast during the construction process will put the Village at a disadvantage when negotiating these changes into the contract if, and/or when, they occur, 7.2.1.1 - DBB Contracting and Procurement Methods There are several types of contracting methods to be used under the DBB project delivery type. A very common approach is the lump sum, or fixed price bid. This is commonly used in the vertical construction industry or for any project where quantities are not easily measured. The Village is accustomed to this method, as well as the unit-price method, which is commonly employed in the horizontal construction industry. A complication that can arise in the administration of construction for undergrounding projects is ihe quantification of the extensive number of conduits of varying sizes that will be installed under the project. For this reason, the electrical undergrounding contracting industry is more accustomed to the fixed price, or lump sum bid, approach to procuring this type of work. This approach also shifts the responsibility for quantification to the contractor, which reduces the Village's risk of quantity overruns (or under runs and the claim for lost profits) that may have occurred under a unit price approach for the same work. For this project, it would be important to procure the contractor once the utilities have released their designs and after the compiled utility plans have been prepared. Because this is a fixed price procurement method, prospective contractors would need fully developed and permitted design plans and specifications to bid from. The Village would be expected to have easements acquired and designs finalized to avoid change orders during construction. I I 66 The roundabout at Westwood Drive and Harbor Drive 7.2.2 Construction Management at Risk (cMAR) Construction Management al Risk (CMAR) is similar to DBB because the CMAR fulfills the role of general contractor during the construction phase. The "risk" in CMAR is the Construction Manager holds the trade contracts and takes on the risk of performing the construction while guaranteeing the completion of the project for a negotiated price. This price is usually determined when the design is between 50% and 90% complete. The CMAR is usually hired by the owner prior to the project design being completed. Typically, the CMAR performs most of the work through subcontractors procured through a competitive bidding process very similar to DBB. Howeve¡ the CMAR's fees are negoliated separately by the Village and those fees are a comparatively small porlion of the overall construction cost. The central idea of CMAR is to gain the advantage of price competition in the subcontractor work packages combined with the qualifications-based selection of the General Contractor as the CMAR. This delivery method is different from DBB in that the CMAR offers schedule, budget, and constructability advice during the project planning and design phases, as well as advisory professional management assistance to the Village prior to construction. With CMAR project delivery the construction manager and contractor are a hybrid of the traditional DBB roles. Another way to look at this is the CMAR manages the construction of the project. This can be very beneficial for owners who have minimal in-house staff to manage the project and for projects with scopes of work covering multiple disciplines. Having pre-conslruction Construction Manager advisory services can idenlify advantageous changes to reduce project costs and/or allow construction of certain portions of the prolect to begin before the design is finalized. For example, the CMAR can bid out portions of the project with approved designs at any time, without having to wait for the entire design to be completed. The CMAR and owner can come to an agreement on a guaranteed maximum price (GMP) based on a partially completed design, which takes into account the cosl to complete. Coming to an agreement early in the project on preferred materials, equipment, and prolect features can also be helpful in allowing the use of per-formance specifications or reduced specifications rather than standard specifications, This can reduce 7.0 PROJECT DELIVERY METHODS design costs since plans developed for a DBB procurement generally need to be more detailed than those used for a CMAR procurement process. The following is a summary of the advantages and disadvanlages of the CMAR pro¡ect delivery method: Advantages: . This project delivery method can arguably require the leasl number of owner employees because the CMAR can expand to meet the Village's staffing needs. The CMAR takes much of the burden of construction management off the Village staff and provides professional advisory management assistance during design. The CMAR may eliminate the need for the Village to hire additional staff to supporl the project. . Portions of the construction can be "fast-tracked" prior to fully completing the design. ' The Village maintains a greater degree of control over the construction budget since it's discussed throughout the project design. During construction, the Village would maintain the authority over whether monies from the construction contingency fund are expended. . CMAR project delivery gives the Village the opporlunity to incorporate a contractor's perspective and input into the planning and design phases of the project. Because the CMAR is involved in the design process, ii is more difficult for them to make a claim related to the clarity of the plans or not fully understanding the scope of work. This is why CMAR generally results in lower cost growth (fewer change orders) than other methods. . The CMAR participates in value engineering and constructability reviews, which can lower costs and achieve schedule efficiency. . Companies that offer CMAR prolect delivery are generally concerned about their reputation since mosi CMAR's are selected on a qualificalions basis. They are significantly motivated to per-form well to uphold their reputation, ' The CMAR is far less likely to develop an adversarial relationship with the Village during the course of the pro¡ect. This results in a consiruction team motivated to perform well for the Village, resolve KimleyDHorn 67 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN issues quickly and cost effectively, and maintain a positive working relationship so they can continue working with the Village on future projects. In this manner, risk is better managed and claims/lawsuits are often fewer. . The CMAR process offers the Village "open book" transparency on how the construction price is developed. All of the subcontractor bid proposals, CMAR overhead, project management, profit, and contingencies are clearly identified, shared with the Village, and agreed upon before the work begins. This also allows the Village to know the full budget for the project, unlike the DBB method where budget issues may not be discovered untilwell into the construction process. . Because the CMAR is ultimately responsible for the schedule and budget, they generally will bid the work to qualified, bondable subcontractors who the CMAR has confidence will construct their scopes of work successfully. . Our experience with this delivery method has been positive, with projects being completed on-time or ahead of schedule and under the negotiated GMP. When the cost of the project is less than the GMB the contingency funds, which can be held outside of the GMP contract, are retulrned to the Village. Disadvantages: . To provide the best value to the Village, the proper selection of the CMAR is critical, This is a "people" business and getting the right combination of skills and expedise is essential for project success, . Because the CMAR provides a GMP for the project, the CMAR is in an "at-risk" position during construction. Depending on what challenges are faced during construction, the contingencies developed during the GMP negotiation may not be sufficient to cover the costs of dealing with those challenges. Because the CMAR provided a GMP, they are responsible for overcoming the challenge regardless of the cost. This can put them in an adversarial role with the Village if this situation develops. . Despite the CMAR finding it very difficult to pursue change orders from plan ambiguities because they were involved in the design process, they may become very aggressive on change orders due to changed conditions (increase in scope) or adverse weather impacts. 7.2.2.1 - CMAR Contracting and Procurement Methods CMAR is a two-step procurement process: 1) pre-construction services and then 2)construction services. A Request for Qualifications (RFa)to select the CMAR is the first part of the two-step process. The RFQ process follows the same rules as the Consultants Competitive Negotiations Act (CCNA) process in the state of Florida. Based on the qualifications submitted, the Village narrows the pool of potential contractors to a short list. The Village can then either select from the short list or invite the short listed CMAR's to make a presentation. The Village can then select the contractor based on who made the best presentation. Once the CMAR is selected, an initial agreement on a fixed fee for pre- construction services is negotiated, Pre-construction services can include the following: . Performance of quantity surveys . Suggestions regarding constructability and methods . Value engineering . Suggestions regarding cost reductions . Development of a detailed construction schedule ' Development of the final GMP after completion of the 907o construction documents that includes the subcontractor bidding proÇess, . Participation in public outreach The GMP for the project will consist of the following elements: . Public adveftisement for the subcontractor bids . Prequalification of the subcontractors . Analysis of all subcontractor bids to eliminate gaps and incomplete bids ' A detailed construction schedule 68 liemized breakdown of all direct costs, general conditions, CMAR management fees, overhead and profit, and the Owner's contingency The GMP is presented to the Village in a comprehensive document and the individual components are reviewed by Village staff and the design team consultants. Comments are made to the CMAR and the price is adjusTed until a final agreement is reached, Once the GMP is accepted, the second step in the two-step procurement process commences-the construction phase. The CMAR performs allthe duties a general contractor would under a traditional DBB procurement. Additionally, the CMAR also performs the following services: Conducts and arranges all meetings for the project, including agenda development and minutes distribution Schedules and coordinates the work amongst the various trades, owner, design team, and slakeholders Tracks and provides a log of Contingency Use Directives (CUD) Provides executive monthly reports regarding the project progress Pafticipates in public outreach activities, including the role of "Project Liaison" if desired by ihe owner. To take advantage of the preconstruction services provided by the CMAR, it would be important to contract with a CMAR during the design phase so they have the opportunity to weigh in on the designs as they are released and inform the compiled utility plans to achieve the most efficient design and construction approach ahead of GMP development. Because this would be a qualifications based selection, design plans and specifications would not be needed until GMP development. 7.2.3 Design-Build (DB) The Design-Build (DB) delivery method has gained popularity and is sometimes seen by the industry as a solution to the limitations of the other project delivery methods. This delivery method is a service provided by a single entity that provides both the design and construction services. The main benefit is the DB provides a single responsible party for the design and construction of conventional projects. DB combines engineering and conslruction services under one contract, minimizing the disputes the 7.0 PROJECT DELIVERY METHODS Village would normally handle, ln DB, these become internalteam disputes that may not involve the Village. Using the DB method, a preliminary scope of work and budgetary opinion of cost would be prepared by an independent consultant and the Village would then seek DB firms who would be responsible for the design and construction of the entire project. The following is a summary of the advantages and disadvantages of the DB pro¡ect delivery method: Advantages: . DB can theoretically deliver a project in a shorter amount of time than a conventional DBB because there is only one selection process (DB team) instead of two (design team and contractor) . The Village will have one contract with a single entity for both design and construction that simplifies contract administration . Similar to CMAR, cost efficiencies can be realized because the contractor and designer work together throughout the entire project ' Change orders lypically only occur due to changes to the original scope that are initiated by the Village . Portions of the construction can be "fast-tracked" prior to fully completing the design Disadvantages: . For this project much of the schedule efficiency that DB can offer is hampered significantly by the design efforts and schedules of the utility owners. This is because the design-builder exercises little control over these entities so they pose a significanl schedule risk to the design-builder in both the design and construction phases of the project. The enhanced level of risk may cause the design- builder to charge a risk premium to cover the potential of assessed liquidated damages. . For this type of project, the easement acquisition process would be problematic under the DB delivery method. lf the design-builder is responsible for obtaining easements, there is a schedule and cost risk due to property owners who are unwilling to grant an easement. lf liquidated damages are included in the contract, a cost premium may be assessed by the design-builder to assume the schedule risk. Additionally, the design-builder may be less Kimley))Horn 69 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN inclined to negotiate a change with a properly owner who is willing to grant an easement, bul not in the location preferred by the utility owner or in the location that offers the lowest cost to the project. This increase in the prolect cost would place negative pressure on the design-builder's profit margin, which reduces their motivation to accommodate the property owner's request. The easement acquisition process presents a schedule risk a DB contractor may not be willing to assume under a fixed schedule duration. The Village has significantly less control and involvement over a DB project than traditional DBB or CMAR. To take full advantage of any shorter implementation benefits that DB offers, the Village must be highly responsive in its decision making. The Village loses the benefit of the checks and balances that exist when contracting separately witl'r irrdeperrdent design consultants and a general contractor or CMAR. May be problematic when there is a requirement for multiple agency design approvals. There is a risk that an adversarial relationship could develop if the quality of the pro¡ect is not what was expected by the Village. Under this delivery method, the design team works directly for the contractor, who may not have the best interest of the Village in mind. 7.2.3.1 - DB Gontracting and Procurement Methods There are several alternalives to contracting and procuring DB services. Contracting can be through a fixed price lump sum agreement similar to DBB or, like the CMAR delivery method, through a pre-construction fee and GMP development process. The procurement process is usually a two-step process. The first step is issuance of an RFQ and the submittal of qualifications by prospective DB teams. The owner would then establish a shorl list of the best qualified teams to then submit a cost and technical proposal to the owner. The cost and technical proposal usually contains any technical innovations developed by the DB team along with schedule and any other pertinent details related to the design and construction process. ln some cases, owners find it beneficial to produce "bridging documents" that are prepared by an independent consultant. The bridging documents provide detailed information related to the quality and function of the desired project. They can also contain any schedule or design constraints that may otherwise be unknown to a DB team. These documents can reduce the risk the owner does not receive what they initially anticipated at the onset of the project. Once the cost and technical proposals are received by the owner from the DB teams, a DB team can be selected based on a combination of pricing, approach, and qualifications. For this project, it would be important to select a DB team after each of the utilities has released their designs but ahead of the compiled utility plans to achieve the most efficient design and construction approach leading inio GMP development. The Village may elect to provide performance specifications ahead of selection to provide the framework for the construction of the prqect. Because this would be a qualifications and pricing based selection, design plans from each of the utilities would be required ahead of GMP development. I 70 7.2.4 lntegrated Project Delivery (lPD) lntegrated Project Delivery (PD) is relatively new method specifically geared towards building construction and is being used more and more in conjunction with Building lnformation Modeling or BlM. This method was developed using ideas developed by Toyota and is designed to solve key construction issues such as a project schedule delays, cost overrun, and lensions among project team members. IPD is defined by the American lnstitute of Architects as "a project delivery approach that integrales people, systems, business structures and practices into a process thal collaboratively harnesses the talents and insights of all participants to optimize project results, increase value to the owner, reduce waste, and maximize efficiency through all phases of design, fabrication, and construction."1 There are eight main sequential phases to the IPD method: 1 . conceptualization phase fexpanded programming] 2. criteria design phase {expanded schematic designl 3. detailed design phase fexpanded design development] 4. implementation documents phase fconstruction documents] 5. agency review phase 6. buyout phase 7. construction phase 8. closeout phase 9. facilities management IPD requires collaboration between the primary parties to share the risk and responsibility for project delivery, ln a contractual sense, the owner, contractor, and designer are joined in a multi-party agreement to create a team-based approach with the goal to maximize collaboration and efficiency. Compensation typically consists of three components: 1) reimbursement to cover costs, 2) incentive for achieving desired budgetary goals, and 3) rewards for accomplishing set project goals. 7.0 PROJECT DELIVERY METHODS or advocating its use. Therefore, we have not considered it as a viable alternative for delivery of any phase of this program, 7.3 Delivery Methods Used by Local Municipalities ln developing our recommendations, we also reviewed how other local municipalities delivered their overhead to underground utility conversion projects. The following table provides a summary. Town of Jupiter lsland DBB As shown in the table, a mix of Design-Bid-Build, Design-Build, and CM-at-Risk project delivery methods have been employed by various municipalities to deliver overhead to underground conversion projects 7.4 Project Area Characteristics To start our analysis of project delivery we first looked at what we learned during the development of the project phasing and sequencing plan. During that analysis it became apparent the project phases can be broken into groups based on total impacted area including: . alternating work zones to minimize those impacts, There is very little industry experience with this method, Kimley-Horn is not aware of it being used in the public sector or on horizontal infrastructure projects. Kimley-Horn is also not aware of any contractors within the undergrounding industry thal are experienced with this method 1 "lntegrated Project Delivery: A Guide" (PDF). American lnstitute of Architects2OAT version 1 ) ) DBBJupiter lnlet Colony Town of Gulfstream DBB City of Hollywood CMAR City of Pompano Beach CMAR Lake Worth DB CMARTOPB (Worth Ave) DBBTOPB (Everglades lsland) TOPB (Nightingale/La Puerta)DBB TOPB (Lake Towers)CMAR City of Hallandale Beach CMAR CMARCity of Kissimmee City of Sunny lsles (Collins Corridor)DBB Town of Palm Beach flown-Wide, PH1-N,S)CMAR Town of Longboat Key DB MethodMunicipality KimleyDHorn 71 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN r complexities based on the land use that is contained in each phase, and . priorities set by the Villages other Capital lmprovement projects The types of land uses in the Village generally consist of multi-family residential, mixed use commercial and residential, and single family residential. Understanding the level of complexity existing in any given phase can aid in the project delivery selection process. By grouping the land use classification, the diversity of major work elements contained in each phase, and the anticipated community impacts involved in working in any given phase area, this level of complexity can be more easily seen. Community impacts include a combination of factors such as impact to private propefty owners, traffic impacts, sufficient right-of-way to perform the construction operations (or lack thereof), impacts related to other infrastructure work beyond undergrounding to be performed, and the level of stakeholder coordination required to execute the work. The table below su m m arizes th is i nformation. It is notable the major work elements described in the table are those anticipated to be constructed in conjunction with the undergrounding project by the contractor selected for each phase. Most projects are unfunded at this time and involve outside stakeholder par'ricipation. 7.5 Project Delivery Recommendations The Village's undergrounding program is a very large and complex infrastructure program that will be implemented in a phased manner over four to six years. ln developing recommendations for project delivery methods for each of those phases, the risks to cost, schedule, and level of scrvicc expectations must carefully be considered. Each key factor identified in the opening of this chapter must be reviewed for their risk impacts for each of the project delivery methods. lf any single phase falters in any of those three risk areas, the remaining phases of the program will be detrimentally affected, For this reason, the project delivery method must balance those risks with cost, while yielding the highest probability of pro¡ect success. It is our opinion the CMAR method of project delivery yields the highest probability of success for delivering the multiple phases of the Village's Undergrounding Program. This is a method approved for use by the Village, The following sections reinforce this opinion based on the three areas of risk; cost, schedule, and level of service. Cost The Villagc has placcd a high priority on cost. lt may be the deciding factor as to whether this project moves forward or not. We understand the question may arise whether using a CMAR will raise or lower the cost of the project. Having a very cost conscious group involved during the design process might lower the total cost of the projecl. However, by shifting the cost guarantee burden onto the CMAR, a case can be made that the actual savings may be less than promised if the CMAR is too conservative and risk-averse. There are studies that indicate a substantial savings in cost growth (fewer change orders) through use of CMAR, but no reliable information on comparative initial cost for similar infrastructure projects, This is mostly due to owners not buikiing the exact same project twice under different delivery methods. While the cost savings potential exists, there is no guarantee it will cost more or less than any other delivery system. The CMAR pro¡ect delivery method requires the least number of owner employees to manage the process because the CMAR can expand to meet the owner's staffing needs. While not reflected in the GM? the Phase 1 Mixed Use Commercial/ Single and Multi-Family Residential Undergrounding, Village Communications, Street Lighting, Stormwater High Phase 2 Mixed Use Commercial / Single and Multi-Family Residential Undergrounding, Village Communications, Street Lighting, Stormwater, Watermain Replacement Very High Phase 3 Mixed Use Commercial / Single and Multi-Family Residential Undergrounding, Village Communications, Street Lighting, Stormwater, Watermain Replacement Very High Phase 4 Single-Family Residential Undergrounding, Village Communications, Street Lighting, Watermain Replacement High Major Work ElementsLand Use Community lmpacts Project Area 72 reduced owner personnel required to manage the efforts of the CMAR is a cosl savings that needs to be considered. The CMAR process offers the Village "open book" transparency on how the construction price is developed. All of the subcontractor bid proposals, CMAR overhead, project management, profit, and contingencies are clearly identified, shared wiih the Village, and agreed upon before the work begins. This also allows the Village to know the full project budget, unlike the DBB method where budget issues may not be discovered untilwell into the construction process. As compared to other pro¡ect delivery methods, the Village maintains a greater degree of control over the construction budget and use of any contingency funds. Change orders are inevitable in any underground i nf rastructu re project. Wh i Ie u pfront su b-su rface i nvestigation miti gates this risk, it cannot eliminate the risk. ln a DBB project delivery the owner and design professional work together to manage the rising project cost due to change orders on the project. ln a CMAR project delivery ihe owner and design professional work together to preserve the construction contingency, which ultimately lowers the final cost of the project, A cosl advantage may be achievable through the Village's direct purchase of materials, which can be streamlined through use of the CMAR procurement method. The CMAR can coordinate these efforts directly, retain responsibility for accepting delivery storage and installation of these materials while achieving tax savings for the Village. Kimley-Horn's history with this delivery method has been positive with projects being completed on-time or ahead of schedule and under the negotiated GMP. When the cost of the prolect is less than the GMP, the contingency funds are returned to the Village. Schedule Schedule is very impoftant to the Village due to pressure from FPL to covert overhead lines or risk FPL moving foruvard with their storm hardening efforls. Because this is a phased program, a substantial delay in one phase can impact the ability to begin construction in a subsequent phase. These delays can create a domino effect that can impact the overall 7.0 PROJECT DELIVERY METHODS program schedule. This can lead to increased costs due to labor/material price increases over time. CMAR has the ability to fast-track certain activities. Working with the design team, elemenls of the project design can be completed early so construction of those elements can commence in an expedited manner. This can be advantageous for infrastructure elements such as water and drainage improvements that may need to be constructed in advance of the undergrounding infrastructure due to sequencing requirements. Additionally, schedule compression may allow flexibility when it comes to installing cedain prgect components at certain times of the year, thus facilitating a successful pro¡ecl completion. For example, highly disruptive roadway impacts are more desirable in the summer months when traffic volumes are typically at their lowest. As part of a lessons learned approach, there are also technical reasons for performing certain construction tasks at certain times of the year. Feeder transitions from the overhead to the underground system at the phase boundaries are much more desirable in the winler time when electrical demand is low. Performing these transitions during the hotter months can drive up costs because the process becomes more complicated to execute. By obtaining constructability comments and perspectives from the CMAR during the design process, the Village can achieve schedule efficiencies that are not available under traditional DBB. Reducing the schedule duration will reduce the cost of the general conditions on the prolect, Level of Service Although noi identified by the UUTF as a high priority, a major criterion in choosing a project delivery method for this program is the delivery method's ability to accommodate the needs of various stakeholders in a complex environment. The Village works very hard to protect lhe interests of the community. A high level of service and responsiveness to community needs, desires, and concerns is considered very important. The undergrounding program is fundamentally different than most Village projects in that the work is not confined to Village prope{y or the public KimleyDHorn 73 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN right-of-way, The Village's contractor will be required to perform work on nearly every private property in the Village, lt is imperative the Village's contractor perform work urr privale pruperly in a manner that minimizes the disturbance to that property to reduce the risk of property owner claims against the Village and pro¡ect cost escalation. The ability to deliver the level of service to the community they expect best aligns witlr the CMAR rnethoci. Because the CMAR selection process has a qualifications component, their reputations are very important to them. They are highly motivated to do a good job for their client as they are typically desirous of winning the next prolect for the same client. Additionally, because the Village retains a great deal of control over the actions of the CMAR, when the need for change arises, as ii often does with private individuals, it can easily be implemented by the CMAR. Since the CMAR is ultimately responsible for the schedule and the budget, they will generally bid the trade elements to subcontractors who are qualified and bondable, plus the CMAR has confidence will construct their scopes of work successfully. This enhances the quality of the work and reduces the risk that either the design professional or utility owner will reject the work, Work that is rejected and must be redone can pose a significant schedule risk in addition to quality concerns, Another advantage of this method is that the CMAR is far less likely to develop an adversarial relationship with the Village during the course of the project. This results in a construction team that is motivated to perform well for the Village, resolve issues quickly and cost effectively, and maintain a positive working relationship so they can continue working with the Village on future projects. A lawsuit resulting from poor pedormance or claim on a project of this magnitude could have significant schedule and cost impacts. 74 7.0 PROJECT DELIVERY METHODS ;1: i:xf:-t{jqd KimleyDHorn 75 f oooo apter 8) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) RISK ASSESSMENT A project on the scale of the Village of Key Biscayne's Overhead to Underground Ut¡l¡ty Conversion will inherently involve risks. Risks for a project of this type generally are categorized in two ways: 1) risks to project budget and 2) risks to prolect schedule. Part of the intent of the master planning process is to identify risks to the project ahead of project design and construction to be prepared to mitigate those risks throughout the course of the prgect. Schedule Risks Design and Preconstruction Phase The design of an overhead to underground conversion project involves parties who are not contractually obligated to the Village to meet a design schedule, AT&I Comcast, and FPL will each need to produce detailed design documents of their underground communications and electrical networks that will be used by the Kimley-Horn design team to create the conduit plans and ultimately bid documents for construction of the prolect. Since these utility owners are not under contract with the Village, there will be limited control over their design schedules. ln the event of a delay, there will be limited recourse for the Village. While it is aniicipated each utility owner will be able to provide a schedule and will work to meet that schedule in conjunction with the rest of the design team, there is the potential for delays to occur beyond the control of the Village or Kimley-Horn. For example, in the event of a major weather event, such as a hurricane, utility owners may allocate all resources to recovery efforts, including design team members, causing a delay to the project. Therefore, the need to incorporate these utility owners in the design process because of the proprietary nature of their networks is considered a negative schedule impact risk. As part of the conversion process numerous new easements will be needed throughout the Village to place ground-mounted equipment for both electrical and communications networks. Each easement will require coordination with the impacted property owner and may also entail a difficult negotiation process, particularly in the case of seasonally absent owners or those unwilling to grant an easement. The Village could employ an eminent domain process to obtain easements required for the work, however, that process can be particularly lengthy and significantly impact both the cost and schedule. Bid Phase During the bid phase of the project the primary risk to schedule will be re-bidding the project if not enough qualified, competitive bids are received. This may be particularly true in a strong construction market with significant demand. There are several potential contributing factors, including ambiguities in the bid documents, perceived or actual risks, and limited numbers of local contractors qualified for the work, As a result, bids received may exceed the project budget, and in an effort to obtain more competitive bids, the project may be re-designed and/or re-bid, having a negative schedule impact. Construction Phase During the Construction Phase of the project there are a number of factors that can contribute to project delays. The Village has varying degrees of controlto mitigate these risks. The anticipated schedule risks during the construction phase include, but are not limited to: J KimleyDHorn 77 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES _ MASTER PLAN Contractor's staffing, use of subcontractors, and equipment reliability as these will impact the ability of the Contractor to meet the project schedule Coordination with various utility owners required during the Construclion Phase of the pro¡ect who will pedorm certain portions of the work, as well as their execution schedule for such work. For example: ) AT&T and Comcast will not allow any crews other lhan their own to install their cabling and equipment. > During aerial cabling and utility pole removal, coordination with various utility owners will be required. This work must be performed by the utility owners and cannot commence until all underground systems are installed and all services have been converted to underground. Unforeseen conditions that can result in delays to the construction schedule as alternative designs are prepared to achieve project goals based upon the new information. Service conversions from overhead to underground connections for electrical and communications can be delayed by unwilling and/ or absent owners, Parlicularly for the reasons and in the situations listed below: > Communication service swaps can sometimes require attic access and must be per-formed by the utility company, > Propedy owners whose service entrance equipment does not meet the National Electric Cocle (NEC)will neeclto have these service entrances replaced prior to conversion. Weather conditions, including extended periods of rain, tropical storms, and hurricanes, Weather events can disrupt construction by reducing the production rate of construction crews and/or delaying cerlain por.tions of the work. Additionally, utility owners prioritize the provision and restoration of service to existing customers and will abandon a conversion project until recovery efforts are complete after a storm. 78 S Mashta Drive looking northwest Schedule Risk Mitigation Design and Preconstruction Phase As utility owners do not have the same contractual obligations to the Village as the design team, it is padicularly impoftant to develop methods to mitigate the risk they present to the overall project schedule. To mitigate this risk, it is recommended the Village initiate design ol multiple, separate work areas at one time and overlap phase schedules so the impact of a delay in the design of a single phase on the overall project schedule is reduced, By having multiple phases with multiple work areas per phase, the portion of the Village in active construction at any given time is small relative to the project size, therefore reducing the perceived impact to the community at any given time while providing schedule control benefits to the Village. By overlapping the phases, the utilities can design future phases while construction work is active in a previous phase. This provides additional time not only to complete the design work, but to identify and procure equipment easements. This reduces the risk to the overall pro1ect schedule if the design of any single phase is delayed due to storm recovery efforts. Certain significant pieces of equipment required for completion of the project have limited flexibility where they can be located in the final design of the underground system. An example would be a switch cabinet that marks the limit of a service area boundary defined by electrical load demand. Since these pieces of equipment must be located in ceftain areas, a longer duration to acquire the easement may be necessary if property owner negotiations or an eminent domain process are needed. ldenlifying these locations early in the planning and design process provides extended periods of time to acquire required easements prior to each project area going into construction. To mitigate the risk of unforeseen subsurface conditions impacting construction and to properly plan for the installation of the electric and communications infrastructure, we recommend record drawing research and soft dig utility locates be performed for known and identifiable utilities during the design phase. As a result, the risk of underground utility conflicts leading to schedule delays and construction claims is reduced. This also increases the clariiy of the construction documents, which reduces risk to potential bidders and allows for lump sum bidding for various scopes of work. Lump sum bidding can be employed on infrastructure projects when the scope of work is clearly defined and the risk of quantity overruns is low. Unit price bidding is tradiiionally used on projects where quantities are likely to change because precise estimates cannot be made. Construction Phase To mitigate the risk the chosen contractor fails to perform the work within the desired schedule, we recommend: requiring bidders submit historical evidence with their bid proposal to demonstrate past success in meeting schedules on similar projects requiring bidders submit references with their bid proposal the Village can contact to discuss schedule performance on past similar projects engaging a Construction Manager who has the authority to remove and replace poor performing subcontractors and/or to bring in additional resources when threats to the project schedule are identified. 8.0 RISK ASSESSMENT 1 Kimley))Horn 79 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Having the Village's selected contractor perform most of the work is the best method to guarantee work is performed in a timely manner. Because the Village's selected contractor has a strong and direct contractual obligation to meet an agreed-upon schedule, the risk of schedule impacts caused by the contractor are reduced. To reduce schedule risk posed by elernents of construction that must be performed by the utility owners it is critical a detailed construction schedule clearly identify whcn thc activitics arc rcquired during the project and their duration, All dates and durations must be clearly communicated to the utility owners and the Village must obtain a commitment to those dates [r<¡¡lr the utility owners prior to the commencement of each phase. Coordination meetings should be held on a regular interval and should include the utility owners. At these meetings any schedule or sequence adjustments made should be discussed and coordinated. Experience has shown employing a well-qualified Construction Manager has been extremely beneficial in facilitating this process. Some levelof unforeseen conditions can be expected with any project of this scale. When unforeseen conditions do arise, it is important the design team, construction team, utility owners, and Village work togeiher on developing solutions as quickly as possible to avoid schedule impacts The team's focus should remain on development of a solution until the unforeseen condition is overcome to minimize or eliminate schedule impacts. During previous projects the service conversion process has presented challenges when absentee and/or unwilling property owners are encountered. To compound the challenges, communication companies consider their customer information to be confidential, which often makes it difficult for outside entities, including the construction team or owner, to contact absentee properly owners and/or discussing concerns with unwilling property owners. Having a strong public outreach component that proactively reaches all property owners offers them an-understanding of the prolect and how they will be individually affected is recommended. This will mitigate the risk delayed service conversions on the part of individual propefty owners cause delays to the overall project. Performing this outreach continuously and early also aids in identifying where problems may be encountered in the future so proactive actions can be taken. When an owner's service entrance does not meet the National Electric Code, it will need to be upgraded prior to service conversion process. To reduce the impact of delays caused by this condition the following process is recommended: During the desigrr plrase a review of all rneters shall tte peflorrled to determine ''",hei'e code issues rnar- exist The Village can then notify these property owners that their service entrances need to be upgraded in advance of the project along with instructions on how to initiate the work lf by the time construction begins the work has not been completed by the property owner, we recommend the construction contract include an allowance line item for the Village to perform this work on behalf of the property owner Finally, the associated costs should be assessed against the propefi by the Village After service conversions are completed, the de-energized overhead wires and poles must be removed by the utility owners. This type of work is considered very low priority for the utility companies and they will demobilize from the projecl if they are needed to respond to another service repair or recovery effort elsewhere in the system, presenting a I 80 schedule risk for the project. Experience has shown that pressure applied by municipal leadership on the utility companies can be effective in expediting this process. A diligent Construction Manager has also been effective in keeping the process moving forward. Weather conditions, padicularly in South Florida, can present a schedule risk that is both difficult to anticipate and difficult to mitigate. Significant storm events will not only hamper the efforts of the Village's conlractor but utility owners will shift focus away from the conversion project and onto recovery efforts in the aftermath of a storm. Work by utility owners will not resume on the conversion project until their individual recovery efforts are complete, which can take varying amounts of time depending upon the magnitude of a storm event, Utility owners may also choose to use stockpiled materials intended for conversion projects in the recovery efforts and restock those materials only after recovery efforts are complete, To mitigate this risk, the Village could request FPL provide materials for an entire phase area at the onset of the phase's construction, However, this would require the Village provide a location to store these materials in a secure environment, The storage location would need to consider some of the materials needed for this project will need to be stored to avoid exposure to the elements. For example, the underground conduit may not withstand prolonged exposure to ultraviolet rays and would need to be covered or stored indoors, The Village may wish to explore warehouse/ storage yard rentalto evaluate whether it would be worth the associated costs to mitigate against the risk to schedule. Budget Risks Design and Preconstruction Phases While cost overruns could potentially occur during the design phase, the risk is relatively small, parlicularly given the size of the project. The most likely scenario for design phase cost overruns would be a change or addition to the overall project scope by the Village. As previously discussed, the project will require the acquisition of numerous easements over the course of desígn and implementation. Each easement has the polential to add easement acquisition costs. These costs may come in the form of staff labor, consultant labot legal fees, and potentially agreements with property owners in the form of redesign, additional landscaping, etc. During a project of this magniiude it can be expected that some easements may need to be acquired through the eminent domain process. This process can be expensive and is difficult to quantify a budget for such expenses since the number of eminent domain processes that may be required over the life of the program cannot be accurately predicted. Construction Phase As with project schedule, the construction phase is where most budget risks to the project are found. These risks include, but are not lirnited to: Delays in the project schedule can lead to delay claims where the contractor seeks additional compensation, and when delays to the prgect are significant the impact of inflation can become significant relative to project budget. Material costs can vary significantly over the lenglh of a project of this scale. For example, an increase in oil prices can drive material and equipment costs up. The cost of petroleum based items such as asphalt, as well as HDPE and PVC conduits would increase along with fuel costs for the construction equipmenl with an increase in oil prices. Local and national economic and construction markei conditions can also influence project costs, When demand is high and potential bidders are busy, labor and material prices are likely to be higher than when the industry is slow and there is increased competition to drive prices down. Unforeseen sub-sudace conditions including unknown/unmarked utilities, unsuitable soils, contaminated soils, and/or rock conditions can all add cost to the construction of the prolect. During the course of the pro1ect there may be the need to implement specific landscaping requirements or specialized pavement and driveway restoration due to unavoidable impacts lo existing elements or as a means to secure a required easement or other private property impact. These special considerations can add cost to the prolect. I B.O RISK ASSESSMENT ) ) ) Kimley)>Horn B1 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES _ MASTIR PLAN The addition of any previously unbudgeted costs for replacements or improvements necessitated by the undergrounding program. For example, the replacement of existing street lighting that is currently installed on overhead utility poles. Utility owners will also encounter some of the same budget risks, and to the extent increased labor and material costs can be passed along to the Village, it is expected they will do so. Construction Phase Project schedule delays generally correlate with budget impacts, therefore quickly resolving any delays and closely managing schedule are a good mitigating measure for budget control on the project. There are.sef,/eralways to mitigate increases in material costs tha.t rna.y þs experienced during the project. Schedule control is important, since material prices can fluctuate over time but generally will increase due to inflation. This project offers a unique opportunity for the Village to direct purchase materials in large quantities to achieve both volume pricing and tax advantages. For example, conduit and HDPE piping can be purchased directly by the Village using their tax-exempt status to save the sales tax. The contractor can receive bids for these materials from suppliers with purchase orders being issued directly by the Village. This allows the contractor to remain responsible for the coordination and delivery of these materials, therefore reducing the risk of the Village becoming responsible for nrairrlainirrg an adequate flow of materials to the contractor. As previously discussed, market conditions can influence project costs both positively and negatively. While the Village cannot control market conditions, action can be taken to encourage competition among potential bidders for each of the bid packages, providing incremental benefits to the project cost. One approach is to hold an industry forum with members of r Budget Risk Mitigation Design and Preconstruction Phase During the preconstruction phase, one of the larger budget risks is tied to the easement acquisition process. Property owners unwilling to dedicate an easement for necessary equipment on their property may necessitate the Village commence with eminent domain proceedings to complete the project. This process can be expensive and time consuming. To mitigate this risk, adequate time should be allowed within the project schedule to discuss and alleviate concerns with impacted property owners. Another mitigation measure is to exercise flexibility in the size, shape, and location of easements obtained for equipment to aid the negotiation process. Where possible, equipment should be located in the right-of-way to avoid the need to procure an easement altogether. Where the equipment must be placed within private property due to design and space constraints, it is helpful that the person(s) discussing proposed easement locations with property owners understand the flexibility available to the design team for relocating equipment to facilitate quick negotiations during the preconstruction phase. During the design phase the construction documents should undergo a value engineering process to identify potential reductions to construction costs. The Kimley-Horn design team includes team members with experience in the power and communications distribution industry who can review not only the supplementary conduit plans being produced by Kimley-Horn, but also the network designs produced by FPL, AT&T, and Comcast. The intent of these reviews is to provide assurances the network designs do not contain unnecessary upgrades, are efficient, and are a "like for like" overhead to underground conversion design. 82 the contracting community to generate interest in bidding the packages as they are adveftised. lf the Village were to pursue a Construction Manager at Risk (CMAR) procurement method, it is recommended the Construction Manager(s) be procured on a competitive basis. Encouraging competition among interested parties provides a measure of mitigation against rising construction costs in a growing market. It is recommended that geotechnical explorations, record drawing research, and subsurface utility locating be performed during the design phase, This will reduce the risk of unforeseen subsurface conditions being encountered during the construction phase, for example : unknown/unmarked utilities, unsuitable soils, contaminated soils, and/or rock conditions. Unforeseen subsurface conditions cannot be completely eliminated, but this initial investment will eliminate the majority of conflicts that othenn¡ise would have arisen had this exploration and research not been performed. Since encountering unforeseen subsudace conditions is inevitable on any urban underground infrastructure project, it is imperative the design team, construction team, and Village stay focused on a solution for any given conflict until the problem is resolved. When the project team is able to quickly determine a solution in a non-adversarial manner, costs due to the conflict are generally minimized. Specialized drilling equipment can be employed io limit surface disruption, which can minimize the risk of increasing restoration costs due to specific landscaping requirements or specialized pavement and driveway restoration costs. While horizontal directional drilling is generally a costlier installation method than open cut trenching, lhe savings in specialized restoratlon costs can sometime make it a more cost-effective approach to complete the pro;ect. Entry and exit pits for each segment of installation are still required, meaning excavation is not completely eliminated, but it is significantly reduced and can be planned in a way that avoids the areas with the costliest restoration requirements Pits will also need to be excavated in locations where conduits make sweeps or connect to above grade equipment. Horizontal directional drilling is most useful when installing conduits in a long straight line. Horizontal directional drilling presents a risk of hydrofracture ("Frac-Out") occurring. Hydrofracture causes areas above the drilling location to depress along the drilling line along with the release of drilling fluids to l ) ) ) ) ) ) ) ) .¡l ¡!t1,'i ¡t 8.0 RISK ASSESSMENT Kimley)>Horn 83 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN the surface. Certain soil conditions and shallow drilling depths increase the likelihood of hydrofracture. By planning conduit routing properly and using deliberate decision making regarding when it is appropriate to employ horizontal directional drilling, the risk of increased restoration costs can be mitigated. ffi ;îi;:i;#;:,:ïä ffi :îffi*:ä ;*" ;ää""' in a given area. l-or this project, it is known the Village has separately budgeted infrastructure projects that could be programmed into the undergrounding project, Additionally, the Village has requested a number of aged Miami-Dade Water and Sewer Department water mains be replaced throughout the project areas. Our recommendation is to allow these Village infrastructure projects and those othenruise desired by the Village to share in the roadway restoration costs. This provides a benefit to both the Village and the other entities in that no single agency is responsible for the amount of roadway repaving they would be required to perform if they performed their project on a stand-alone basis. Another cost saving measure related to paving that can mitigate risks to the project budget is the deferral of milling and resurfacing until after a number of phase areas have been completed. ln this manner, miles of streeis can be bundled into a milling and paving bid package that will gain the inierest of the larger highway paving contractors and allow the Village to achieve volume pricing that only large paving projects can provide. During the project the Village may encounter improvements that are necessitated by the undergrounding program, such as replacement of street lighting currently installed on utility poles. The primary way to mitigate these costs is to review Village plans for infrastructure improvements and existing conditions within work areas to determine those elements most likely to be impacted by the undergrounding and determine planning level costs for each element. For impacted street lights not included in any separate Village replacement program, there exists an option to engage FPL to replace these street lights under their street lighting program. Within FPL's line of standard lighting, the Village would be responsible for a nominal Cost in Aid of Construction (CIAC) of approximately $1,200 per pole, as well as operating costs, However, the standard line of FPL lighting is limited in selection and the Village would need to decide what fixtures and poles would be acceptable for use as an alternative to the lighting that is currently being installed under the Village's lighting program lf the Village desires to pursue FPL standard lighting, it is recommended this determination be made prior to beginning final design of the undergrounding pro¡ect. To miiigate the ¡'isk ihai inc¡'easing iaboi'and mate¡'ial cosis are passed on to the Village from the utility owners, we recommend two review activities occur during tlre desigrr plrase of eaclr portion of tlre prujecl. First, the design team should work with each utility owner during the design process to value engineer their network designs so the final design is an efficient and cost effective "like for like" system, so the Village does not become responsible for the costs of upgrading utility owner assets. Secondly, a review of the costs presented by the utility owners to the Village and design team should be performed to determine if it is reasonable, accurate, and provide a level of assurance that it does not contain costs for network upgrades or betterment, but rather only those costs to provide a "like for like" system. 84 B,O RISK ASSESSMENT a a\ ,-) .) 'ì ) ) ) ) ) ) ) ) ) ')'l -) ) ) ) ) ) ) ,) j ) ) J J J J J J J J J J J J J J 85 ,f Kimley>)Horn t o1 ù o i ' ,;ll.!.¡-¡¿.;-.*¡å¡;*l*- a. aF'6û f¡r¡¡¡lÊtiJ r. û:ütt¡L, '"rl¡ å F I o o o o o o o O o o * ,!i *. ¿'¡t*# t ,c -r- r'è î ¡ -lq h :-t / .{b, I o a o t t t -¡-q f a o o o o o O Q_--> a 4 f 5 ã ./r !#t \''-,,- ¿t- ';. t I I hapter I TRANSPORTATION MANAGEMENT PLAN A Transportation Management Plan flMP) has been developed to coordinate traffic impacts related to both the undergrounding program and other known significant infrastructure projects for each phase/year of the construction to minimize impacts to the residents and businesses. Based on the proposed undergrounding project phases and other known infrastructure projects (by the Village and others), Kimley-Horn has assessed the traffic impacts from construction for each phase of the project. The following section describes the methodology utilized to develop the TMB as well as overall guiding principles (general guidelines) for use by the Village and affected contractors during the implementation of the undergrounding program. The TMP is a specific set of strategies to manage the work zone impacts of a project. lts use may evolve over time, but its current role is to assist in the development of the design of construction phasing plans, iraffic control plans, and project specification documents, and to facilitate discussions between the Village, designers, utility owners, contractors, and other key stakeholders related to traffic impacts. lt should also be used by the Village as a tool during the maintenance of traffic (MOï) permitting process to better coordinate construction traffic impacts as specific permits are applied for by the construction community. Graphics and/or boards of the proposed TMP strategies are recommended for use during the public outreach process. An overallTMP, as well as general traffic control guidelines for the program, were also developed. The TMP strategies follow standard MOT guidelines, schematic in nature, and are displayed on GIS maps in this section. Fufther communication with the following stakeholders is recommended as the TMP evolves throughout the implementation of the program: Þ Village of Key Biscayne Police Department Þ Village of Key Biscayne Fire Department þ Village of Key Biscayne Publíc Works Department þ Village Manager's office Þ Undergrounding Utilities Task Force þ Village Council þ Utility companies (FPL, AT&T, Comcast, Hotwire) þ Outside utility providers: Miami-Dade County Water and Sewer Department, Miami-Dade Public Works, AmeriGas, and American Traffic Solutions þ Various Key Biscayne Homeowners Associations Þ Commercial businesses: (i.e. commercial district businesses, hotels, country clubs, etc.) 9,1 Roadway Network The roadway network within the Village is described below. The main north-south thoroughfare is Crandon Boulevard that connects the Village with the mainland through the Rickenbacker Causeway to the north and ends at the Bill Bags Cape Florida State Park entrance. I \ ¡ ) ) ,) ) ) ) ) ) ) STAKEHOLDER - COM M U N ICATION CONTACTS ,J Kimley))Horn 87 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN West of Crandon Boulevard, Harbor Drive circulates as the westernmost north-south thoroughfare connecting to Mashta Drive on the south. Mashta Drive is southernmost east-west thoroughfare and the only entrance to Mashta lsland. From Harbor Drive to Mashta Drive, Fernwood Road runs parallel to Crandon Boulevard. A series of traffic calming circles and raised intersections are present throughout the residential network. East of Crandon Boulevard a variety of local roads provides access to the multi family rcsidences and hotels. The rest of the Village is comprised of local residential, commercial, or mixed-use roads. 9.2 Traffic Conditions Prior to Start to Work Traffic Volume Data Tiaffic counts, road capacities, and Levels of Service (LOS)for 11 major road links are presented in the counts, collected on at least two weekdays in either April or March of 2015. This was the most recent traffic data available for the Village, A location map of the 7 1 different roadway link locations is provided at right. The data contained the peak season 2015 traffic count data presented in a series of tables per location. The highest volume identified was used for analysis for three scenarios: daily, AM peak hour, and PM peak hour. After careful review, some abnormalities were found at two of the links in comparison with adjacent locations (location 6 and 7). Therefore, as construction is expected to start in 2020, more updated traffic data is recommended to be obtained. Tables 1 , 2, and 3 on the following pages contain traffic volumes, roadway classes, capacities (adjusted as per FDOT criteria in the 20.13 Quality/Level of Service Handbook), volume to capacity ratios, and LOS for the 11 links in each of the three scenarios. The overall trend on the island is the two-lane arterial roadways tend to have LOS C or better. Rickenbacker Causeway south of the toll has LOS B untiljust north of Harbor Drive where the roadway transitions into the developed region of the island and changes from Rickenbacker Causeway (SR 913) to Crandon Boulevard. Additionally, directionality is well-defined, with traffic generally heading onto the island in the AM peak hour and off the island in the PM peak hour,I 88 Rickenbacker Gauseway (At Toll) Rickenbacker Causeway (Bear Gut Bridge) Rickenbacker Causeway (At Golf Course) Rickenbacker Gauseway (At Tennis Center) Rickenbacker Gauseway (North of Harbor Dr.) Crandon Blvd. (Between Heather & Grand Bay Dr.) Crandon Blvd. (At Bill Baggs Park Entrance) Harbor Drive (Between W. Heather Dr. & Mclntyre sr.) Harbor Drive (Between W. Enid Dr. & Mashta Dr.) Harbor Drive (Between Wood Dr. & W, Mashta Dr Fernwood Road (Between W. Heather Dr. & Mclntyre @ o c @ c @ Eleven Roadway Link Locations 9.0 TRANSPORTATION MANAGEMENT PLAN l l ) Kimley,>Horn 89 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN Lesend - Phase I Phase 2 Phase 3 Pirase 4 lmpacted Roads Q Flasher $ Signat - Major Road _ Narrow Road, Use for One-Way Detour Only lf Needed Wider Road, Use forTwo-Way Detours As Needed - - Traffic Route Option - - Traffic Route Option B - - Traffic Route Option C -NOT IMPACïED ROAD Lo Lln. ..,x.. ¡À .,2 -.\poe' Dr Dr //aôo $¡ / ;i I E W'Palmwood ut Ln Dr m;D Sun Harbor Cir, I N Club o Þo Þ, or¿ró <Ò Masb@ ì\ DÈ\ \ N+0 450 900 1,800 q "t:\w E Feet ô^o S rest I ¡,,cLffgo 5e o Lt.älEIf.l il L I Cape Florida 90 TRANSPORTATION MANAGEMENT PLAN OVERALL MAP l J ) ) J ) ) ) I I ) ) ) \ ) ) ) ,: ) ) ) ) i I ) ) ) ) Table 1 Existing 2015 Daily Peak Season Level of Service (LOS) 4L ART DIVIDED 59,244 9.0 TRANSPORTATION MANAGEMENT PLAN o.74 c79,90074,400 0.801 Rickenbacker Causeway (at TolD B33,931 74,400 0.46 79,900 o.422Rickenbacker Causeway (Bear Cut Bridge) 4L ART DIVIDED 74,400 o.47 79,900 0.43 B3Rickenbacker Causeway (at Golf Course) 4L ART DIVIDED 34,729 0.45 79,900 o.42 B4Rickenbacker Causeway (at Tennis Center) 4L ART DIVIDED 33,428 74,400 0.45 B4L ART DIVIDED 35,673 74,400 0.48 79,9005Rickenbacker Causeway (Just north of Harbor Dr) t¡32,400 0.05 33,800 0.05 c6Crandon Boulevard (between E Heather & Grand Bay Dr) 4L ART DIVIDED 1,664 15,540 1.55 16,380 1.47 F7Crandon Boulevard(2) (at Bill Baggs Park Entrance) 2L ART DIVIDED 24,A85 12,480 0.30 c2L ART UNDIVIDED 3,789 lt 11,840 o.32IHarbor Drive(1) (between W Heather Dr & Mclntyre St) 4.24 c2L ART UNDIVIDED 3,006 il 84011 o.25 12,480IHarbor Drive(1) (between W Enid Dr & W Mashta Dr) il 11,840 4.21 12,480 o.20 C10Harbor Drive(1) (between W Wood Dr & W Mashta Dr) 2L ART UNDIVIDED 2,540 0.28 12,480 o.27 c11 Fernwood Road(1) (between W Heather Dr & W Mclntyre St) 2L ART UNDIVIDED 3,366 11,840 (1) Based on FDOT Class ll Roadway with 2jo/o capacity reduction for 2-lane undivided roadway without exclusive turn lanes. (2) Based on FDOT Class ll Roadway with 5% capacity increase for 2-lane divided roadway with exclusive left turn lane. (s) V/C = Volume to Capacity Ratio Location No. 2015 Daily Volume Roadway Class vtc Ratio Daily Gapacity vtc Ratio Existing Daily LOSFacility TypeStreet Segment Daily c LOS ELOS D ,J Kimley>)Horn 91 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Table 2 Existing 2015 AM Peak Hour Peak Season Level of Service (LOS) 0.61 cEB0.65 1 Rlckenbacker Causeway (at ïcll)WB 2,392 1,481 4L ART DIVIDED 3,660 0.40 3,940 0.38 B NB 1,257 0.34 o.32 B2Rickenbacker Causeway (Bear Cut Bridge)SB 4L ART DIVIDED 1,376 3,660 0.38 3,940 0.35 B NB 1,276 0.35 0.32 B3Rickenbacker Causeway (at Golf Course)SB 4L ART DIVIDED 1,358 3,660 o.37 3,940 0.34 B NB 1,270 0.35 0.32 B4Rickenbacker Causeway (at Tennis Center)SB 4L ART DIVIDED 1,350 3,660 0.37 NB 1,399 0.85 0.34 0.82 B D5Rickenbacker Gauseway (Just nodh of Harbor Dr)SB 1,630 0.76 3,940 1,700 0.73 D NB 1,243 102 0.06 0.06 cbCrandon Boulevard (between E Heather & Grand Bay Dr)SB 4L ART DIVIDED 4L ART DIVIDED 51 1,630 0.03 1,700 0.03 c NB 814 1.03 0.97 E7Crandon BoulevardP) (at Bill Baggs Park Entrance)SB 2L ART DIVIDED 953 7BB 1.21 840 1 .13 F NB 165 o.28 0.26 cB Harbor Drive(1) (between W Heather Dr & Mclntyre St)SB 2L ART UNDIVIDED 137 600 o.23 640 0.21 c NB 128 o.21 o.20 cHarbor Drive(1) (between W Enid Dr & W Mashta Dr)SB 2L ART UNDIVIDED 107 600 0.18 640 0.17 c NB 100 0.17 0.16 c10 9 Harbor Drive(1) (between W Wood Dr & W Mashta Dr)SB 2L ARÏ UNDIVIDED 109 il 600 0.18 640 0.17 C NB '189 0.32 0.30 c11 Fernwood Road(1) (between W Heather Dr & W Mclntyre St)SB 2L ART UNDIVIDED 143 600 o.24 640 4.22 c {1) Based on FDOT Class ll Roadway with 20% capacity reduction for 2-lane undivided roadway without exclusive turn lanes. (2) Based on FDOT Class ll Roadway with 5% capacity increase for 2-lane divided rcadway with exclusive left turn lane. (3) V/C - Volume to Capacity Ratio Location No. Facility Type 2015 AM Peak Hour Volume Roadway Class Peak Hour Capacity vtc Ratio vtc Ratio Existing Peak Hour LOS Peak HourDirectionStreet Segment LOS ELOS D 92 I 1 Table 3 Existing 2015 PM Peak Hour Peak Season Level of Service (LOS) 9.0 TRANSPORTATION MANAGEMENT PLAN 0.58 c ) ) ) ) ) ,) ) ) ) ) ) I ) o.62EB3,660 2,284 2,660 0.73 3,940 0.68 c Rickenbacker Causeway (at Toll)WB 4L ART DIVIDED 0.35 B1,393 0.38NB 3,940 0.31 BSB 4L ART DIVIDED 1,211 3,660 0.332Rickenbacker Causeway (Bear Cut Bridge) 0.38 0.36 BNB1,409 3,660 0.33 3,940 0.30 B3Rickenbacker Causeway (at Golf Course)SB 4L ART DIVIDED 1,190 B1,390 0.38 0.35NB 0.30 B 4L ART DIVIDED 1,188 3,660 0.32 3,9404Rickenbacker Causeway (at Tennis Center)SB 0.88 0.84 DNB1,431 1,630 0.73 '1,700 0.70 D Rickenbacker Causeway (Just north of Harbor Dr)SB 4L ART DIVIDED 1 ,191 il5 c970.06 0.06NB c102 il 1,630 0.06 1,700 0.066Crandon Boulevard (between E Heather & Grand Bay Dr)SB 4L ART DIVIDED 1.13 FNB9501.21 1 .15 840 1.08 FSB 2L ART DIVIDED 905 il 7887Crandon Boulevarde) (at Bill Baggs Park Entrance) 0.34 0.32 cNB206 c151 600 0.25 640 0.24IHarbor Drive(r) (between W Heather Dr & Mclntyre St)SB 2L ART UNDIVIDED 0.28 c1770.30NB 640 0.19 cSB 2L ART UNDIVIDED 122 il 600 o.20IHarbor Drive(1) (between W Enid Dr & W Mashta Dr) o.26 0.25 cNB157 il 600 o.21 640 0.20 G '10 Harbor Drive(1) (between W Wood Dr & W Mashta Dr)SB 2L ART UNDIVIDED 127 c2030.34 o.32NB 0.26 c 2L ART UNDIVIDED 164 il 600 0.27 64011 Fernwood Road(1) (between W Heather Dr & W Mclntyre St)SB (1) Based on FDOT Class ll Roadway with 20% capacity reduction for 2-lane undivided roadway without exclusive turn lanes. (2) Based on FDOT Class ll Roadway with 5% capacity increase for 2-lane divided roadway with exclusive left turn lane. (3) V/C = Volume to Capacity Ratio Location No. Facility Type 2015 PM Peak Hour Volume Roadway Glass vtc Ratio Peak Hour Capacity vta Ratio Existing Peak Hour LOS DirectionStreet Segment Peak Hour LOS ELOS D J KimleyDHorn 93 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN 9.3 Traffic Conditions During the Work To more precisely determine how construction activity will impact traffic in the project area, an evaluation of the construction activities for each type of work was completed. Not all construction activities will generate a large displacement of the current motorists. Three major traffic controlling ,.^^ i*^l^-^^+^l J, ,-:^^ ^^^^+-. .^¡:^^ ...:ll L^. .^ ^:^-:4^-.^r :..^- ^ -r-I I reqùursù l¡ | lvlçl I tsl ll(t\l \lul ll lV (/\Jl lùl,l UUl,l\Jl Mlll I lctvet è'lvl llllui:ll lL ll I lpAUtU on the traveling public. These include lane restrictions, shoulder closure, and shorl-ternr closurcs, Defour rcute altetr¡alrves ate slrcswn on the maps beginning on page 98. However, the timing, sequence, and implementation of closures and lane restrictions will be detailed in the maintenance of traffic plans provided by the contractor during the construction process. This allows the contractor the freedom to construct the project in the way they determine is the most efficient for their operations. Lane Restrictions Multiple Lane Restrictions: Multiple lane restrictions consist of prohibiting any traffic from entering or exiting a portion of roadway in a defined direction of travel (i.e. northbound or southbound)for an established construction zone length and quantitative duration. The multiple lane restriction uses full lane closures to complete construction tasks while maintaining operational lanes for conveying traffic flows. Once the construction is completed within the initial porlion of the roadway, the traffic control is "flipped" or modified, shifting traffic onto the previously impacted lanes and closing the remaining lanes for construction activities. This type of lane restriction can be accomplished with signage and barricades or with construction flagmen, depending on the duration of the restriction. Weekend Closure: Weekend closures are traffic control measures that restrict or close travel lanes for an entire weekend. ln most applications, a weekend is considered 9:00 p.m. Friday evening to 5:00 a.m. Monday morning. Weekend closures are installed using barricades, vertical panels, flashing arrow panels, truck mounted attenuators, and the appropriate construction signage lo convey the maintenance of traffic. Weekend closures should be scheduled to avoid peak weekends where access and mobility throughout the Village is essential to the success and operation of any special event or holiday. Night-time Closure: Night-time closures are traffic control measures that restrict or close travel lanes for an entire night. Night-time closures are installed using cones, flashing arrow panels, truck mounted attenuators, and the appropriate construction signage to convey the maintenance of traffic. Night-time closures should be scheduled to avoid peak nights when access and mobility throughout the Village is essential to the success and operation of any special event or holiday. Construction aclivities arrlici¡rated to occur throughout the undergroundlng program that may use lane restrictions are: . Conduit installation (undergrounding) . Equipment and cable installation (undergrounding) . Pole and wire removal (undergrounding) . Watermaininstallation . Drainageimprovements . Street lightlng improvements . Pump station improvements The use of a multiple-lane restriction, weekend closure, or night-time closure will be determined during design and construction of each phase Shoulder Closure A shoulder closure consists of prohlbiting any traffic by public motorists from driving on lhe roadside shoulder in a defined direction of travel (i.e., northbound or southbound) for an established lengtlr corrstrucl"ion zone and quantitative duration. ln the case of the nofth-south thoroughfares, this closure will be applied in both the norlhbound and southbound directions of travel. The closures are anticipated to span the time required to complete the construction of facilities outside of the travel lanes and may reduce travel lane widths. However, they will not eliminate the use of any travel lanes. Construction activities using shoulder closures are: . Conduit installation (undergrounding) . Equipment and cable installation (undergrounding) . Pole and wire removal (undergrounding) 94 . Street lighting improvements . Pump station improvements Short-term Closure A complete direction closure consists of prohibiting any traffic by public motorists from entering or exiting the roadway in a defined direction of travel (i.e., northbound or southbound) for an established length construction zone and quantitative duration, ln the case of the north-south thoroughfares, this closure could be applied in boih the nofthbound and southbound directions of travel. Although not anticipated to be needed often for the undergrounding program, if necessary these closures could span a maximum distance of one to two blocks of roadway at a time and be restricted to a weekend time frame. ln lhe case of the main east-west arterials and the local residential, commercial or mixed-use roads, the need for their closure to traffic or availability for a detour depends on the width of the road. This is further evaluated below. 9.4 General Project Schedule and Construction Sequence The undergrounding of overhead utilities, namely electrical and communication (FPL, AT&I Comcast), is planned lo occur in four phases with starting dates lrom2O2O-2O23. Additionally, other improvements may occur during the same time as the undergrounding. These improvements could include the Village's CIB the Village's stormwater master plan improvements, and Miami-Dade County WASD watermain replacement. The Village's CIP improvements are small-scale projects planned to occur during each year of the program and may be performed in conjunction with the undergrounding. The Village's stormwater masler plan is a 1O-year phased program of improvements. The Village is considering accelerating those improvements to coincide with the undergrounding program, Miami- Dade WASD watermain improvements are planned to occur in conjunction with the undergrounding program and be confined io the undergrounding phase project area during any given year. These improvements were considered when recommending transportation management options. The following table has the anticipated construction sequence. See a/so Chapter 6 of this master plan, 9.0 TRANSPORTATION MANAGEMENT PLAN The initial construction activities in any given phase will include conduit construction by a mixlure of open cut trenches and directional boring along with the installalion of equipment and cabling. The final six months of any given phase will include the removal of the existing overhead poles and wires. Therefore, there will be an overlap when adjacent phases will experience construction impacts potentially requiring road closures near each other. Table 4 Anticipated Construction Sequence Since the focus of the program is the underground conversion of overhead utilities and known large infrastructure programs, private construction projects (homes and businesses) are not currently included in the major work elements, but could have some impacts to traffic behavior in the Village. ) ) ) ) ) ) ) ) Phase 1 Mixed Use Commercial/ Single and Multi- Family Residential Undergrounding, Village Comm unications, Street Lighting, Stormwater, Watermain Replacement 2020 Undergrounding, Village Communications, Street Lighting, Stormwater, Watermain Replacement 2021 Phase 2 Mixed Use Gommercial/ Single and Multi- Family Residential 2022 Elsewhere in Village Demolition and removal of overhead utilities from Phase 1 2023 Phase 3 Mixed Use Commercial/ Single and Multi- Family Residential Undergrounding, Village Communications, Street Lighting, Stormwater, Watermain Replacement Demolition and removal of overhead utilities from Phase 2 2023 Elsewhere in Village Phase 4 Single-Family Residential Undergrounding, Street Lighting, Watermain Replacement 2024 Demolition and removal of overhead utilities from Phase 3 2024 Elsewhere in Village 2025 Elsewhere in Village Demolition and removal of overhead utilities from Phase 4 Land UseProject AreaYear Major Work Elements Kimley>)Horn 95 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN It is recommended these projects be reviewed for traffic impacts with this TMP to coordinate impacts to the greatest extent practical. lt is not possible to predict private construction activities at this time. The Village's Public Works Department should use this TMP to guide them in the issuance of MOT permits and coordinate the efforts for private construction community within Village construction project areas. Once MOT permits are issued and the MOT measures are implemented in the field, the oporations should bc monitorcd closely for effectiveness, Observed issues should be corrected through appropriate modification of the approved MOT based on these observed operational conditions. 9.5 Traffic Control Considerations: Traffic Gontrol Gonsiderations on Main North-South Thoroughfares: The following describes the traffic control considerations on the main north- south thoroughfares through the Village. lt outlines restrictions to impacting these tlroroughfares atrd alternate routes if one of the thoroughfares were to be impacted for construction. The traffic control considerations on the main north-south thoroughfares are as follows: From Ocean Lane Drive to Mashta Drive, Crandon Boulevard, Fernwood Road, and Harbor Drive run parallel to each other > lmpacts to Fernwood Drive and Harbor Drive shall be minimized as much as possible. lntermittent closure of a single lane could be allowed if flag men are used or if two-way traffic can be maintained at alltimes. > Only two of the three roads can be impacted at the same time. lf either Fernwood Drive and Harbor Drive are impacted, Crandon Boulevard should be fully open to traffic > Fernwood Drive and Harbor Drive can be closed to traffic (open to localtraffic only) only if required, preferably for a single block at a time and for a brief period, Both roads should not be closed to two-way traffic at the same time. From Harbor Drive to N Mashta Drive, W Mashta Drive is the only thoroughfare to provide access to Mashta lsland; therefore, the roadway cannot be closed > Work to be conducted from the road shoulder without impacting lhe travel lanes > lntermittent closure of a single lane is allowed if flag men are used Traffic Control Considerations for the other Roads: The rest of the Village is comprised of a variety of commercial and local roads. We lrave classified them as follows for the purposes of maintaining traffic during construction : . Narrow road - use for one-way detour only if needed ' Wider road - use for two-way detour as needed These are color codeci and separated in the maps beginning on page 98. The intent is to have available detour options as work occurs on the main roads (thoroughfares) and lhere is the necessity to detour traffic through the local roads. The local roads should always maintain access to local traffic and access to driveways. The exhibits provide suggested cross streets for transportation management based on field visits conducted in June 2018 to verify lane widths are adequate to accommodate the detoured traffic. lt should be noted that no singular cross street is recommended for a detour, and where possible, multlple adjacent roadways are recommended, By providing multiple options for the detour, the impact to the residential cross streets can be minimized, To promote drivers to use the earlier detour options and avoid the majority of drivers waiting until the last cross street before the road closure to detour, it is recommended variable message signage be provided so specific road names can be recommended for the detour. The specific timing and implementation of closures and lane restrictions will be detailed in the MOT plan to be submitted by the contractor. Specific conditions and recommendations contained in this TMP will be communicated to the contractor in the construction documents. The contractor shall always maintain access to local traffic and access to driveways. I 96 l ) Guidelines for others that occupy the roads: . Landscapers and other contractors should be restricted to parking on roads without lane closures, or are outside the affected work area, unless othen¡,¡ise approved by the Village . Other contractors should be restricted io working on roads without on-going undergrounding work, unless otherwise approved by the Village . Access to cyclists and pedestrians will be described in the construction documents for implementation by the contractor 9.6 Traffic-Relatecl Work Restrictions: The contractor shall maintain the same number of existing travel lanes and parking lanes in each direction open to traffic at all times, except as noted herein. Per the Village's noise ordinance, the creation of any plainly audible sound in connection with construction is only permitted from 7:00 am to 6:30 pm Monday through Friday. Therefore, no construction activities are permitted during nights, weekends, and holidays. Weekdays ' Mondays, Tuesdays, Wednesdays, Thursdays, and Fridays that are not Village holidays shall be considered weekdays. The day after Thanksgiving shall be considered a holiday, A "holiday weekend" shall be defined as the period between noon on the weekday before a holiday and noon on the weekday after a holiday. . Work will not be allowed on Village observed holidays. Full Closures or Partial Closures . Full or padial closures will be allowed during weekdays. . A full closure of the main norlhbound and southbound thoroughfares will not be allowed at the same time. . A full closure of any travel lane(s) that does not allow the maintenance of two-way travel at all times will require the use of flag men during the closure period. . A full closure of any travel lane(s) that will create a one-way travel direction, or complete roadway closure, will require advance approval from the Village of Key Biscayne Public Works Department 9.0 TRANSPORTATION MANAGEMENT PLAN Conflicting Closures . No two adjoining corridors may be closed in the same direction at the same time . No two corridors that act as alternates to each other may be closed at the same time Notification, Coordinat¡on, and Approval of Closures . Contractors must notify the Village Engineer at least one week in advance of any proposed closures. . An internalVillage of Key Biscayne communication representative shall coordinate all closure activity, This cotlld be the Village's project manager, r Any work requiring a closure will need to have an approved traffic control plan and corresponding MOT permit from the Public Works Depaftment. . All approved closures must be communicated to the Village on a weekly basis by the contractor during the week prior to the closure so the Village can include traffic alerts on the Village website or undergrounding website. . The Village will produce a weekly media alert for traffic impacts for the upcoming week. At the discretion of the Village a phone number may be published in these media alerts that allows impacted motorists to call and report observed issues with the MOT operations. . The Village's Public Works Department will coordinate closures among projects through lhe MOT permitting process and keep the community apprised of upcoming closure activities through media releases. . Field personnel need to notify the Village Engineer and Design Engineer of any cancellations or changes in closure schedules. . All roadway closures, material haul routes, and detours shall be approved by the Village of Key Biscayne prior to implementation. Material haul routes through the City of Miami and Miami-Dade County shall have appropriate agency approvals. . Contractor shall submit the details of the contemplated activities and related traffic impacts to the Village Enginee¡ City of Miami, ) ) ) ) ) ) ) .) ) ) Kimley>)Horn 97 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN and Miami-Dade County as needed to receive approval at least 21 days in advance of the contemplated activities that may impact those jurisdictions. Material hauls on local streets will be subject to the Village of Key Biscayne's requirements and local ordinances. After approval of traffic control plans and associated closures and detours on Crandon Boulevard, the contractor shall place advance closure notice information signs per Village of Key Biscayne and FDOT requirements and advise affected businesses, residents, and stakeholders at least two weeks in advance of impending approved closures. ln all cases where there are roadway impacts, the contractor shall assure access is maintained or otherwise provided to and from abutting properties. After approval, the contractor shall advise residents and businesses of any impending access restrictions, Full closure of roads in a manner that prevents access to residences and businesses will not be permitted. Temporary traffic control devices shall not be set up in advance of a closure unless approved by the Village. Upon completion of the closure, traffic control devices shall be removed from the roadways and shoulders by the end of the work day. The devices may not be left or stockpiled on shoulders or in clear zone areas. The conlractor shall provide schedules of daily activities and corresponding traffic control plans, This information shall be provided in advance and during construction progress meetings. The information provided shall specify the limits of ihe work activities and related traffic control plan by location, direction, and time. The construction schedule and associated traffic control plans shall be developed in a format suitable for release to other agencies and the public, and shall be updated as necessary. Contractors will remove all traffic controlfor temporary lane closures prior to holidays or weekends that adjoin a holiday, Lane closures that require an extended duration and are implemented with appropriate barriers, traffic control devices, and signage shall be allowed to remain in place during a holiday or holiday weekend. Special Events . Partial or full closures on corridors are not allowed when a special event occurs within that roadway corridor. Emergency Services . Field personnel shall coordinate with emergency services for any paftial closure where no shoulders are available. . Detour routes shall be communicated to emergency services on a weekly basis, or more frequently as the detour routes change. SpecialApproval . The Village Public Works Department must approve any exceptions, . Any requests for special exceptions shall be made with four weeks advanced notice to allow time for a thorough review and approval, if required. 98 9.7 Transportation Operations Plan Recommended strategies will be used to improve transporlation operations/safety within prolect work zones. Corridor/ Network Management Signaltiming changes shall be made when detouring traffic during lane closures. Police officers shall be utilized as needed to adjust signal timing to dissipate excessive backups. Signaltiming changes shall be made when detouring traffic during lane closures. Police officers shall be utilized as needed to adjust signal timing to dissipate excessive backups Signaltiming/ coordination improvements The speed reduction signs shall be installed at locations shown in the MOT plans. Speed Iimit reduction/variable speed limits Temporary traffic barrier Temporary traffic barrier shall be installed at locations shown in the MOT plans. Crash attenuators are not anticipated but shall be placed at locations proposed by the contractor to break temporary traffic barrier runs for access to work zone. Crash attenuators Type A warning lights shall be mounted on top of all construction signs as noted in the MOT plans. Type C steady-burn warning lights shall be mounted on all channelization devices during nighttime activities. Work Zone Safety Management Warning lights Signaltiming/ coordination improvementsTraffic/lncident Management and Enforcement Dedicated (paid) police enforcement DPS officers shall be used as needed for monitoring and flushing out traffic at signalized intersections along the approved detour routes. Responsibilities/Requirements/ Special Considerations Selected Strategies I % 9.0 TRANSPORTATION MANAGËMENT PLAN Kimley>)Horn 99 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN :TG ¡tl d op:.ttto Ê¡t U t rüÈ u (Ë ¡¡ Legend Phase I - lmpacted Roads i,, ,: Potential lmpacted Roads Narrow Road, Use for One-Way Detour Only if Needed Wider Road, Use forTwo-Way Detour Only if Needed Traffic Route OptionA Traffic Route Option B Traffic Route Option C o to¡¡ lwaYll.+l s Not lmpacted Road Major Road Flasher One-Way Signal n s I I I I , I I ONE ¡TAY l!€|!(t,o ar o CL Allend¿7u LakeVilla Dr Wdk Coconut Ln rand Bay Estates Cir Dr SunseÉ Harbo unr¡se-Þrb N Club o -cJHeoiou (1l oIo ì Mashta Dr Mashta Ct Grapetree \o'a N E 0 350 700rw 2ù Cape Florida Park BlvdS 100 TRANSPORTATION MANAGEMENT PLAN PHASE I MAP 9.0 TRANSPORTATION MANAGEMENT PLAN reenwood'Þr- o ar Lesend.........".-\b e- - @w&& o fıñEì lwaYll+l $ Phase 2 lmpacted Roads Potential lmpacted Roads Flasher One-Way fo filI r P z Signal Tiaffic Route Option Traffic Route Option B Traffic Route Option C Major Road Narrow Road, Use for One-Way Detour Only if Needed Wider Road, Use forTwo-Way Detour Only if Needed Not lmpacted Road ô tt ã (t Su Harb N 0' 350 700 J a çLot9 w E S VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN TRANSPORTATION MANAGEMENT PLAN PHASE 2 MAP KimleyDHorn 101 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN 700 ìl I I I I - W o s $ Narrow Road, Use for One- Way Detour Only if Needed Wider Road, Use forTwo- ¡' d I î Lô N r{urtleW¡l k& 0 tlg fil rJ w E S 102 TRANSPORTATION MANAGEMENT PLAN PHASE 3 MAP 'ì 9,0 TRANSPORTATION MANAGEMENT PLAN ì ) ) )-l I I ) ) ') ) ) ) ) ) ) ) ) ) ) ) _) ) .) .) ,*) ) ._,) J --) ) ) ,) ) .) ... ) J VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN orE W Palmwood Beechwood 'tt oo¡ E (ü 0. (Ð r!! ô ı€ Go Redwood Dr Oe 3'g Sr5 oSatinwood Dr !trs g! l"cl oEl äãJ t.3lf -^.,1-Elr- Enid Enid Enid Dr st Satinwood Dr c CLor E oÈô o l,tl AIlend¿7u Leeend - Phase 4 - lmpacted Roads O Flasher ffi one-Way * Signal Traffic Route Option Traffìc Route Option B Traffìc Route Option C Major Road Narrow Road, Use for One- Way Detour Only if Needed od W Matheso Dr Sunset Mashta Wider Road, Use forTwo- Way Detour Only if Needed Not lmpacted Road 9)( Mashta Ct Knollwood 'å!"Cape Florida oh N+0 350 700 1,400 ÞwE Feet S TRANSPORTATION MANAGEMENT PLAN PHASE 4 MAP KimleyDHorn 103 I I I !a il tt I / \':ñ, ?/ / I * I { t -a a €,, r r r,ir.,{6i,ittl\\.fli"'"lt ¡ '* I /.\/,'"a\rr?4.,ira'O 1 ..ril. I ,-' '/{b .. a 'Ja-,F '.t.t '-l a {F 'J\ r-i, 1r\ -- --À f.i ÈiN \'''- I a/'{lP fÞ.¡.t 4 'tl \I 1': -*--...- *øjlrir,l tt r,ft¡ç,¡ t , I..ïF , t \ \.r'- r,qf,q ,{l ' {Í.: :, tr,. ,l,r \r, Ç ì '¡ a t\ t' .J ?/r ¡ I \,./ ï t \ -'''-'i)'\' '*'rtt*\ n\ \¡ ,, t'$,'''I ì*- ,^'l ,/ ã ¡ \ la .. -\*"2q,{' ð.?:'t-,nt}¡-ir F,* ', lrl r -a ítl t a¡ t oo ao /,ooooooocooooaoooo -\ a ** l1 ,f fl J, ¡ t / ¿j ' .1 ,g t. l ¡I '. JÌ I rl Ii; I r t hapter 10 PUBLIC OUTREACH PROGRAM The undergrounding project in the Village of Key Biscayne will incorporate a Public Outreach Program to ensure the community is informed on the process, the benefits, and costs, The Community Outreach Program is a critical part of the public education and transparency efforts. lt will create a link between the engineering team, Village staff, elected leaders, the Undergrounding Task Force (UUTÐ, utility owners, Village residents, and the media. The program should include a "boots on the ground" approach ihat will engage the community and communicale through presentations, print and electronic media, public meetings, and a Speakers Bureau, This bureau would include the UUTF and other community stakeholders ínterested in receiving and disseminating information. The Community Outreach Program will need to have separate communication plans to ensure we are reaching both residents and businesses. These plans may include: The development of a project brand logo and tag line so residents can immediately identify communications related to this project. Community meetings with Village organizations and groups are involved in Village issues, such as the Key Biscayne Chamber of Commerce and Key Biscayne Historicaland Heritage Society. We will also meet with smaller, private groups who may express an interest in the undergrounding project. Village Hall-style meetings in coordination with the Key Biscayne Chamber of Commerce, and other local community or neighborhood groups, based on the project schedule and needs. Establishment of a Speakers Bureau and Community Outreach Program, Ensure surrogates who are interested in receiving information or disseminating information are provided regular briefings or talking points so they can share information to their members or contacts. Develop a separate outreach program for the multifamily residences east of Crandon Boulevard that focuses on meeting with condo managers and residents to provide them with factual information, leave behind materials in the condo office, and to connect with the unit owners about the project. Separate meetings and presentations can be provided as requested to address individual condominium, business, or neighborhood needs, with access to planning and engineering team members or Village staff. Setup and provide access to communication hotlines, emails and online forms that residents can utilize to address questions or concerns. During the construction phase of the project, specific communications can be made with affected residents and businesses to keep them informed of the progress and to coordinate how they may be affected throughout the construction phase. A public information team ready to respond to community questions and concerns. Village Communications The Village and UUTF will require regular communications with residents and businesses using various mediums to ensure regular updates are being delivered, The Speakers Bureau would be provided with talking points and messages they can use to share with their contacts. This includes the utilization of direct mail, email services, and online communications such as: I t ) ) ) ) ) ) ) ) ) ) ) ij fl ñ ) KimleyDHorn 105 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Consistent updates to the prolect website to provide fresh and new content 24/7, serving as a one-stop shop for project information and activities. Utilization of social media to share information. The undergrounding project has a Facebook page and the Village has a Twitter feed that can be used. Facebook and online ads about community presentations that are occurring can be posted to encourage pafiicipation. Email communications to share information, updates, or alerts that need to be quickly dispersed. Printing of direct mail, brochures, and fact sheets to provide residents information about the project. This includes the distribution of the fact sheet inserted into the lslander lVen¿s. Neighborhood by neighborhood updates as the project progresses, including progress reports, alerts, and completion of milestones and goals, The implementation of live Tele-Town Hall meetings that allows the residents to call in to listen to the meetings and ask questions during the Q&A portion. Media Relations The media can provide opportunities to get information out and share details. The outreach plan can include story opportunities and interviews with stakeholders, surrogates and third-par1y groups. These opportunities may ínclude the following: Provide the /s/ander lVeuzs regular press releases on new information, as well as present opportunities for stories or interviews. Guest editorials into the lslander lVews from the Village Manager, Public Safety officials, and experts, Keep an open dialogue with hhe lslander /Venzs to ensure factual information is presented. "Letter to the Editor" program that focuses on our messages and facts about undergrounding, by helping residents who want to share their experiences. Guest appearances on radio shows/podcasts including Rat Radio. Work with other news outlets with reach into the Village or national or regional magazines and periodicals that have an interest in undergrounding. 1/"* tlqo ?uM,,, Phãse r North Undergroundfng Protect [oin tùe undergroundtug proiect consh¡cdonteam for co6ec, donug aud cþnnersat¡on Àsù< questions and stay informed as thc proJect orwe¡ fonra¡ù lnformation brochure for community meeting with construction team in Palm Beach È I &1' lil¡i.lv. i'i, 'r.¡,'¡¡ir',1 '. 'r', ìlY .'. i. ìr1, I ¡¡;l r' ;.,t!, ,r{,r! I ,'.- WHEN:WHERE: r{il 106 I -l '') .l 'l I ') .ì .) I,) .l 'l I') 'l ) ) ) ) ) ) ) ) -)J J J J J J J J J J J J J J J J J #e ABÕU1 'HÊpÞoJ Ect "Éfiñ" FU NDI NG FAqs cÓl.rAcrUNDERCNOUilD? 3¡ @ See What WeVe Been Up To! Meeting Agendas & Recordings mtur¿l feåtur6. Reliability Resilient, Reliabte, and Protected Utilities Protected util¡tì6 er€ v¡tel to ênsr¡ng the teÉ¡l¡enq/ of a communivs most ¡mpo¡tånt resourc6 ¿nd connections protect¡ng thè V¡llage of Key BiscåyrElutilitis by burying them undsrground rÏìèansa safer, moÍe teli¿blq mre ræilient ånd mre beåutifulV¡llðge for residents end v¡sitds- lfl,ou usê ðnd enjoy the mturðl features ðnd public lends å¡ound th€ V¡llâge lhèn most l¡kelyyou åre affected by the visual ¡mpact ttp* ex¡sting overhead lines haw. Underground the ut¡lit¡es and en¡)y be¿utifulvieu/s ånd Prolæted conffitima Resilienry Undsgrdnd sjEtems ðre geffielly mre r6istðnt to dåmãge and âre rèstored to eryice mse quicklythan ærhe¿d syslåmr Underground Ð6tems ¿re les6 sus€eptible to dðmage from reaths evènts ðnd contæt wìth wg€tåt¡on ând wildlife. Safety Undtrgr@nd s)6tems ãre gensälly ãfer thån q/erhead Ð6têms bêcausê the equipment and cðbles arê 16 access¡ble to the public Aesthetics Elim¡nating overheðd ut¡lity lins¡nwillremæ obs¡ructiorìs stend¡rìg betwe€n those who l¡æ end play in thovillegeend the its Screenshot example of Village of Key Biscayne Utilities Underground website 1O.O PUBLIC OUTREACH PROGRAM KimleyDHorn 107 n- r11 OVERALL PROGRAIVI CPINION OF SCHEDULE Based on the Phasing and Sequencing Plan described in Section 6 of this master plan, a more detailed opinion of schedule was developed to better understand how each individual phase would interact with each other during the implementation process. To develop an opinion of schedule to this level of detail at this stage of the planning process, we primarily used our current relevant experience and lessons learned with this type of construction activity. ln addition, schedule considerations were developed through discussions with the Village, area contractors with expedise in undergrounding, and the utility owners. These schedule considerations can be categorized into Design Phase Schedule Considerations and Construction Phase Schedule Considerations. t l ) ) ) ) ) ) ) ) ) ) ) l l ) ) ) ') ) ) ) .) J Design Phase Schedule Considerations . Survey and utility base mapping must occur prior to the utility owners beginning their design efforts . AT&T and Comcast require the FPL design to be complete prior to beginning their design efforts . FPL Binding Cost Estimates and Utility Agreements are generally produced within three to four months after Village acceptance of the conceptual FPL design and sufficient progress on the easement acquisition process recognizing the various modifications to the design that are made during this process . CMAR procurement should occur after the completion of the FPL concept design but before completion of the final bid documents to take advantage of constructability review comments and value engineering suggestions Easement acquisition is desired to begin as early as possible and be completed prior to the siad of construction. Eminent domain processes are not considered in this schedule, All easements are assumed to be granted to the Village without compensation. Any required permits are desired to be secured prior to the starl of construction Any Village infrastructure work that is to be designed and constructed within an undergrounding phase area is to be included in the bid package for that undergrounding phase area KimleyDHorn 109 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN Because of the requirement for FPL to harden their infrastructure, design and construction of this undergrounding program should begin as soon as practical Pre-Construction Services/Bidding/Award of Phase 1 is to begin in the first quarler of the year to allow adequate time for pre-construction activities and GMP development needed to prepare for an early June construction start. This allows "heavy" construction activities to happen around the school during the summer months. Community outreach is a continuous process that spans across design and construction Construct¡on Phase Schedule Considerat¡ons ln general, construction activities around the K-B schoolshould be coordinated to occur during the summer in any one phase "Heavy" construction activities, such as underground infrastructure work and conduit installation, are desired to be constructed in the summer months when traffic volumes are lowest Year-round construction activities are considered for tlre undergrounding program Water main, stormwater, and conduit installation activities may occur simultaneously in any phase area. To m i n i m ize com m u n ity/traffic i mpacts, " heavy" construction impacts will not be allowed to occur in adjacent phases at the same time Cable and equipment installation activities may overlap the duration of backbone conduit installation within a phase To achieve schedule compression, portions of phases that can be overlapped should be to the greatest extent practical while minimizing traffic and resident impacts Feeder switch over to the underground system should be coordinated to occur in the cooler months when electrical demand is low, which reduces the complexity of the process and associated costs Conversion of individual electric and communications services will follow the energization of the new underground system Overhead wire and pole removal cannot begin until allservices are converted to the new underground system Roadway, sidewalk, and landscape improvements may occur during the final restoration stage of each phase Schedule Durat¡ons The durations of significant activities that occur within each project phase were developed based on information gathered from a variety of sources. Design durations are largely based on Kimley-Horn's experience with similar projects and through schedule discussions with FPL, AT&T, and Comcast. Construction activity durations were based on relevant projects currently underway or already completed. These were compared to the activities proposed in this master plan as part of the opinion of cost development, which yielded significant activity durations and were then incorporated into the overall schedule. Appropriate schedule contingencies were also applied to account for normal weather impacts, potential geological challenges, and unforeseen conditions. I 110 1 1 .) .l .l ").l ,l .) ).) .) I I I ) '),f ,) ) ) ) ) ) ) .) J J J J J ,J J J J J J J J / lne program schedule began in March 2018 with the development of this master plan. / Oeta¡led design will need to start as soon as practicalto minimize the duration and completion date of the program. / Design begins earlier for subsequent phases before prior phase completion to allow more time for the easement acquisition process. / Construction Manager selection occurs prior to final design completion to allow them the opportunity to provide constructability reviews and make value engineering suggestions. / fne design of the communications networks fotlows the design of the electrical network to allow cootdination of the designs that promotes the collocation of electrical and communications equipment in common easements. This reduces the overall number of easements required for the program. / Construction activities for the program are expected to kick off in the summer o12020 with Phase 1. / Construction durations for each phase range from 1ïto 24 months depending on the quantity of work to be performed and complexity of each phase. { ln order to accelerate the schedule, the construction phase for Phases 2,3n and 4 of the program overlaps the previous adjacent phase construction schedule by a minimum of 6 months with potentialto overlap 12 months or more. 11.0 OVERALL PROGRAM OPINION OF SCHEDULE / fne overlap of the construction activities in each phase is subject to "heavy" construction being complete in the previous phase prior to allowing "heavy" construction activities to begin in the subsequent phase. This is done primarily to mitigate community and traffic impacts. / tne final six months of the construction activity schedule for each phase is reserved for switch ove6 pole removal, and final restoration. lt is not expected that this will be a continuous construction activity. Experience with similar projects has shown that the coordination required with FPL, Af&I and Comcast can be time consuming and therefore requires a duration of time for the switch over and pole removal to be accomplished. { An aneas of the Village are scheduled to be converted to an underground system by the middle of 2025. Final pole removal is scheduled to be completed by the end of the second quarter in2026. { me schedute does contain time contingencies for normal weather impacts, soilconditions, and typical unforeseen conditions. lt does not account for significant schedule impacts related to significant weather events that cause the utility owners to focus efforts on storm recovery rather than undergrounding. lt also does not consider significant contractor issues related to litigation, bankruptcy, non- performance, and the like because these types of issues are impossible to predict. OVERALL SCHEDULE HIGHLIGHTS Kimley>)Horn 111 t/I ù I ,--aw ),¿iii,.l' oo o o a o2018 201 g | 1st 0uarter .2nd Ouarler: 3rd Quarler 4th 0uaderl 1st 0uarler 2nd 0uarler 3rd 0uarter ,4th 0uaderl 1st 0uarter llar Feu lilarcnl A0' rilav Ju¡ Ju,y Ailg Scpl ocl Nov occ l.ran rel lilarci Ä0 i¡dt Ju. Jury Âu0 Sept oct Nov Oe: llan fe! ¡rl¡rch 2021 2nd 0uader 3rd Oua¡1er 4th Ouafer Julv Âuq SeDl I ocl No! Dec 1st Ouarler lzno 0uanerl 3rd 0uarter: 4lh 0uarrerl 1st I lp trtay ,tun I lu,, o"q soÞt oct tlnv Dec I LanApr l,lay Ju¡Jafl Feb M¡rc¡ iil:r,nl:l$1.4 o o o ao Ðevelopment PHASE ûr o o o PHASE t2 a PHASE ü3 o o o o o PHASE ü4 o o o o o o oo O o112 The bind¡ng cost estinate and ut¡l¡U agreement development pr\cess will occur concurrentty w¡th the final 3-4 months oÍ the design/b¡d phases. Adve¡lisement for CMAB's should occur 5-months pr¡0r to des¡red pre-conslruct¡ln serv¡ces start. E MasterPlanning EË pre-Conskucti0nserv¡ces/B¡dding/Award E Survey == Conslruclion I Design Phase - Swilchover/Pole Removal/Final Resloralion = EasementAquis¡l¡on ù I ,n I ,/t/I ,|¡ llrII \ -. -.ðt J- I a.at,.',\'l'l'i apter 12 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) I 12J Approach The following elements were considered when developing this Opinion of Probable Cost (OPC)for each phase of the project. Use of recent cost information from similar projects: Recent bid prices lor overhead utility underground conversion projects currently underu,ray or already completed in similaç local coastal communities were used for the development of unit prices for this planning-level OPC. Use of comprehensive construction costs: Final bid prices for similar projects in the Miami-Dade area were used to develop unit costs that were applied to the overall program. This allows for inclusion of many smaller scale costs that may othenvise be overlooked during the master planning process. Use of a consistent unit cost application methodology: Since it is not feasible to perform detailed design for the entire program at this time, bid prices from similar projects were used to create sample model pro¡ect areas for five separate area types. These sample areas were then scaled up based on the linear footage of overhead to underground conversion required in any given phase. overhead utilities to an underground location within an assumed area. Kimley-Horn then prepared quantity estimates for the sample project area. Construction work elements estimated for the sample projects included the following: . Construction general conditions (mobilization, maintenance of traffic, bonds, survey, etc.) . FPL, AT&I and Comcast main conduit installation . Cable and equipment installation . Service conduit installation . Direct costs from FPL, AT&T, and Comcast for their labor, equipment, and materials related to both installation and demolition activities . Pavement restoration ' Site restoration . Landscaping for equipment screening Based on the lypes of areas that exist within the Village, five sample prolect areas were developed to project costs across the Village-wide pro¡ect. A summary of these five sample projects are described below:: 1. Typical Residential Area/Roadway lnstallation (i.e. Phases 1 , 2, and 3) - Units costs were developed for this sample project area that considered installation of underground utílity infrastructure within road right-of-way in a single family residential area where service lines would be converted from the rear to the front streel. I 12.2 Sample Project Area Development To develop unit costs that could be applied to quantities for a large- scale program area, unit costs associated with various "sample projects" representative of larger areas within the Village were developed. Kimley-Horn first used the sample projects to model the conversion of KimleyDHorn 115 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN 2. Residential Connectors/Roadway lnstallation (i.e., Phases 1, 2, and 3) - Unit costs for this sample project area were similar to the sample pro¡ect above, with the exception that costs associated with FPL feeder and Comcast fiber to the node conduit were included. The density of these east-west connectors is also significantly less than the residential described in sample prolect 1. 3. Residential on the Water/Non-Roadway lnstallation {i.e. Harbor Drive and Mashta lsland) - Unit costs for this sample project area were similar to the sample project above, with the exception that costs associated with asphalt trench repair for installation of underground infrastructure within the roadway were removed. Costs were added to consider additional sodding requirements and potential driveway restoration associated with a conduit installation off the roadway. Additionally, the electrical load in this sample project is higher due to the larger homes and waterfront amenities including potential boat dockage, This increases the electrical density, quantities of electrical backbone, and equipment. 4. Multi-Family Area Roadway lnstallation (i.e. Phases 2 and 3) - Unit costs for this sample project were developed considering overhead utility undergrounding in a dense multi- family area. This sample project includes higher costs related to general condiiions and maintenance of traffic, higher quantities of elecirical and communication backbone, increased electrical and comm un icati ons eq ui pment density, and increased restoration costs. 5. Fernwood Mixed'Use/Roadway Installation (i.e., Fernwood Road - Phases 1,2, and 3) - Unit costs for this sample project were developed for a representative section of a por-tion of the Village served by the Fernwood Road corridor. This corridor is the route for main electrical and communications conduit. lt also serves a mix of commercial and public buildings, as well as residential. Equipment, feeder, and communication backbone will be denser than typical residential sample projects due to the addition of commercial parcels. 12.3 Project Area Line ltem Unit Costs Based on the unit prices and quantities developed for each sample project area, total costs for each sample project area could be developed. The total costs for each sample propct area were then divided by the length of undergrounding within the sample prolect area to develop a representative unit cost per linear foot conversion that could be applied on a Village-wide basis to each of the program's phase areas. The unil prices per foot of conversion were categorized into the appropriate line item category for use in the overall OPC. A summary of each line item category outlined in the opinion of probable cosf rs in the table to the right. 12.4 Quantity Estimation GIS shape files were developed during this Master PIan for roadways, parcels, existing overhead utility localions, and outside infrastructure project information (water main, CIP projects, etc.) and were used to evaluate the quantities of program elements, including the length of overhead to underground conversion. Based on this GIS data, lhe following quantities were developed for each phase: ' Lenglh of existing overhead utilities to be converted underground ' Length of roadway anticipated to be impacted by conduit installation ' Estimated conduit joint trench length . Number of parcels per phase 12.5 Credits The following credits have been considered in the OPC. Other potential cost savings opportunities are discussed in the latter pafi of this chapter Florida Power and Light Government Adjustment Factor (GAF) Waiver Credit: lt is expected the Village will enter an Underground Facilities Conversion Agreement with FPL for the conversion of Village-wide overhead facilities. ln accordance with the FPL Tariff, this program qualifies for a GAF waiver of 25o/o. The GAF waiver credit amount has been estimated aI25% of the total estimated FPL contribution-in-aid-of-construction (CIAC) cost to install 116 1 Village of Key Biscayne Overall Program Opinion of Probable Cost - August 2018 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST the underground system, in accordance with budget cost estimates provided by FPL and the FPL Tariff, ln the latest tariff revision, effective February 22,2018, cedain elements of the CIAC calculation can be excluded if the applicant intends to conved existing non-hardened feeder facilities to underground feeder facilities. The calculation would exclude the cost to remove the existing overhead feeder facilities and the net book value of those feeder facilities. ln turn, however, the applicant does not get credit for the estimated salvage value of the existing overhead facilities to be removed. Despite that, the revision typically results in a lower CIAC to be paid by the applicant. It is our understanding that there are two proposed bills making their way through the legislature that may provide some additional incentive for FPL customers to underground their utilities, potentially allowing FPL to tap into a pool of money they ordinarily would only be able to access for storm recovery efforts. There are limitations on how much of this may be accessed to maintain reasonable electric rates. Assuming these bills get approved by the state, it would be up to the PSC to adopt rules to implement and administer the law. Because those details are unclear at this point and the bills have not yet passed, the topic will need to be discussed during negotiations with FPL ahead of the design phase of this project. 12.6 lnflation The Construction Cost Index (CCl) as calculated by Engineering A/ews-Record was used to estimate an average inflation rate to be applied to this program. The CCltracks the change in price FPL Overhead to Underground Conversion $10,200,000 2 CATV Overhead to Underground Conversion $1,300,000 3 Telephone Overhead to Underground Conversion $2,8oo,ooo 4 FPL Direct Costs $6,2oo,ooo 5 CATV Direct Costs $800,000 6 Telephone Direct Costs $1,goo,ooo 7 lnstall FPL Services $1,500,000 I lnstallTelephone and CATV Service Conduit $2,400,000 I lmpacted Street Líght Replacement (Village Custom)$1,100,000 10 Restoration $6,000,000 11 Construction Management $3,800,000 12 Eng i neeri n g/Perm itti ng/Surveying $2,000,000 13 Construction Adm inistration $1,800,000 14 Legal Fees/Easement Acquisition $500,000 15 Public Outreach $300,000 16 Gredits 17 FPL Credit - 25% GAF Waiver $(4,400,000) 18 Subtotal Undergrounding Project Costs $38,200,000 19 10% Contingency $3,800,000 20 lnflation $4,800,000 21 Total Undergrounding Project Costs $46,800,000 Optional ltems to Consider "Vista" Style Switch Cabinets (estimated at 40 total)$2,400,000 Additional Street Lights (Village Custom)$4oo,ooo Extra Conduit for Future Utility Lines (lncluding FTTP)$5,300,000 Roadway lmprovements - Milland Overlay lmpacted Roads $3,600,000 Roadway lmprovements - Raising Roads lmpacted by Storm lmprovements $9,8oo,ooo Roadway lmprovements - Traffic Calming $1,000,000 Water Main Replacement (AC and Unkown)$3,800,000 Sidewalks (Safe Routes to Schools Program, Budget est. by Village)$1,000,000 Stormwater lmprovements (From Stormwater Master Plan)$23,470,000 Equipment Screening (lncluded in conversion costs)$ Beautification (Cost varies depending on level of improvements)$ Description Opinion of Probable CostItem No ) ) ) ) ) ) ) ) ) -) KimleyDHorn 117 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN for a specific combination of construction labor, steel, concrete, cement, and lumber using data from 20 cities in the United States, The CCI is similar in concept to the well-known CPI (Consumer Price lndex), which tracks the consumer prices for a representative base of goods and services for urban consumers, but is considered more reflective of the construction industry and construction labor rates. The average yearly historical CCI's between January 1990-August 2016 were reviewed. The average percentage increase of construction costs during this time (January 1990 and August 2016), as well as the time between the years 2006 and 20'16, was 3,0% per annum. The average annual percentage increase in average construclion costs for any given year since 1990 ranged between 2.5o/o and 3.9o/o. Based on this information, an annual inflation factor of 3o/o was used for estimating inflation cosi impacts in this OPC. lt should be noted that inflation is difficult to accurately pro¡ect into the future and historical trends are not necessarily indicative of future inflation rates. Month-to-month or year-to-year changes in inflation rates could be significantly more or less than the percentages assumed for this OPC, 12.7 Assumptions and Limitations Assumptions made in the preparation of this OPC include the following 12.7.1 General Assumptions and Limitations This OPC considers the undergrounding of electrical, cable, and telephone facilities only, Cellular facilities, broadband infrastructure improvements or new broadband network installations, planned infrastructure improvements, and/or other facilities are not considered in this OPC. The unit costs provided assume all cable, electrical, and telephone conduit will be installed in a joint trench (with required separalion) by the same contractor who is directly contracted by the Village. This OPC assumes the Village will engage a contractor to install all equipment and materials except those items and operations required to be performed by the utility owner. We recommend the Village perform as much of the construction as possible. This provides the Village with more control over project costs and schedule. lt has been our experience that costs are lower, the schedule is minimized, and the work is generally more efficiently coordinated when the municipality performs the work versus when work is per-formed independently by the various utility owners. Even in the case where the utility owners perform the work, there are still items needing to be performed by the municipaliiy, such as easement acquisition, restoration, and rearrangement of customer service entrances from overhead to underground. Items and operations required to be per-formed by the utility owner include, but are not limited to, underground system make-ready and energization, telephone cable and equipment installation, cable television cable and equipment installation, and overhead infrastructure removal. Costs related to these utility owner activities have been included in this OPC. The OPC developed for this master plan is based on a high-level cost analysis for large-scale planning and budgetary purposes based only on the information available at the time this master plan was developed. The OPC contained in this master plan should not be considered applicable to a single block or other specific smaller scale areas since variations may exist on a smaller scale. Roadways disturbed by the undergrounding will require trench repair. Milling and resurfacing of the disturbed pavement has been included as a separate line item in the OPC. Roadway repairs are anticipated to be milled and resurfaced for one lane width and a minimum of 100 feet in either direction in accordance with County standards. Crandon Boulevard is a County-maintained road and therefore milling and resurfacing would be required along this corridor. Detailed network designs for proposed electrical, cable, or telephone infrastructure have not been performed and therefore were not available at the time of this master plan. This OPC is based on assumptions and generalizations regarding elements that a typical underground utility conversion project within the Village of Key Biscayne is likely to include. This OPC assumes a phased construction approach as outlined in this Master Plan. Each phase of construction is expected to have approximately a 18 to 24-month construction duration. 118 ) ) ) ) ) Construction will occur continuously throughout the phase assuming year-round construction for the undergrounding program as the Village does not have seasonal construction restrictions. It is assumed the Village will acquire private easements to lmplement the program when sufficient right-of-way is not available to contain the new underground equipment. lt is assumed easements will be donated by propeñy owners when required, as has been the case on other undergrounding projects. Costs related to any eminent domain processes, or compensation for easement space, are not considered in this master plan. Legal costs are estimated at 2.5o/o of the total base construction cost, Cost related to obtaining financing for the program are not included in this OPC. We recommend the Village establish a budget for financial consultants, closing costs, and other related costs of obtaining project funding. It ls assumed the Village will enter into a right-of-way agreement with applicable utility owners for the installation of new underground cabling and equipment within the Village and/or State road right-of-way 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST Over the life of the project, considerable effort is expected to be required from Village staff, including the Village Manager's office and the Depaftment of Public Works. lt is recommended the Village hire a project coordinator to assist the Village with the management and coordination of the project plus act as a resident liaison. Costs associated with the pro1ect coordinator, Village staff time, and use of Village facilities and resources have not been included in this OPC. Revenue generated or costs related to potential Village-owned broadband infrastructure improvements are not considered in this OPC. While these improvements may be constructed concurrently with the undergrounding program, any costs related to this effort are not included in the undergrounding program. Provisions for additional street lighting have been included in this OPC. lt is assumed that existing street lights mounted to FPL or AT&T owned poles on arterial roadways will be replaced in approximately the same location with new FPL standard street lighting. Additionally, proposed street lights for areas that do not currently have lights have been placed at roughly the same intervals as existing lights elsewhere in the residential neighborhood. Costs for custom poles have been prepared based on the recent T I Looking south onto Mashta lsland along West Mashta Drive from Harbor Drive ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ,-) J Kimley>)Horn 119 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN T Fernwood lighting RFP, At the same time, the Village should consider entering into an agreement with FPL lo provide lighting throughout the Village. FPL does not assess capital costs for the standard lighting installation but does charge a CIAC for the associated conduit installation. The operating costs will be paid for under the existing separate Village operating budget for street lighting. Existing decorative street lighting that is already served with underground infraslructure is assumed to remain in service. Construction cost contingency has been estimated at a rate of 1Oo/o. An allowance for restoration of private propefty after service installation and utility demolition is included. Our OPC also includes an allowance for equipment screening. All construction projects carry inherent risk for construction claims, litigation, or other such legal action against the Village for personal or property damages, This OPC does not include costs associated with contractor termination, re-mobilization, construction claims, litigation, or other such legal action. It can be expected that cost variations may occur throughout the life of the program based on market conditions, labor and material price fluctuations, and other factors. Kimley-Horn has no control over the cost of labor, materials, equipment, or over the contractor's methods of determining prices or over competitive bidding or market conditions. The OPC provided herein is based on the information known to Kimley-Horn at this time and represent only Kimley-Horn's Judgment as a design professional familiar with the construction industry. Kimley-Horn cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from its OPC. Costs related to the abandoning of rear yard easements has not been considered or included in the OPC at this time. reimbursed to the program by the private propedy owner and therefore have not been included in this OPC. ln many locations throughout the Village, electric and communications services originate from a rear property easement, To be compliant with current utility company standards, these services will be converted to a front street location under this program. I 12.7.2 Existing Conditions . Allowances for repair/replacement of service entrances on private property not meeting existing building codes should be included in the project to maintain the project schedule. These types of costs, while expected to be a rare occurrence, are expected to be 120 Directional boring machine in Palm Beach 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST ) ) ) ) ) ) ) ) It is assumed that new utility infrastructure related to the conversion process will be installed in public right-of-ways and easements. lt is fudher assumed this infrastructure will be installed in a manner that minimizes relocation of existing utilities in these same locations. These potential impacts cannot be accurately quantified at this time and are therefore not included in this OPC. 12.7.3 Construction Methods: Directional Bore vs. Open Trenching Conduit for electrical and cable/telephone infrastructure are typically installed using open-cut trenching or directional boring. Costs for these methods for installation within a typical residential area within the Village were analyzed to determine the most cost-effective installation method, Directional Boring . Due to the conduit separation requirements for AT&I FPL, and Comcast inTrastructure, a typical installation within the roadway by directional bore would require a minimum of three separate bores, each containing multiple conduits-FPL primary/service conduit, AT&T mainline/service conduit, and Comcast mainlinel service conduits. FPL feeder conduit may or may not be bored separately from the other FPL primary/service conduits depending on the site-specific factors. . Restoration will be required at each "bore pit" and within areas of the roadway that need to be excavated to intercept primary conduits for transformers, feeder conduits for switches, and service conduits for each building. One restoration area per property was assumed in the analysis. Open Cut . This method assumes AT&T, FPL, and Comcast infrastructure will be installed in a joint trench with the required separation between each utility. Asphalt trench repair is assumed to be required for most joint trench installations as the opportunities for an off-roadway joint trench installation within the Village is limited due to right-of-way and property improvement restrictions, Based on these assumptions, costs for installing a typical conduit run by directional bore was estimated to carry an appreciably higher cost than installation of those same conduits within a joint trench (via the open- cut installation method), despite the lack of pavement repair required. Additionally, there are technical challenges with boring on many of ihe Village's roadways that can be overcome using the open cut method These challenges include: . Narrow right-of-ways with a high level of utility congestion . Significant number of electrical and communications conduits to occupy a corridor with very limited space . Spacing requirements between electrical and communications facilities requiring separate bores . Bore spacing required for constructability to prevent multiple bores from converging together as often happens in sandy conditions and tight spacing Based on the analysis above, it is assumed by this OPC that open-trench installation methods will be used for most of the joint trench conduit installation within Village right-of-way. lt is fufther assumed the FPL, AT&T, and Comcast service conduit installation on private property will be installed via directional bore, minimizing private property disturbances and related restoration costs for the many high-end finishes that exist on private property. FPL service conduit was assumed to be installed as a separate bore to maintain the required separation to avoid electromagnetic interference issues. An exception to this may be the multi-family condominiums on the east side in Phase 2 between Galen Drive and E. Enid Drive. This project area includes large properties with long distances between service points. These buildings are also fed from rear yard overhead poles in easements. Because most properties are large, multi{amily condominiums, there is relatively little service conduit to be installed. Many of the service drops are also already undergrounded, therefore it may be possible to intersect these lines and refeed through existing conduit. Most runs are anticipated to be either feeder or primary electric and/or communications backbone. This reduces the number of entry/exit pits required throughout the area, which in turn reduces the anticipated cost of bore machine setups related to J KimleyDHorn 121 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN directional boring. Combining this with the general desire to disturb as little landscaping and private parking lots as possible, could create a situation where direciional boring becomes more technically feasible and the related costs are less than or comparable to an open cut conduit installation. To allow the contractor the greatest freedom to achieve the lowest cost installation with the greatest schedule efficiency, the decision whether to bore or trench will be lett to the construction team. 12.7.4 Electrical and Communications Utility Systems . Underground electrical and communications facilities to be constructed under this program are anticipated to be significantly different from their overhead counterparts based on the nature of an underground system design and layout. However, costs related to "betterment" or system upgrades are assumed to be the responsibility of the ulility owner. For example, the existing feeder ties would be replaced underground in-kind at a cost to the Village. New feeder ties not currently in existence (that are intended to enhance system reliability) could be installed at a cost to the utllity owner. . Electrical system costs may ultimately inclurde a mix of "Vista" and FPL standard switch gear should the Village desire to incorporate "Vista" equipment in the system. This would provide improved resiliency and storm surge protection since the Vista cabinet is waterproof. This OPC considers that all ihe switchgear will be standard style, wilh the option to upgracle to the Vista style cabinet . "Like-for-Like" copper systems were considered in lhis OPC for the undergrounding of telephone facilities. lt is furlher understood that AT&T may wish to upgrade to a fiber system after the initial overhead to underground conversion is complete or in conjunction with the program. AT&T stated they will install an upgraded fiber optic network concurrently with the Village's undergrounding program only if the Village funds those upgrade costs. Therefore, the upgrade has not been considered in the base OPC, " Like-for- Li ke" fi ber/coaxial systems (FTTN) were considered i n th is estimate for the undergrounding of cable television facilities. This OPC only considers the minimum number and size of conduits required to implement the overhead to underground utility conversion. Spare conduits have not been included in this OPC. 12.8 Opinion of Probable Cost Summary A summary of total pro¡ect costs, including contingency and inflalion, is provided below Village of Key Biscayne Overall Program Opinion of Probable Cost Summary - August 2018 Overhead to Underground Conversion - FPL $17,900,000 Opinions of Probable Construction Cosf by project phase are provided beginning on page 122. 1 2 Utility Conversion Costs - ATT & Comcast $9,200,000 3 lmpacted Street Light Replacement (Village Custom)$'1,100,000 4 Restoration $6,000,000 à Construction Management $3,8oo,ooo 6 En g i neeri ng/Perm itting/Surveying $2,000,000 7 Construction Administration $1,800,000 I Legal Fees/Easement Acquisition $500,000 I Public Outreach $3oo,ooo 10 FPL Credit - 25% GAF Waiver $(4,400,000) 11 Subtotal Undergrounding Project Costs $38,200,000 12 10% Contingency $3,800,000 13 lnflation $4,900,000 14 Total Undergrounding Project Gosts $46,800,000 Item No. Opinion of Probable Cost Description 122 ) ) ) ) ) ) ,) ) ) ) ) ) ) ) ) -) 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST KimleyDHorn 123 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN PHASE 1 - Village of Key Biscayne Overall Program Opinion of Probable Cost - August 2018 $2,7oo,ooo 2 1__ L) 4 5 6 7 I I 10 11 12 13 14 15 16 17 18 19 20 21 FPL Overhead to Underground Conversion CATV Overhead to Underground Conversion $300,000 Telephone Overhead to Underground Conversion CATV Direct Costs FPL Direct Costs $700,000 $200,000 $1,300,000 Construction Management lmpacted Street Light Replacement (Village Custom) $500,000 $1,000,000 $400,000 $1,600,000 $600,000 $400,000 lnstallTelephone and CATV Service Conduit Restoration Telephone Direct Costs lnstall FPL Services Eng i neering/Permitting/Surveying $soo,ooo $500,000 $100,000 Gonstruction Admi nistration $100,000Legal Fees/Easement Acquisition FPL Credit - 25% GAF Waiver Public Outreach Credits $(1 ,'100,000) Subtotal Undergrounding Project Costs $9,400,000 $1,000,000 $1,200,000lnflation 10% Contingency PHASE 1 Total Undergrounding Project Costs $'12,000,000 Description Opinion of Probable CostItem No. i I I I 124 ffi 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN ô otr -r] 1C : offi& É-nlJcf N V/E+ S 0 333.3 C lmpacted Street Lesend - - , Overhead Utilities r' lmPacted Roads r ,Potential lmpacted Phase-l I Parcels OPINION OF PROBABLE COST PHASE I MAP Kimley>)Horn 125 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN PHASE 2 - Village of Key Biscayne Overall Program Opinion of Probable Cost - August 2018 IJ Ê-'.:,1 b 1 FPL Overhead to Underground Gonversion $3,3oo,ooo 2 CAW Overhead to Underground Conversion $500,000 3 Telephone Overhead to Underground Conversion $1,ooo,ooo 4 FPL Direct Costs $2,3oo,ooo 5 CATV Direct Costs $200,000 6 Telephone Direct Costs $600,000 7 lnstall FPL Services $500,000 I lnstallTelephone and CATV Service Conduit $700,000 9 lmpacted Street Light Replacement (Village Custom)$300,000 10 Restoration $1,800,000 11 Construction Management $1,20o,ooo 12 Eng i neerin g/Perm itti n g/Surveyin g $600,000 13 Construction Administration $600,000 14 i Legal Fees/Easement Acquisition $200,000 15 Public Outreach $100,000 16 Gredits 17 FPL Credit - 25% GAF Waiver $(1,400,000) 1B Subtotal Undergrounding Project Costs $12,500,000 19 10% Contingency $1,300,000 20 lnflation $1,600,000 21 PHASE 2 Total Undergrounding Project Costs $15,4oo,ooo Description Opinion of Probable CostItem No { 126 {o -o rÛ P lz Legend -. Overhead Utilities ¡ lmpacted Roads - ,Potential lmpacted Roads C lmpacted Street Lights x Phase 2 Parcels I L Lou U(ü o) nfl É N w E 333.3 667 ß¡_tlUD 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN OPINION OF PROBABLE COST PHASE 2 MAP KimleyDHorn 127 1 FPL Overhead to Underground Conversion I $g,zoo,ooo 2 CAW Overhead to Underground Conversion $400,000 3 Telephone Overhead to Underground Conversion $900,000 4 FPL Direct Costs $1,900,000 5 CATV Direct Costs $200,000 $600,0006 7 Telephone Direct Costs lnstall FPL Services $400,000 I lnstallTelephone and CATV Service Conduit $700,000 9 lmpacted Street Light Replacement (Village Custom)$100,000 10 Restoration $1,900,000 11 Construction Management $1,1oo,ooo 12 Eng i neerin g/Perm itti ng/Su rveying $500,000 13 Construction Adm inistration $500,000 14 Legal Fees/Easement Acquisition $200,000 15 Public Outreach $100,000 16 Gredits 17 FPL Credit - 25% GAF Waiver $(1,400,000) 1B Subtotal Undergrounding Project Costs $11,300,000 19 10% Contingency $1 ,100,000 20 lnflation $1,400,000 21 PHASE 3 Total Undergrounding Project Gosts $13,900,000 Description Opinion of Probable Cost VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN PHASE 3 - Village of Key Biscayne Overall Program Opinion of Probable Cost - August 2018 ,*ìr af: -1:r'ì :, -: ! :+**g#s.Þ -q i "*r..lv '/ jL?, /, +-lE, {È;tÉl:.; i*'t\ .#:¡. .' F sqriz t.-r"d' I 128 pt 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN ,II N Â, l Sonesta r E Lesend - -. Overhead Utilities l lmPacted Roads '' ,Potential lmpacted Roads c lmpacted Street Lights Phase 3 Parcels o.l w E S DN L o filoIo OPINION OF PROBABLE COST PHASE 3 MAP Kimley)>Horn 129 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN PHASE 4 - Village of Key Biscayne Overall Program Opinion of Probable Cost - August 2018 i sl,l oo,ooo1 2 FPL Overhead to Underground Conversion CATV Overhead to Underground Conversion 10 11 12 $100,000 4 6 7 I I r 13 )14 16 17 18 20 21 .)$300,000 5 Telephone Overhead to Underground Conversion FPL Direct Costs Telephone Direct Costs CATV Direct Costs $600,000 $300,000 $l oo,ooo lnstallTelephone and CAW Service Conduit $300,000 lnstall FPL Services lmpacted Street Light Replacement (Village Custom) $100,000 $200,000 $4oo,ooo $800,000Restoration Construction Management Engineering/Permitting/Surveying $200,000 Construction Adm in istration $200,000 Legal Fees/Easement Acquisition $100,000 15 Public Outreach $ Creclits FPL Credit - 25% GAF Waiver Subtotal Undergrounding Project Costs $4,300,000 000) 19 10% Contingency $400,000 lnflation $500,000 PHASE 4 Total Undergrounding Project Gosts $5,2oo,ooo Description Opinion of Probable CostItem No Ì;,." "irr:r:: 130 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST VILLAGE OF KEY BISCAYNE UTILITIES UNDERGROUNDING MASTER PLAN o h0 GI Lesend - -. Overhead Utilities r lmpacted Roads ¡' --' n Potential'Impacted Roads o lmpacted Street Lights Phase 4 Parcels N w E 0 333.3 667 1,333 Feet S I Þ OPINION OF PROBABLE COST PHASE 4 MAP Kimley))Horn 131 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN 12.8.1 "Vista" Style Switch Cabinets As described in Chapter 5, two types of switch cabinets can be provided by FPL based on preference or circumstance: 1) the standard "PME' switch cabinet or 2)the "Vista" switch cabinet. The Vista cabinet has a slightly smaller footprint, is shorter, and only requires an eight-foot clearance on one side of the cabinet rather than all sides for the standard switch. The Vista cabinet is also hermetically sealed to prevent water intrusion. The Vista switch cabinet costs approximately $60,000 more than a standard switch cabinet. Forty-one aerial switches exist in the current overhead system. FPL has indicated the underground system would not need as many switches as the aerial system. Since we cannot confirm how many wlll be required, we assumed the underground system would need 40 switch cabinets, one less than what exists today. This line item also includes FPL's GAF Waiver discount of 25o/o. 12.8.2 Additional Street Lights As described in Chapter 5, it is estimated 1 18 street lights will be impacted by this program and will need to be replaced. Forty street lights are currently being installed by the Village as part of their separate lighting program. lt is also estimated a minimum of 41 street lights would be required in Village areas currently without lighting. Kimley-Horn has included in our OPC these additional street lights, assuming the Village elects to installthe minimum number identified. A photometric plan may be required and may increase that number significantly. '12.8.3 Extra Concluit for Future Utility This OPC includes costs associated with the installation of spare conduit infrastructure for a Fiber to the Premises (FTTP) Broadband Network that could be used by competitor communication providers interested in providing service to the community. As described in the separate Technical Memo dated June 20, 2018, this includes the installation of conduit to all parcels in the Village. Conduit lengths were estimated using the total length of public roadway for each phase of the undergrounding project. This OPC does not include fiber optic cable or equipment, nor does it include the drop conduit between the right-of-way and the service point of the building/facility to be served. Additionally, assumptions identified in the Technical Memo were maintained with exception of the contingency, which was removed, and general conditions, which were further refined to reflect real-world market conditions. 12.8.4 Roadway lmprovements The Village UUTF requested Kimley-Horn investigate the feasibility of raising public roadways to mitigate future effects of sea level rise. Although this master plan does not contemplate the effects of sea level rise nor sustainability, Kimley-Horn performed a brief analysis of the costs associated with such an endeavor. This analysis assumed roads would consistently be raised by six inches only in the areas where stormwater improvements are proposed in the Village's stormwater master plan. This Opinion also assumes by raising the roadways, additional concrete gutter, stormwater infrastructure, and design fees would be required. ln addition to raising the roads, traffic calming is an important part of the Village's 2008 master plan. li identified the need for traffic speed control on the roads within the Village. To address this issue the Village engaged a consultant to prepare a Traffic Calming Master Plan in 2012. This master plan identified nine roadways that warranted traffic calming measures, assigned an improvement cost to them, and included the cost in this OPC without consideration for inflation. 12.8.5 Water Main Replacement Provided with the GIS data from Miami-Dade County was information related to the material type of individual segments of the water main system. Kimley-Horn was able to isolate and identify the existing asbestos cement (AC) water main that exists as part of the County's overall system within the Village. The Village staff has expressed interest in replacing all existing AC water main pipe. This line item cost includes current real-world material and installation costs for 1 ,257 LF of 12" or greater AC water main, 5,755 LF of AC water main less than 12", and i 8,354 LF of listed "Unknown" water main less than 12" that will need to be identified before determining whether it would need to be replaced. Not all Unknown water mains may need to be replaced if they are determined to be made of an acceptable material. The County has indicated that they would be willing to include these upgrades in their budget estimates to reimburse the Village for the work. 132 12.0 OVERALL PROGRAM OPINION OF PROBABLË CONSTRUCTION COST UTILITY INTEGRATION LANDSCAPE STRATEGY - PROTOTYPE STUDY 4' Prototype Study #1 - Minimum Constraints t¡¡(,¿u¡u Prototype Study #2 - Moderate Constraints I I f I f I Í 4', o4 Prototype Study #3 - Maximum Constraints FPL UTlLITY BOX FPL UNL.]TY BOX FPL UNLITY BOX ) ) ) ) ) -) Kimley>)Horn 133 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN 12.8.6 Sidewalks (Safe Routes to Schools) The budget for this project has been previously established by Village Council with hopes that costs savings could be realized by incorporating this pro¡ect into the undergrounding of utilities project. Additionalsidewalk improvements throughout the Village have not been contemplated in this OPC. 12.8.7 Beautification Acknowledging the guidelines established by the Village of Key Biscayne Landscape Management Plan, anticipating the spatial constraints associated with varied adjacencies, and projecting budgetary mindfulness, the landscape strategy for integration of utility interventions (a.k.a., electrical and communications equipment), utilizes a series of principles rather than a prescriptive formula to guide placemaking efforts within the public realm. A process-oriented approach to implementation will be coupled with the guiding principles of Species Diversity, Site Specificity, Layering, and Blending in order to integrate these man-made interventions within a natural context. The costs associated with screening the utility interventions have been included in the overall underground conversion costs at $1,000 per property. This figure can be broken out and increased or decreased as required by the Village. 12.8.8 Stormwater lmprovements As described in Chapter 4, the Village hired a consultant to prepare a master plan for the implementation of the Village's drainage improvements, which includes upgrades to stormwater pump stations and gravity drainage wells. Because the improvements proposed by this drainage master plan are widespread, Kimley-Horn has been asked to incorporate these improvements into the undergrounding master plan to realize efficiencies in constructing them at the same time. The fier 2 improvements identified in the master plan are extensive. The cost for these improvements developed by this master plan are included in our OPC. Although the Village has setup a stormwater enterprise to pay for drainage improvements, the Village currently does not have lhe budget to incorporate all the improvements identified in this master plan. 12.9 Cost Reduction Opportunities This OPC was prepared based on the understood goals and objectives of the program, including conversion of all overhead utilities to an underground location within the Village municipal limits. As a benefit to the Village, this master planning effort explored several cost reduction opportunities that could be considered by the Village. However, these opportunities may require the goals and objectives of the program be altered, variances from the Village Code of Ordinance requirements be issued, or offsetting revenue and/or grant funding be applied to the program. A summary of such options is presented below: 12,9 ,1 Construction Methods The overall program cost for undergrounding the existing overhead utilities could be reduced if specific construction techniques and/or sequences are considered. This could be accomplished in severalways. Pavement Milling and Resuffacing Gost Sharing: As outlined in other sections of this Master Plan, additional infrastructure projects are proposed throughout the Village over the expected duration of the undergrounding program including drainage and water main projects. These infrastructure projects are anticipated to incorporate milling and resurfacing of their work area. For areas where these projects and the undergrounding conversion project will be in the same location, the cost of the required milling and resurfacing could be shared between the participating entities (i.e., Village, Miami-Dade Water and Sewer Depadment, etc.), Details regarding the assumptions that were made for each utility owner with significant infrastructure projects within the Village are noted below: > Stormwater Master Plan lmplementation: The Village recently completed the preparation of a stormwater master plan that proposes numerous infrastructure improvements to the Village's stormwater management systems within the Village. The proposed stormwater management system improvements could be implemented in conjunction with the undergrounding project, and where the two projects impact the sarle roadways, the cost o[ rnillirrg and resurfacirrg tlrose roads could be shared between the two programs. 134 ì ) ) ) ) lmprovements by the Miami-Dade Water and Sewer Department: The Miami-Dade Water and Sewer Department (MDWASD) owns and maintains the water and sewer distribution and collection infrastructure within the village limits. The Village completed a septic-to-sewer conversion program approximately 10 years ago where the customers within the Village still using septic tanks had sewer mains installed fronting their propefties to connect to the sanitary sewer system. As paft of this program, MDWASD also replaced any AC water distribution pipes within the septic- to-sewer pro¡ect area. However, there are still portions of the Village where AC pipe remains that were not on septic, and therefore, were not impacted by that project. Coordination with MDWASD to replace this remaining AC pipe is ongoing, and if the MDWASD were to coordinate its replacement with the Village's undergrounding program and where the two projects impact the same roadways, the cost of milling and resurfacing those roads could be shared between the two programs. Because MDWASD has not established any funding for this program at this time, we cannot quantify any estimated savings that could be realized. > Raising of Low-Lying Streets: Some of the costs related to milling and resurfacing, including the above referenced pavement cost sharing credits, could be funded by a program to raise low-lying roads within the Village. Currently several roads in the Village are low enough and experience minor flooding during king tide events, even when no rainfall has occurred. Raising these low-laying roads will reduce the frequency of tidal flooding and help the drainage system function during storm events by providing additional head on drainage wells discharging water. Village staff expressed interest in this program, but no funding for such a project has been established, therefore we have not quantified any estimated savings related to this program. Volume Pricing for Pavement Milling and Resurfacing: This program also offers the opportunity for the Village to take advantage of volume pricing related to the milling and resurfacing 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCTION COST costs associated with large-scale paving programs. Thus, the following could be considered: > Postponement of milling and resurfacing until multiple phases of undergrounding have been completed. After u nderg rou nd i n g and other p roposed i nfrastructure projects, identified above, in given phases are complete, the milling and resurfacing work can be subsequently bid and awarded by the Village (i.e. two or three phase areas per bidding cycle), Trenches and bore pits would be repaired to grade after conduit installation with final milling and resurfacing to occur later under a separate contract administered by the Village. > Milling and resurfacing work could occur at night to minimize traffic impacts to residents and increase paving efficiency. 12.9,4 Offsetting Revenues, Credits, and/or Grant Funding The Village may be able to offset some of the project construction cost through various revenues, credits, or grant funding opportunities. This would ultimately result in a lower net cost realized by the Village for the program. These opportunities include the following: . Sales Tax Savings: The direct purchase of communications conduit and other necessary materials for the duration of the program for which the Village will realize a sales tax savings. . Additional credits or financial contribution from the utility owners: There is a benefit each utility owner realizes in avoided storm recovery efforts after an underground conversion is complete. Currently, only FPL offers a credit (GAF Waiver)for this benefit. The Village should continue to explore ways the utility owners can participate in offsetting the cost of the program based on the benefits they will receive. This can take on the form of enhanced credits, no cost system betterments, etc. ln our experience this negotiation will delay lhe project, prevent conversion, and ultimately pole removal. . Broadband lnfrastructure Revenue. The Village could decide to use the program as an oppoftunity to assist in the installation of another communications service provider to provide property owners with another option for services beyond the legacy ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ,) ) ) .) J KimleyDHorn 135 VILLAGE OF KEY BISCAYNE UNDERGROUNDING OF UTILITIES - MASTER PLAN providers. Revenue or cost sharing agreements could be entered between the Village and interested providers. Hotwire communications has expressed an interest in a partnership with the Village to provide a fiber-to-the-home network but would require a volume customer agreement to do so. This option would result in all homes within the impacted area receiving FTIH services, but at a monthly cost to each owner. Grant Funding. Grant funding such as the FEMA Pre-Mitigation Grant program could be pursued to help offset program costs. Award amounts are typically small in comparison to the cost of an undergrounding program, Despite this limitation, the grant funds would offset the program costs. These grants can be applied for on a phase-by-phase basis to maximize the benefits, so long as the federal government still offers the funding program, lt should be noted that grant funds received from state or federal sources to offset the costs of an underground conversion program cannot exceed the amount of the CIAC prior to the GAF Waiver being applied in accordance with the FPL Tariff. 136 Fernwood Road looking north from W. Mclntyre Street 12.0 OVERALL PROGRAM OPINION OF PROBABLE CONSTRUCÏION COST KimleyDHorn 137 UTILITIES RESILIENT. RELIABLE. PROTECTED. www,kbu nderground,com KimleyDHorn Expect More. Experience Befter.