HomeMy Public PortalAboutResolutions-2011 - 05RESOLUTION 2011 - 05
A RESOLUTION FOR APPROVAL OF SELLING OF REAL ESTATE LOTS OWNED BY THE CITY
OF TIFFIN IN TIMBER RIDGE VIEW PART TWO LOTS 31
WHEREAS, the City of Tiffin Iowa, An Iowa Municipality (The "City"), received, as part of the Settlement
Agreement with LDR IOWA CITY LLC, A Wisconsin Limited Liability Company (LDR) a real estates lot known as
Lot #31
WHEREAS, the lot have been declared clear of liens or encumbrances and transfer of property has been
properly recorded with the Johnson County, Iowa Recorder, as previously recorded in Book 51, Page 168,
WHEREAS, the City Council of the City, after holding a properly noticed public hearing on the issue; the City
Council may desire to make a decision to sell the properties as detailed below:
Lot #31, to sell to the public.
AND WHEREAS, Notification to the Public will be published and posted as required in accordance to Iowa
Code. (Mandated Procedures Attached.)
NOW THEREFORE, IT IS RESOLVED THAT:
1. A Notice of the date, time, and place of the hearing on this issue was properly published.
2. A Hearing was held on the issue.
3. That the properties described below are henceforth zoned:
Lot #31 R1 -C Residential
4. The City Attorney will examine and assist with all documents pursuant to the sale of real estate property
in accordance to the Iowa Code.
On the 91h day of February, 2011 at a regular City Council meeting of the City Council, Tiffin, Iowa, Council
person Chris Ball introduced Resolution 2011-05 A RESOLUTION FOR APPROVAL OF SELLING OF REAL
ESTATE LOTS OWNED BY THE CITY OF TIFFIN IN TIMBER RIDGE VIEW PART TWO LOT 31and
seconded by Council person Travis Weipert and made motion for approval.
a
Ayes: Chris Ball, Jim Bartels, Mark Petersen, Travis Weipert
Nay: None
Absent: Mike Gericke
With four votes for City Council approval, Mayor Phillips declared that the Resolution 2011-05 A RESOLUTION
FOR APPROVAL OF SELLING OF REAL ESTATE LOTS OWNED BY THE CITY OF TIFFIN IN TIMBER
RIDGE VIEW PART TWO LOTS 31 be adopted and signified his approval of the same by affixing his signature
thereto.
Passed and approved this 9th day of February 2011.
city !Affth
ILoo�� �I
- . -.
es .
Rut Demuth, City Clerk
a
{
t
Prepared by: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340
Return to: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340
RESOLUTION NO. 2011-04
RESOLUTION AUTHORIZING STAFF TO SUBMIT THE FOLLOWING
CAPITAL TRANSPORTATION PROJECTS AND COST ESTIMATES TO THE
JOHNSON COUNTY COUNCIL OF GOVERNMENTS FOR INCLUSION IN THE
REVISED LONG RANGE TRANSPORTATION PLAN TO BE ADOPTED MAY OF 2012
WHEREAS, our community/organization is a'member of the Johnson County Council of Governments; and
WHEREAS, the Federal Highway Administration now requires that the JCCOG Long Range Transportation
Plan include a fiscally constrained project list for the JCCOG urbanized area; and
WHEREAS, the Johnson County Council of Governments Urbanized Area Policy Board has directed JCCOG
staff to receive said capital transportation project lists by.resolution '
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF TIFFIN, IOWA, THAT:
1. The following list of anticipated federally funded projects be included in the revised version of the JCCOG
Long Range Transportation Plan to be adopted by May of 2012.
See Exhibit A
2. The following list of anticipated locally funded projects be included in the revised version of the. JCCOG
Long Range Transportation Plan to be adopted by May of 2012.
See Exhibit B
Passed and approved this 12th day of Janu 11.
W. Phi ps; ay
ATTESC�?�
Ruth emuth, City Clerk
It was moved by Council person Chris Ball and seconded by Council person Travis Weipert the Resolution be
adopted, and upon roll call there were:
AYES: NAYS: ABSENT:
X Chris Ball
X Jim Bartels
X Mike Gericke
} X Mark Petersen
X Travis Weipert
4
1
2012-2040 Long Range Plan - Federally Funded Transportation Infrastructure Projects
Fxhihit A
Project Title
Project Descriptions(include type of:project`locatign, length, etc) I
_
$ Cost Estimate Anticipated Year of
(Present,dollar) Construction (2012-2020_,
2021-2030, 2031-2040
Ireland Ave ( Railroad St to Hwy 6)
Grade& Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,800,000 2010-2015
Trail (Jasper Ave to 1-380)
Grade and Pave Trail
$238,000 2010-2015
Jasper Ave (Hwy 6 south to Clear Creek Bridge)
Phase One
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2010-2015
Ireland Ave (1-80 to Clear Creek)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,500,000 2015-2020
Trail head east of Jasper Ave
Grade and Pave Trailhead
$30,000 2015-2020
Trailhead at Ireland
Grade and Pave Trailhead
$30,000 2015-2020
Ireland Ave (Clear Creek Bridge to Railroad St.)
Replace Bridge and Grade and Pave
$1,500,000 2015-2020
Jasper Ave (Bridge to 1-80) Phase Two
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2015-2020
Jasper Ave (Hwy 6 north 2000 ft) Phase Three
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2015-2020
Trail south on Ireland to Villages Development
Grade and Pave Trail
$200,000 2015-2020
Jasper Ave (Completed portion north to
Forevergreen,Rd) Phase Four
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2020-2025
Hwy 6 (Ireland to Main St)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2020-2025
Hwy 6 (Ste hans St to Jasper Ave.)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$2,000,000 2020-2025
Hwy 6 (Jasper Ave to 1-380)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2020-2025
Interchange at Forevergreen Rd off 1-380
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$20,000,000 2020-2025
Forevergreen Jasper to James Ave)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2025-2030
$34,298,000
2012-2040 Long Range Plan - Locally Funded Transportation Infrastructure Projects
Fvhihi4 R
�.,
Project Title - "
Project`Des' iption`(include:,type of'' reject, location, Iengthr etc:)
$ Cost -Estimate
(Present -dollar)
Anticipated Year`of
Construction (2012-2020,
2021-2030.2031-2040.
1
Railroad St. (Ireland to Main St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$180,000 ;
2010-2015
2
Roberts Ferry Rd (Goldfinch Dr. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$1,500,000
2010-2015
3
4
Third St. (College St to Grant St.)
College St. (Railroad to Third St.)
Improve Curb, Gutter and Sidewalks and Pave Street
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
$270,000
2010-2015
2010-2015
5
Grant St (Railroad St. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020
6
1 Main St. (Railroad St. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020
Second St. (Ireland Ave to Stephans St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$450,000
2015-2020
8
Third St. ( Grant to Brown St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$360,000
2015-2020
9
17
Summerha s St (H 6 south to end of St)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020-
10
340th St. (Ireland Ave to Kansas Ave.)
Grade and Pave and install infrastructure
$1,000,000
2020-2025
11
Brown St. (Hwy 6 south to Railroad Tracks)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2020-2025
12
1 Forevergreen Rd(Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
13
Oakdale (east to Jasper Ave)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
14
Oakdale (Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
15
Ireland (Oakdale to Forevergreen)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
16
Ireland (340th to 360th)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
17
Ireland 360th to IWV Rd.),
Grade and Pave and install infrastructure
$1,000,000
2030-2035
18
1360th (Ireland to Kansas),
Grade and Pave and install infrastructure
$1,000,000
2030-2035
19.
360th (Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
20
Half Moon (1-80 to Hwy 6)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
21
Half Moon (Hwy 6 to Oakdale)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
22
Half Moon (1-80 to 360th)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
23
$16,110,000
24
25
26
27
28
28
Prepared by: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340
Return to: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340
RESOLUTION NO. 2011-04
RESOLUTION AUTHORIZING STAFF TO SUBMIT THE FOLLOWING
CAPITAL TRANSPORTATION PROJECTS AND COST ESTIMATES TO THE
JOHNSON COUNTY COUNCIL OF GOVERNMENTS FOR INCLUSION IN THE
REVISED LONG RANGE TRANSPORTATION PLAN TO BE ADOPTED MAY OF 2012
WHEREAS, our community/organization is a member of the Johnson County Council of Governments; and
WHEREAS, the Federal Highway Administration now requires that the JCCOG Long Range Transportation
Plan include a fiscally constrained project list for the JCCOG urbanized area; and
WHEREAS, the Johnson County Council of Governments, Urbanized Area Policy Board has directed JCCOG
staff to receive said capital'transportation project lists by resolution
NOW, THEREFORE; BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF TIFFIN, IOWA, THAT:
1. The following list of anticipated federally funded projects be included in the revised version of the JCCOG
Long Range Transportation Plan to be adopted by May of 2012.
See Exhibit A
2. The following list of anticipated locally funded projects be included in the revised version of the JCCOG
Long Range Transportation Plan to be adopted by May of 2012.
See Exhibit B
Passed and approved thi day of Janua 2011.
o e . P Ili s, or
Y��4
ATTES .
Rut Demuth, City Clerk
It was moved by Council person Chris Ball and seconded by Council person Travis Weipert the Resolution be
adopted, and upon roll call there were:
AYES:' NAYS:
X
X
X
X
X
ABSENT:
Chris Ball
Jim Bartels
Mike Gericke
Mark Petersen
Travis Weipert
2012-2040 Long Range Plan - Federally Funded Transportation Infrastructure Projects
Fxhihit A
Project Title "
Project De`scr'iption (include type of project, location, length, etc.)-
$ Cost`EstirfiA Anticipated Year of
(Present dollar) Con'struction�(2012-2020,
2021-2030, 2031-2040
Ireland Ave ( Railroad St to Hwy 6)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,800,000 2010-2015
Trail (Jasper Ave to 1-380)
Grade and Pave Trail 1
$238,000 2010-2015
Jasper Ave (Hwy 6 south to Clear Creek Bridge)
Phase One
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2010-2015
Ireland Ave (1-80 to Clear Creek)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,500,000 2015-2020
Trail head east of Jasper Ave
Grade and Pave Trailhead
$30,000 2015-2020
Trailhead at Ireland
Grade and Pave Trailhead
$30,000 2015-2020
Ireland Ave (Clear Creek Bridge to Railroad St.)
Replace Bridge and Grade and Pave
$1,500,000 2015-2020
Jasper Ave (Bridge to 1-80) Phase Two
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2015-2020
Jasper Ave (Hwy 6 north 2000 ft) Phase Three
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2015-2020
Trail south on Ireland to Villages Development
Grade and Pave Trail
$200,000 2015-2020
Jasper Ave (Completed portion north to
Forevergreen Rd) Phase Four
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2020-2025
Hwy 6 (Ireland to Main St)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2020-2025
Hwy 6 (Ste hans St to Jasper Ave.)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$2,000,000 2020-2025
Hwy 6 (Jasper Ave to 1-380)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2020-2025
Interchange at Forevergreen Rd off 1-380
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$20,000,000 2020-2025
Forevergreen (Jasper to James Ave)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000 2025-2030
$34,298,000
P
2012-2040. Long Range Plan - Locally Funded Transportation Infrastructure Projects
Exhibit B
Project Title
Project Description:(include type of project, location, length, etc.)
$..Cost Estimate
(Present dollar)
Anticipated Year of
Construction (2012-202.0,
2021-2030 2031-2040
1
Railroad St. (Ireland to Main St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$180,000
2010-2015
2
Roberts Ferry Rd (Goldfinch Dr. to Hwy 6)
Omprove Curb, Gutter and Sidewalks and Pave Street
$1,500,000
2010-2015
3
4
Third St. (College St to Grant St.)
College St. (Railroad to Third St.)
Improve Curb, Gutter and Sidewalks and Pave Street
Improve Curb, Gutter and Sidewalks and Pave Street .
$270,000
$270,000
2010-2015
2010-2015
5
Grant St (Railroad St. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020
6
1 Main St. (Railroad St. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020
7
Second St. (Ireland Ave to Stephans St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$450,000
2015-2020
8
Third St. ( Grant to Brown St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$360,000
2015-2020
9
Summerhays St ( Hwy 6 south to end of St)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020
10
340th St. (Ireland Ave to Kansas Ave.)
Grade and Pave and install infrastructure
$1,000,000
2020-2025
11
Brown St. (Hwy 6 south to Railroad Tracks)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2020-2025
12
Forevergreen Rd(Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
13
Oakdale (east to Jasper Ave)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
14
Oakdale (Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
15
Ireland (Oakdale to Forevergreen)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
16
Ireland 340th to 360th)
Grade and Pave and install infrastructure
$1,000,000 2025-2030
17
Ireland (360th to IWV Rd.)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
18
360th Ireland to Kansas)
Grade and Pave and install infrastructure
$1,000,000.
2030-2035
19
360th (Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
20
Half Moon (1-80 to Hwy 6)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
21
Half Moon (Hwy 6 to Oakdale)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
22
Half Moon (1-80 to 360th)
Grade and Pave and install infrastructure •
$1,000,000
2030-2035
23
$16,110,000
24
25
26
27
28
28
Prepared by: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340
Return to: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340
RESOLUTION NO. 2011-04
RESOLUTION AUTHORIZING STAFF TO SUBMIT THE FOLLOWING
CAPITAL TRANSPORTATION PROJECTS AND COST ESTIMATES TO THE
JOHNSON COUNTY COUNCIL OF GOVERNMENTS FOR INCLUSION IN THE
REVISED LONG RANGE TRANSPORTATION PLAN TO BE ADOPTED MAY OF 2012
WHEREAS, our community/organization is a member of the Johnson County Council of Governments; and
WHEREAS, the Federal Highway Administration now requires that the JCCOG Long Range Transportation
Plan include a fiscally constrained project list for the JCCOG urbanized area; and
WHEREAS, the Johnson County Council of Governments Urbanized Area Policy Board has directed JCCOG
staff to receive said capital transportation project lists by resolution
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF TIFFIN, IOWA, THAT:
The following list of anticipated federally funded projects .be included in the revised version of the JCCOG
Long Range Transportation Plan to be adopted by May of 2012.
See Exhibit A
2. The following list of anticipated locally funded projects be included in the revised version of the JCCOG
Long Range Transportation Plan to be adopted by May of 2012.
See Exhibit B
Passed and approved this 12th day of January, 2011.
( lypj '�' "
o e W.Phi ips, o
ATTES
Ruthemuth, ldiClerk
It was moved by Council person Chris Ball and seconded by Council person Travis Weipert the Resolution be
adopted, and upon roll call there were:
AYES:
NAYS: ABSENT:
X
Chris Ball
X
Jim Bartels
X
Mike Gericke
X
Mark Petersen
X
Travis Weipert
2012-2040 Long Range Plan - Federally Funded Transportation Infrastructure Projects
Cvhihi+ D
Project Title
Project=Description (include type of projectaocation, length', etc:);
$°Cost Estimate'
(Present 'dollar)
Anticipated Year of
Construction (2012-2020,
2021-2030„2031-2040
Ireland Ave ( Railroad St to Hwy 6)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,800,000
2010-2015 f
Trail (Jasper Ave to 1-380)
Grade and Pave Trail
$238,000
2010-2015
Jasper Ave (Hwy 6 south to Clear Creek Bridge)
Phase One
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000
2010-2015
Ireland Ave (1-80 to Clear Creek)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,500,000
2015-2020
Trail head east of Jasper Ave
Grade and Pave Trailhead
$30,000
2015-2020
Trailhead at Ireland
Grade and Pave Trailhead
$30,000
2015-2020
Ireland Ave (Clear Creek Bridge to Railroad St.)
Replace Bridge and Grade and Pave
$1,500,000
2015-2020
Jasper Ave Bridge to 1-80) Phase Two
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000
2015-2020
Jasper Ave (Hwy 6 north 2000 ft) Phase Three
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000
2015-2020
Trail south on Ireland to Villages Development
Grade and Pave Trail
$200,000
2015-2020
Jasper Ave (Completed portion north to
Forevergreen Rd) Phase Four
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000
2020-2025
Hwy 6 (Ireland to Main St)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000
2020-2025
Hwy 6 (Stephans St to Jasper Ave.)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$2,000,000
2020-2025
Hwy 6 (Jasper Ave to 1-380)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000
2020-2025
Interchange at Forevergreen Rd off 1-380
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$20,000,000
2020-2025
Forevergreen (Jasper to James Ave)
Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails
$1,000,000
2025-2030
$34,298,000
a
2012-2040 Long Range Plan - Locally Funded Transportation Infrastructure Projects
Fxhihit R
i Project Title
Project Description (include type of project,-location,,length, etc.)
$ GostEstimate
(Present dollar)
Anticipated Year of
Construction (2012-2020-
2012-20202021-2030,.20312040
2021-2030,,2031-2040
1
Railroad St. (Ireland to Main St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$180,000
2010-2015
2
Roberts Ferry Rd (Goldfinch Dr. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$1,500,000
2010-2015
3Third
4
St. (College St to Grant St.)
College St. (Railroad to Third St.)
Improve Curb, Gutter and Sidewalks and Pave Street
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000 2010-2015
$270,000 2010-2015
5
Grant St (Railroad St. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020
6
Main St. (Railroad St. to Hwy 6)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2015-2020
7
Second St. (Ireland Ave to Stephans St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$450,000
2015-2020
8
Third St. ( Grant to Brown St.)
Improve Curb, Gutter and Sidewalks and Pave Street
$360,000
2015-2020
9
Summerha s St ( Hwy 6 south to end of St)
Improve Curb; Gutter and Sidewalks and Pave Street
$270,000
2015-2020
10
340th St. (Ireland Ave to Kansas Ave.)
Grade and Pave and install infrastructure
$1,000,000
2020-2025
11
Brown St. (Hwy 6 south to Railroad Tracks)
Improve Curb, Gutter and Sidewalks and Pave Street
$270,000
2020-2025
12
Forevergreen Rd(Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
13
Oakdale (east to Jasper Ave)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
14
Oakdale (Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
15
Ireland (Oakdale to Forevergreen)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
16
Ireland (340th to 360th)
Grade and Pave and install infrastructure
$1,000,000
2025-2030
17
Ireland (360th to IWV Rd.)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
18
360th Ireland to Kansas)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
19
360th (Ireland to Half Moon)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
20
Half Moon (1-80 to Hwy 6)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
21
Half Moon. (Hwy 6 to Oakdale)
Grade'and Pave and install infrastructure
$1,000,000
2030-2035
22
Half Moon (1-80 to 360th)
Grade and Pave and install infrastructure
$1,000,000
2030-2035
23
$16,110,000
24
25
26
27
-
28
28