AN ORDINANCE OF THE CITY OF JEFFERSON, MISSOURI, AUTHORIZING THE
MAYOR AND CITY CLERK TO EXECUTE AN AGREEMENT WITH FERCON
CONSTRUCTION, IN THE AMOUNT OF $133,700.00 FOR THE ROLAND STREET
AND MARSHALL STREET (300 BLOCK) SIDEWALK AND STREET PANEL
REPLACEMENT PROJECT.
WHEREAS, Fercon Construction has become the apparent lowest and best bidder on
the Roland St. and Marshall St. (300 Block) Sidewalk and Street Panel
Replacement project.
NOW, THEREFORE, BE IT ENACTED BY THE COUNCIL OF THE CITY OF
JEFFERSON, MISSOURI, AS FOLLOWS:
Section 1. The bid of Fercon Construction is declared to be the lowest and best
bid and is hereby accepted.
Section 2. The Mayor and City Clerk are hereby authorized to execute an
agreement with Fercon Construction for the Roland St. and Marshall St. (300 Block)
Sidewalk and Street Panel Replacement project.
Section 3. The agreement shall be substantially the same in form and content as
that agreement attached hereto as Exhibit A.
Section 4. This Ordinance shall be in full force and effect from and after the date
of its passage and approval.
Passed:Lid— p Approved: 1/440t. i,X/.S
•
Call/kt‘
(4 ` 6(tvf-t e` Teir
Presiding Officer, Mayor Carrie Tergin
\..
ATTEST: t APPROVED AS TO FORM:
- •
. r •
jj 1`,,
i-1,661:11 , :/f4i*t(
ity C(IK~ / ity Counselor
FINANCE DEPARTMENT
PURCHASING DIVISION
SUBJECT: Bid 2820– Project 32139 Marshall Street (200-300 Blk) and Roland St. Sidewalks
Public Works, Engineering – Opened August 25, 2015
RECOMMENDATION:
Staff recommends award of the bid to the lowest and best bid meeting specifications as submitted
by Fercon Construction of Jefferson City, Missouri in the amount of $133,700.00.
BIDS RECEIVED:
Fercon Construction, Jefferson City, MO $133,700.00
Concrete Solutions, LLC, Linn, MO $164,586.55
B & P Patterson Concrete, Linn, MO $179,555.00
M & M Landscaping, Eugene, MO $255,504.00
The bid was advertised in News Tribune, posted on the city web site, sent to seven plan houses.
Four additional firms purchased plans but did not respond.
FISCAL NOTE:
44-990-577055 Sales Tax F Funds 10-149-577055 – Entitlement Grant Funds
Marshall and Roland Sidewalk Marshall and Roland Sidewalk
2014-15 Budget $43,700.00 2014-15 Budget $90,000.00
Bid 2820 $43,700.00 Bid 2820 $90,000.00
Balance $ -0- Balance $ -0-
PAST PERFORMANCE:
The City has awarded to this bidder in the past and staff believes the contractor will complete the
work as specified and bid.
ATTACHMENTS - SUPPORTING DOCUMENTATION
Signature il Ltg— '
fica------------._
Pur as
Agent Director of Public Works
r .
1 1
re` :f EtiWL .
ija
Department of Public Works Memorandum
320 E. McCarty Street •Jefferson City, Missouri 65101 • P 573-634-6410 • F 573-634-6562 • www.jeffcitvmo.orq
Date: August 28, 2015
To: Terry Stephenson, Purchasing Director, Finance
From: David Bange, City Engineer IJ
Subject: Project No. 32139; Marshall St. (200-300131k) and Roland St. Sidewalks
Bid No. 2820
Public Works has completed a review of the bids opened at 1:30 p.m. on August 25, 2015 for
the above noted project. As part of the review all the bids were tabulated to check for math
errors and to compare unit price quotes of the various contractors. Attached to this memo is the
tabulation of the four (4) bids received for the project, as well as a listing of the registered plan
holders.
Based on our review, we recommend acceptance of the bid from the low bidder Fercon
Construction, 2014 Clara Drive, Jefferson City, MO 65101. The total amount of the contract will
be one hundred thirty-three thousand, seven hundred ($133,700).
The project will be.expensed as follows:
Fercon Construction ($133,700.00):
Account Number: Amount Available: Required: Remaining:
44-990-577055 $43,700.00 $43,700.00 $0.00
10-149-577055 $90,000.00 $90,000.00 $0.00
If you need any other information please feel free to contact me at extension 6433.
Attachments: Bid Tabulation Sheet, Plan Holders List
cc: Project file
Writer's file
•
Page I CITY OF JEFFERSON
Date:25/08/2015 BID TABULATION
Bid No.2820 ROLAND ST.AND MARSHALL ST.(300BLK)SIDEWALK AND STREET PANEL REPLACEMENT
PROJECT NO.32139
ENGINEER'S ESTIMATE Fercon Construction Concrete Saluda LLC 88P Patterson Concrete M8M landscaping
ITEM APPROX.
NO. DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT .UNIT PRICE AMOUNT y)NIT PRICE AMOUNT
1 Mobilization LS 1 $3,000.00 $3,000.00 $0.00 $0.00 $19,000.00 $19,000.00 $5,500.00 $5,500.00 '$5,000.00 $5,000.00
2 Removals LS 1 $2,750.00 $2,750.00 $4,000.00 $4,000.00 $3,000.00 $3,000.00 53,500.00 $3,500.00 $10,000.00 $10,000.00
3 Earthwork LS 1 $4,000.00 $4,000.00 $4,000.00 $4,000.00 $4,000.00 $4,000.00 $4,000.00 $4,000.00 $10,000.00 $10,000.00
4 Final Site Restoration(Roland) LS 1 $2.500.00 $2,500.00 $1,500.00 $1,500.00 $1,000,00 $1,000.00 $2,000.00 $2,000.00 $8,000.00 $8,000.00
5 Final Site Restoration(Marshall) LS 1 $2,500.00 $2,500.00 $2,500.00 $2,500.00 $1,000.00 $1,000.00 $2,200.00 $2,200.00 $6,000.00 $6,000.00
6 Temporary Site Stabilization SY 750 $4.00 $3,000.00 $0.00 $0.00 $2.50 $1,875.00 $1.00 $750.00 $18.00 $13,500.00
7 Sediment Barrier LF 450 $4.50 $2,025.00 $0.00 $0.00 $4.50 $2,025.00 $4.40 $1,980.00 $6.00 $2,700.00
8 Inlet Protection EA 10 $200.00 $2,000.00 $0.00 $0.00 $100.00 $1,000.00 $150.00 $1,500.00 $400.00 $4,000.00
9 Construction Signage/Traffic Control EA 4 $1,500.00 $6,000.00 $300.00 $1,200.00 $1,200,00 $4,800.00 $500.00 $2,000.00 $2,000.00 $8,000.00
10 Curb end Gutter(Remove B Replace) LF 810 $37.50 $30,375.001 $25.00 $20,250.00 $20.00 $16,200.00 $35.00 $28,350.00 $70.00 $56,700.00
11 Detectable Warnings SF 90 $30.00 $2,700.00 $29.00 $2,610.00 $20.00 $1,800.00 .$19.00 $1,710.00 $54.00 $4,860.00
12 Sidewalk Ramp(Remove 8 Replace) SY 92 $70.00 $6,440.00 $90.00 $8,280.00 $107.15 $9,857.80 $65.00 $5,980.00 $162.00 $14,904.00
13 Sidewalk(Remove 8 Replace) SY 595 $50.00 $29,750.00 $45.00 $26,775.00 $55.00 $32,725.00 $60.00 $35,700.00 $68.00 $40,460.00
14 Concrete Driveway;6"thick(Remove 8 SY 345 $80.00 $27,600.0 $73.00 $25,185.00 $62.86 $21,686.70 $94.50 $32,602.50 $78.00 $26,910.00
15 Concrete Driveway Approach;8'thick SY 115 $80.00 $9,200.0 $81.00 $9,315.00 $98.33 $11,307.95 $120.00 $13,800.00 $112.00 $12,880,00
(Remove 8 Replace)
•
16 Concrete Street;6"thick(Remove 8 , SY 385 $75.00 $28,875.0 $71.00 $27,335.00 $78.66 $30,284.10 $94.50 $36,382.50 $79.00 $30,415.00
17 Subgrade Stabilization Ton 25 $50.00 $1,250.00 $30.00 $750.00 $85.00 $2,125.00 $30.00 $750.00 $15.00 $375.00
18 Rock Excavation CY 10 $150.00 $1,500.00 $0.00 $0.00 $90.00 $900.00 $85.00 $850.00 $80.00 $800.00
TOTAL BASE BID $166,465.00 $133,700.00 $164,586.65 $178,666.00 $255,604.00
%OVER/UNDER ENGINEER'S EST. -19.2% -0.5% 8.5% 64.4141
TOTAL CONTRACT WITH ACCEPTED ALTERNATES $166,465.00 $133,700.00 $164,586.66 $179,656.00 $255,504.00