Loading...
HomeMy Public PortalAboutResolutions-2011 - 05RESOLUTION 2011 - 05 A RESOLUTION FOR APPROVAL OF SELLING OF REAL ESTATE LOTS OWNED BY THE CITY OF TIFFIN IN TIMBER RIDGE VIEW PART TWO LOTS 31 WHEREAS, the City of Tiffin Iowa, An Iowa Municipality (The "City"), received, as part of the Settlement Agreement with LDR IOWA CITY LLC, A Wisconsin Limited Liability Company (LDR) a real estates lot known as Lot #31 WHEREAS, the lot have been declared clear of liens or encumbrances and transfer of property has been properly recorded with the Johnson County, Iowa Recorder, as previously recorded in Book 51, Page 168, WHEREAS, the City Council of the City, after holding a properly noticed public hearing on the issue; the City Council may desire to make a decision to sell the properties as detailed below: Lot #31, to sell to the public. AND WHEREAS, Notification to the Public will be published and posted as required in accordance to Iowa Code. (Mandated Procedures Attached.) NOW THEREFORE, IT IS RESOLVED THAT: 1. A Notice of the date, time, and place of the hearing on this issue was properly published. 2. A Hearing was held on the issue. 3. That the properties described below are henceforth zoned: Lot #31 R1 -C Residential 4. The City Attorney will examine and assist with all documents pursuant to the sale of real estate property in accordance to the Iowa Code. On the 91h day of February, 2011 at a regular City Council meeting of the City Council, Tiffin, Iowa, Council person Chris Ball introduced Resolution 2011-05 A RESOLUTION FOR APPROVAL OF SELLING OF REAL ESTATE LOTS OWNED BY THE CITY OF TIFFIN IN TIMBER RIDGE VIEW PART TWO LOT 31and seconded by Council person Travis Weipert and made motion for approval. a Ayes: Chris Ball, Jim Bartels, Mark Petersen, Travis Weipert Nay: None Absent: Mike Gericke With four votes for City Council approval, Mayor Phillips declared that the Resolution 2011-05 A RESOLUTION FOR APPROVAL OF SELLING OF REAL ESTATE LOTS OWNED BY THE CITY OF TIFFIN IN TIMBER RIDGE VIEW PART TWO LOTS 31 be adopted and signified his approval of the same by affixing his signature thereto. Passed and approved this 9th day of February 2011. city !Affth ILoo�� �I - . -. es . Rut Demuth, City Clerk a { t Prepared by: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340 Return to: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340 RESOLUTION NO. 2011-04 RESOLUTION AUTHORIZING STAFF TO SUBMIT THE FOLLOWING CAPITAL TRANSPORTATION PROJECTS AND COST ESTIMATES TO THE JOHNSON COUNTY COUNCIL OF GOVERNMENTS FOR INCLUSION IN THE REVISED LONG RANGE TRANSPORTATION PLAN TO BE ADOPTED MAY OF 2012 WHEREAS, our community/organization is a'member of the Johnson County Council of Governments; and WHEREAS, the Federal Highway Administration now requires that the JCCOG Long Range Transportation Plan include a fiscally constrained project list for the JCCOG urbanized area; and WHEREAS, the Johnson County Council of Governments Urbanized Area Policy Board has directed JCCOG staff to receive said capital transportation project lists by.resolution ' NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF TIFFIN, IOWA, THAT: 1. The following list of anticipated federally funded projects be included in the revised version of the JCCOG Long Range Transportation Plan to be adopted by May of 2012. See Exhibit A 2. The following list of anticipated locally funded projects be included in the revised version of the. JCCOG Long Range Transportation Plan to be adopted by May of 2012. See Exhibit B Passed and approved this 12th day of Janu 11. W. Phi ps; ay ATTESC�?� Ruth emuth, City Clerk It was moved by Council person Chris Ball and seconded by Council person Travis Weipert the Resolution be adopted, and upon roll call there were: AYES: NAYS: ABSENT: X Chris Ball X Jim Bartels X Mike Gericke } X Mark Petersen X Travis Weipert 4 1 2012-2040 Long Range Plan - Federally Funded Transportation Infrastructure Projects Fxhihit A Project Title Project Descriptions(include type of:project`locatign, length, etc) I _ $ Cost Estimate Anticipated Year of (Present,dollar) Construction (2012-2020_, 2021-2030, 2031-2040 Ireland Ave ( Railroad St to Hwy 6) Grade& Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,800,000 2010-2015 Trail (Jasper Ave to 1-380) Grade and Pave Trail $238,000 2010-2015 Jasper Ave (Hwy 6 south to Clear Creek Bridge) Phase One Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2010-2015 Ireland Ave (1-80 to Clear Creek) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,500,000 2015-2020 Trail head east of Jasper Ave Grade and Pave Trailhead $30,000 2015-2020 Trailhead at Ireland Grade and Pave Trailhead $30,000 2015-2020 Ireland Ave (Clear Creek Bridge to Railroad St.) Replace Bridge and Grade and Pave $1,500,000 2015-2020 Jasper Ave (Bridge to 1-80) Phase Two Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2015-2020 Jasper Ave (Hwy 6 north 2000 ft) Phase Three Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2015-2020 Trail south on Ireland to Villages Development Grade and Pave Trail $200,000 2015-2020 Jasper Ave (Completed portion north to Forevergreen,Rd) Phase Four Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Hwy 6 (Ireland to Main St) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Hwy 6 (Ste hans St to Jasper Ave.) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $2,000,000 2020-2025 Hwy 6 (Jasper Ave to 1-380) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Interchange at Forevergreen Rd off 1-380 Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $20,000,000 2020-2025 Forevergreen Jasper to James Ave) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2025-2030 $34,298,000 2012-2040 Long Range Plan - Locally Funded Transportation Infrastructure Projects Fvhihi4 R �., Project Title - " Project`Des' iption`(include:,type of'' reject, location, Iengthr etc:) $ Cost -Estimate (Present -dollar) Anticipated Year`of Construction (2012-2020, 2021-2030.2031-2040. 1 Railroad St. (Ireland to Main St.) Improve Curb, Gutter and Sidewalks and Pave Street $180,000 ; 2010-2015 2 Roberts Ferry Rd (Goldfinch Dr. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $1,500,000 2010-2015 3 4 Third St. (College St to Grant St.) College St. (Railroad to Third St.) Improve Curb, Gutter and Sidewalks and Pave Street Improve Curb, Gutter and Sidewalks and Pave Street $270,000 $270,000 2010-2015 2010-2015 5 Grant St (Railroad St. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020 6 1 Main St. (Railroad St. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020 Second St. (Ireland Ave to Stephans St.) Improve Curb, Gutter and Sidewalks and Pave Street $450,000 2015-2020 8 Third St. ( Grant to Brown St.) Improve Curb, Gutter and Sidewalks and Pave Street $360,000 2015-2020 9 17 Summerha s St (H 6 south to end of St) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020- 10 340th St. (Ireland Ave to Kansas Ave.) Grade and Pave and install infrastructure $1,000,000 2020-2025 11 Brown St. (Hwy 6 south to Railroad Tracks) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2020-2025 12 1 Forevergreen Rd(Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2025-2030 13 Oakdale (east to Jasper Ave) Grade and Pave and install infrastructure $1,000,000 2025-2030 14 Oakdale (Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2025-2030 15 Ireland (Oakdale to Forevergreen) Grade and Pave and install infrastructure $1,000,000 2025-2030 16 Ireland (340th to 360th) Grade and Pave and install infrastructure $1,000,000 2025-2030 17 Ireland 360th to IWV Rd.), Grade and Pave and install infrastructure $1,000,000 2030-2035 18 1360th (Ireland to Kansas), Grade and Pave and install infrastructure $1,000,000 2030-2035 19. 360th (Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2030-2035 20 Half Moon (1-80 to Hwy 6) Grade and Pave and install infrastructure $1,000,000 2030-2035 21 Half Moon (Hwy 6 to Oakdale) Grade and Pave and install infrastructure $1,000,000 2030-2035 22 Half Moon (1-80 to 360th) Grade and Pave and install infrastructure $1,000,000 2030-2035 23 $16,110,000 24 25 26 27 28 28 Prepared by: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340 Return to: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340 RESOLUTION NO. 2011-04 RESOLUTION AUTHORIZING STAFF TO SUBMIT THE FOLLOWING CAPITAL TRANSPORTATION PROJECTS AND COST ESTIMATES TO THE JOHNSON COUNTY COUNCIL OF GOVERNMENTS FOR INCLUSION IN THE REVISED LONG RANGE TRANSPORTATION PLAN TO BE ADOPTED MAY OF 2012 WHEREAS, our community/organization is a member of the Johnson County Council of Governments; and WHEREAS, the Federal Highway Administration now requires that the JCCOG Long Range Transportation Plan include a fiscally constrained project list for the JCCOG urbanized area; and WHEREAS, the Johnson County Council of Governments, Urbanized Area Policy Board has directed JCCOG staff to receive said capital'transportation project lists by resolution NOW, THEREFORE; BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF TIFFIN, IOWA, THAT: 1. The following list of anticipated federally funded projects be included in the revised version of the JCCOG Long Range Transportation Plan to be adopted by May of 2012. See Exhibit A 2. The following list of anticipated locally funded projects be included in the revised version of the JCCOG Long Range Transportation Plan to be adopted by May of 2012. See Exhibit B Passed and approved thi day of Janua 2011. o e . P Ili s, or Y��4 ATTES . Rut Demuth, City Clerk It was moved by Council person Chris Ball and seconded by Council person Travis Weipert the Resolution be adopted, and upon roll call there were: AYES:' NAYS: X X X X X ABSENT: Chris Ball Jim Bartels Mike Gericke Mark Petersen Travis Weipert 2012-2040 Long Range Plan - Federally Funded Transportation Infrastructure Projects Fxhihit A Project Title " Project De`scr'iption (include type of project, location, length, etc.)- $ Cost`EstirfiA Anticipated Year of (Present dollar) Con'struction�(2012-2020, 2021-2030, 2031-2040 Ireland Ave ( Railroad St to Hwy 6) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,800,000 2010-2015 Trail (Jasper Ave to 1-380) Grade and Pave Trail 1 $238,000 2010-2015 Jasper Ave (Hwy 6 south to Clear Creek Bridge) Phase One Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2010-2015 Ireland Ave (1-80 to Clear Creek) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,500,000 2015-2020 Trail head east of Jasper Ave Grade and Pave Trailhead $30,000 2015-2020 Trailhead at Ireland Grade and Pave Trailhead $30,000 2015-2020 Ireland Ave (Clear Creek Bridge to Railroad St.) Replace Bridge and Grade and Pave $1,500,000 2015-2020 Jasper Ave (Bridge to 1-80) Phase Two Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2015-2020 Jasper Ave (Hwy 6 north 2000 ft) Phase Three Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2015-2020 Trail south on Ireland to Villages Development Grade and Pave Trail $200,000 2015-2020 Jasper Ave (Completed portion north to Forevergreen Rd) Phase Four Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Hwy 6 (Ireland to Main St) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Hwy 6 (Ste hans St to Jasper Ave.) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $2,000,000 2020-2025 Hwy 6 (Jasper Ave to 1-380) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Interchange at Forevergreen Rd off 1-380 Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $20,000,000 2020-2025 Forevergreen (Jasper to James Ave) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2025-2030 $34,298,000 P 2012-2040. Long Range Plan - Locally Funded Transportation Infrastructure Projects Exhibit B Project Title Project Description:(include type of project, location, length, etc.) $..Cost Estimate (Present dollar) Anticipated Year of Construction (2012-202.0, 2021-2030 2031-2040 1 Railroad St. (Ireland to Main St.) Improve Curb, Gutter and Sidewalks and Pave Street $180,000 2010-2015 2 Roberts Ferry Rd (Goldfinch Dr. to Hwy 6) Omprove Curb, Gutter and Sidewalks and Pave Street $1,500,000 2010-2015 3 4 Third St. (College St to Grant St.) College St. (Railroad to Third St.) Improve Curb, Gutter and Sidewalks and Pave Street Improve Curb, Gutter and Sidewalks and Pave Street . $270,000 $270,000 2010-2015 2010-2015 5 Grant St (Railroad St. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020 6 1 Main St. (Railroad St. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020 7 Second St. (Ireland Ave to Stephans St.) Improve Curb, Gutter and Sidewalks and Pave Street $450,000 2015-2020 8 Third St. ( Grant to Brown St.) Improve Curb, Gutter and Sidewalks and Pave Street $360,000 2015-2020 9 Summerhays St ( Hwy 6 south to end of St) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020 10 340th St. (Ireland Ave to Kansas Ave.) Grade and Pave and install infrastructure $1,000,000 2020-2025 11 Brown St. (Hwy 6 south to Railroad Tracks) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2020-2025 12 Forevergreen Rd(Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2025-2030 13 Oakdale (east to Jasper Ave) Grade and Pave and install infrastructure $1,000,000 2025-2030 14 Oakdale (Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2025-2030 15 Ireland (Oakdale to Forevergreen) Grade and Pave and install infrastructure $1,000,000 2025-2030 16 Ireland 340th to 360th) Grade and Pave and install infrastructure $1,000,000 2025-2030 17 Ireland (360th to IWV Rd.) Grade and Pave and install infrastructure $1,000,000 2030-2035 18 360th Ireland to Kansas) Grade and Pave and install infrastructure $1,000,000. 2030-2035 19 360th (Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2030-2035 20 Half Moon (1-80 to Hwy 6) Grade and Pave and install infrastructure $1,000,000 2030-2035 21 Half Moon (Hwy 6 to Oakdale) Grade and Pave and install infrastructure $1,000,000 2030-2035 22 Half Moon (1-80 to 360th) Grade and Pave and install infrastructure • $1,000,000 2030-2035 23 $16,110,000 24 25 26 27 28 28 Prepared by: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340 Return to: Ruth Demuth, City Clerk of Tiffin, Johnson County, Iowa 201 Main St., P.O. Box 259, Tiffin, Iowa 52340 RESOLUTION NO. 2011-04 RESOLUTION AUTHORIZING STAFF TO SUBMIT THE FOLLOWING CAPITAL TRANSPORTATION PROJECTS AND COST ESTIMATES TO THE JOHNSON COUNTY COUNCIL OF GOVERNMENTS FOR INCLUSION IN THE REVISED LONG RANGE TRANSPORTATION PLAN TO BE ADOPTED MAY OF 2012 WHEREAS, our community/organization is a member of the Johnson County Council of Governments; and WHEREAS, the Federal Highway Administration now requires that the JCCOG Long Range Transportation Plan include a fiscally constrained project list for the JCCOG urbanized area; and WHEREAS, the Johnson County Council of Governments Urbanized Area Policy Board has directed JCCOG staff to receive said capital transportation project lists by resolution NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF TIFFIN, IOWA, THAT: The following list of anticipated federally funded projects .be included in the revised version of the JCCOG Long Range Transportation Plan to be adopted by May of 2012. See Exhibit A 2. The following list of anticipated locally funded projects be included in the revised version of the JCCOG Long Range Transportation Plan to be adopted by May of 2012. See Exhibit B Passed and approved this 12th day of January, 2011. ( lypj '�' " o e W.Phi ips, o ATTES Ruthemuth, ldiClerk It was moved by Council person Chris Ball and seconded by Council person Travis Weipert the Resolution be adopted, and upon roll call there were: AYES: NAYS: ABSENT: X Chris Ball X Jim Bartels X Mike Gericke X Mark Petersen X Travis Weipert 2012-2040 Long Range Plan - Federally Funded Transportation Infrastructure Projects Cvhihi+ D Project Title Project=Description (include type of projectaocation, length', etc:); $°Cost Estimate' (Present 'dollar) Anticipated Year of Construction (2012-2020, 2021-2030„2031-2040 Ireland Ave ( Railroad St to Hwy 6) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,800,000 2010-2015 f Trail (Jasper Ave to 1-380) Grade and Pave Trail $238,000 2010-2015 Jasper Ave (Hwy 6 south to Clear Creek Bridge) Phase One Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2010-2015 Ireland Ave (1-80 to Clear Creek) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,500,000 2015-2020 Trail head east of Jasper Ave Grade and Pave Trailhead $30,000 2015-2020 Trailhead at Ireland Grade and Pave Trailhead $30,000 2015-2020 Ireland Ave (Clear Creek Bridge to Railroad St.) Replace Bridge and Grade and Pave $1,500,000 2015-2020 Jasper Ave Bridge to 1-80) Phase Two Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2015-2020 Jasper Ave (Hwy 6 north 2000 ft) Phase Three Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2015-2020 Trail south on Ireland to Villages Development Grade and Pave Trail $200,000 2015-2020 Jasper Ave (Completed portion north to Forevergreen Rd) Phase Four Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Hwy 6 (Ireland to Main St) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Hwy 6 (Stephans St to Jasper Ave.) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $2,000,000 2020-2025 Hwy 6 (Jasper Ave to 1-380) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2020-2025 Interchange at Forevergreen Rd off 1-380 Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $20,000,000 2020-2025 Forevergreen (Jasper to James Ave) Grade & Pave Street, Install Curb, Gutter and Sidewalks or Trails $1,000,000 2025-2030 $34,298,000 a 2012-2040 Long Range Plan - Locally Funded Transportation Infrastructure Projects Fxhihit R i Project Title Project Description (include type of project,-location,,length, etc.) $ GostEstimate (Present dollar) Anticipated Year of Construction (2012-2020- 2012-20202021-2030,.20312040 2021-2030,,2031-2040 1 Railroad St. (Ireland to Main St.) Improve Curb, Gutter and Sidewalks and Pave Street $180,000 2010-2015 2 Roberts Ferry Rd (Goldfinch Dr. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $1,500,000 2010-2015 3Third 4 St. (College St to Grant St.) College St. (Railroad to Third St.) Improve Curb, Gutter and Sidewalks and Pave Street Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2010-2015 $270,000 2010-2015 5 Grant St (Railroad St. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020 6 Main St. (Railroad St. to Hwy 6) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2015-2020 7 Second St. (Ireland Ave to Stephans St.) Improve Curb, Gutter and Sidewalks and Pave Street $450,000 2015-2020 8 Third St. ( Grant to Brown St.) Improve Curb, Gutter and Sidewalks and Pave Street $360,000 2015-2020 9 Summerha s St ( Hwy 6 south to end of St) Improve Curb; Gutter and Sidewalks and Pave Street $270,000 2015-2020 10 340th St. (Ireland Ave to Kansas Ave.) Grade and Pave and install infrastructure $1,000,000 2020-2025 11 Brown St. (Hwy 6 south to Railroad Tracks) Improve Curb, Gutter and Sidewalks and Pave Street $270,000 2020-2025 12 Forevergreen Rd(Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2025-2030 13 Oakdale (east to Jasper Ave) Grade and Pave and install infrastructure $1,000,000 2025-2030 14 Oakdale (Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2025-2030 15 Ireland (Oakdale to Forevergreen) Grade and Pave and install infrastructure $1,000,000 2025-2030 16 Ireland (340th to 360th) Grade and Pave and install infrastructure $1,000,000 2025-2030 17 Ireland (360th to IWV Rd.) Grade and Pave and install infrastructure $1,000,000 2030-2035 18 360th Ireland to Kansas) Grade and Pave and install infrastructure $1,000,000 2030-2035 19 360th (Ireland to Half Moon) Grade and Pave and install infrastructure $1,000,000 2030-2035 20 Half Moon (1-80 to Hwy 6) Grade and Pave and install infrastructure $1,000,000 2030-2035 21 Half Moon. (Hwy 6 to Oakdale) Grade'and Pave and install infrastructure $1,000,000 2030-2035 22 Half Moon (1-80 to 360th) Grade and Pave and install infrastructure $1,000,000 2030-2035 23 $16,110,000 24 25 26 27 - 28 28