HomeMy Public PortalAbout1988_06_08_R110RESOLUTION NO, 88-110
A RESOLUTION: SUPPORTING A DESIGN MODIFICATION TO THE PHASE VI STORM
DRAINAGE PROJECT
WHEREAS, the Phase VI Storm Drainage Improvements Project was
originally proposed in the 1977 Storm Drainage Master Plan prepared by
Bengtson, DeBell, Elkin & Titus; and
WHEREAS, this project has been included in the CIP for a number of
years and is funded in the FY 88 and 89 budgets and Kamber Engineering,
Inc. ]las been hired by the Town to design and prepare construction plans
and specifications for the improvements; and
WHEREAS, Dry Mill Road experiences frequent flooding which will be
alleviated by the Phase VI improvements.
WHEREAS, the Northern Virginia Regional Park Authority (NVRPA) staff
has recommended denial of the original design which shows only minor
improvements to an existing grass lined channel along the W&OD Bike Trail
and is in conformance with the 1977 Master Plan; and
WHEREAS, an alternative routing of the stormwater acceptable to the
NVRPA has been prepared and presented to the NVRPA; and
WHEREAS, Cost estimates indicated that the revised alignment will be
approximately $200,000.00 more than the original alignment, yet the total
amount is still within the proposed construction budget:
THEREFORE, RESOLVED by the Council. of the Town of Leesburg in Virginia
as follows:
PRESENTED June 8, 1988
~DOPTED June 8, 1988
-'2--
S~*PPORTING A DESIGN MODIFICATION TO THE PHASE VI STORM DRAINAGE PROJECT
SECTION I. The revised plan which reroutes stormwater from Dry Mill
Road to proposed underground conduit in the NVRP Bike Trail r~ght-of-way is
supported by this Council.
SECTION II. The NVRPA is requested to review, process and approve the
reuised alignment as quickly as possible in order that this important
project can move ahead.