RESOLUTION NO.
A RESOLUTION:
PRESENTED
88-80 ADOPTED April 27, 198:$
AUTHORIZING A CHANGE ORDER TO THE ROUTE 643 WATERLINE
PROJECT FOR CONSTRUCTION ADMINISTRATION AND INSPECTION
April 27, 1988
WHEREAS, Camp Dresser and McKee prepared construction drawings and
specifications for the 16 inch Route 643 waterline and performed the
construction administration and inspection for the Town; and
WHEREAS, Perry Engineering Company, Incorporated was delayed in
completing installation of the waterline; and
WHEREAS, under the terms of the construction contract, the project
was to have been completed on September 2, 1987; and
WHEREAS, the terms of the contract with Camp Dresser and McKee are
based on services which would have ended in September, 1987 and the
contract was extended to November, 1987 at a cost of $9,200.00; and
WHEREAS, Camp Dresser and McKee has provided contract administration
and inspection services for an additional five months, until April 1,
1988; and
WHEREAS, the Director of Engineering and Public Works reconmmends
approval of a change order in the amount of $13,500.00 to CDM's current
contract with the Town:
WHEREAS, the Town will withhold from the final payment to Perry
Engineering, liquidated damages in the amount of $19,705.00 of the
$22,700.00 additional cost for engineering and inspection.
THEREFORE, RESOLVED by the Council of the Town of Leesburg in
Virginia as follows:
SECTION I. The Manager is authorized to execute a change order on
-2-
AUTHORIZING A CHANGE ORDER TO THE ROUTE 643 WATERLINE PROJECT FOR
CONSTRUCTION ADMINISTRATION AND INSPECTION
behalf of the Town with Camp Dresser & McKee for additional construction
administration and inspection services in an amount not to exceed
$13,500.00.
SECTION II. An appropriation is made from the Utility fund to
account no. 3120.700.140.300 Route 643 Waterline Extension in the amount
of $13,500.00.