AN ORDINANCE OF THE CITY OF JEFFERSON, MISSOURI, AUTHORIZING THE
MAYOR AND CITY CLERK TO EXECUTE A $74,922.50 AGREEMENT WITH
STOCKMAN CONSTRUCTION CORP. FOR THE WESTWOOD DRIVE
STORMWATER PROJECT.
BE IT ENACTED BY THE COUNCIL OF THE CITY OF JEFFERSON, MISSOURI, AS
FOLLOWS:
WHEREAS, Stockman Construction Corp. has become the apparent lowest and best
bidder on the Westwood Drive Stormwater Project.
NOW, THEREFORE, BE IT ENACTED BY THE COUNCIL OF THE CITY OF JEFFERSON,
MISSOURI, AS FOLLOWS:
Section 1. The $74,922.50 bid of Stockman Construction Corp. is declared to be the
lowest and best bid and is hereby accepted on the Westwood Drive Stormwater Project.
Section 2. The Mayor and City Clerk are hereby authorized to execute an agreement
with Stockman Construction Corp. for the Westwood Drive Stormwater Project.
Section 3. The agreement shall be substantially the same in form and content as that
agreement attached hereto as Exhibit A.
Section 4. This Ordinance shall be in full force and effect from and after the date of its
passage and
'approval.
•
Passed:/ / .WI/0 Approved: ✓K 1( � �r 2090
OfailAki - CIA°1
Presiding Officer Mayor Carrie Tergin
ATTEST: APPROVED AS TO FORM:
/ -/1/4�I' /tel-4(4, /(-17±1_,_ 1
ity Clerk: bay Counselor
FINANCE DEPARTMENT
PURCHASING DIVISION
SUBJECT: Bid 2846 — Project No. 33081 —Westwood Drive Stromwater
Public Works, Engineering — Opened 3-8-16
RECOMMENDATION:
Staff recommends award of the bid to the lowest and best bid meeting the specifications,
Stockman Construction Corporation of Jefferson City, Missouri, in the amount of $74,922.50.
BIDS RECEIVED:
Stockman Construction Corp., Jefferson City, MO $ 74,922.50
Mera Excavating, LLC, Bonnots Mill, MO $ 80,480.48
Kauffman Enterprises, LLC, Jefferson City, MO $ 86,480.00
Ken Kauffman & Sons Excavating, LLC, Jefferson City, MO $ 87,410.00
B&P Patterson, LLC, Linn, MO $ 91,795.00
Ed Laubinger Excavating, LLC, St. Clair, MO $ 95,908.00
Concrete Solution, LLC, Linn, MO $ 96,593.96
Twehous Exavating Co., Inc., Jefferson City, MO $ 97,900.09
Sam Gaines Construction, Inc., New Bloomfield, MO $ 129,070.00
Lamke Trenching & Excavating, Inc., Marthasville, MO $ 142,567.37
The bid was advertised in News Tribune, posted on the city web site and specifications were sent
to seven plan houses.
FISCAL NOTE:
44-990-576016 (Sales Tax F)
Westwood Drive Stormwater
2015-16 Budget $74,922.50
Expenses -0-
Encumbered -0-
Bid No. 2846 $74,922.50
Balance -0-
PAST PERFORMANCE:
This vendor has been awarded projects in the past and has completed them as specified and bid.
ATTACHMENTS - SUPPORTING DOCUMENTATION
Signature Ld .J A'�s�l `!.L\ /\ ✓
Purch sin g nt Director of Public Works
``tt IF I f!
14� ,+i 0%
Department of Public Works Memorandum
320 E. McCarty Street •Jefferson City, Missouri 65101 • P 573-634-6410 • F 573-634-6562 • www.jeffcitymo.orq
Date: March 10, 2016
To: Terry Stephenson; Purchasing Director, Finance
From: David Bange, City Engineer D—c)�
Subject: Project No. 33081 —Westwood Drive Stormwater
Bid No. 2846
Public Works has completed a review of the bids opened at 1:30 pm on March 8, 2016 for the above
noted project. As part of the review all the bids were tabulated to check for math errors and to compare
unit price quotes of the various contractors. Attached to this memo is the tabulation of the ten (10)bids
received for the project, as well as a listing of the registered plan holders.
Based on our review, we recommend acceptance of the bid from the low bidder Stockman Construction
Corp,2021 Idlewood Rd,Jefferson City, MO 65109. The total amount of the contract will be $74,922.50.
The project will be expensed as follows:
Stockman Construction Corp.(S74,922.50):
Account Number: Amount Available: Required: Remaining:
44-990-576016 574,92250 $74,922.50 $0.00
If you need any other information please feel free to contact me at extension 6433.
Attachments: Bid Tabulation Sheet, Plan Holders List
DB:tg
cc: Project file
Writer's file
Page 1 of 3 CITY OF JEFFERSON
Date: 08/03/2016 BID TABULATION
Bid No. 2846 WESTWOOD DRIVE STORMWATER
PROJECT NO. 33081
ENGINEER'S ESTIMATE Stockman Construction Mera Excavating, LLC Kauffman Enterprises,
LLC
ITEM APPROX.
NO. DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 Project Mobilization LS 1 $2,500.00 $2,500.00 $1,800.00 $1,800.00 $2,077.08 $2,077.08 $6,875.00 $6,875.00
2 Construction Signage/Traffic Control EA 4 $1,500.00 $6,000.00 $500.00 $2,000.00 $376.06 $1,504.24 $250.00 $1,000.00
3 Inlet Protection EA 4 $200.00 $800.00 $100.00 $400.00 $131.73 $526.92 $150.00 $600.00
4 Sediment Barrier LF 200 $5.00 $1,000.00 $5.00 $1,000.00 $5.46 $1,092.00 $5.00 $1,000.00
5 Removals . LS 1 $6,000.00 $6,000.00 $3,500.00 $3,500.00 $6,351.81 $6,351.81 $11,200.00 $11,200.00
6 Rock Excavation CY 20 $150.00 $3,000.00 $75.00 $1,500.00 $204.58 $4,091.60 $75.00 $1,500.00
7 Subgrade Stabilization Ton 50 $50.00 $2,500.00 $43.00 $2,150.00 $66.46 $3,323.00 $20.00 $1,000.00
8 15"dia RCP Class III LF 30.5 $70.00 $2,135.00 $80.00 $2,440.00 $108.90 $3,321.45 $60.00 $1,830.00
9 48"dia RCP Class III LF 29.4 $375.00 $11,025.00 $275.00 $8,085.00 $332.79 $9,784.03 $175.00 $5,145.00
10 Concrete Flowline for ex. Pipe CY 1.6 $825.00 $1,320.00 $3,750.00 $6,000.00 $1,513.06 $2,420.90 $4,687.50 $7,500.00
11 Type C Inlet(8'x 3') EA 2 $4,500.00 $9,000.00 $6,200.00 $12,400.00 $5,019.14 $10,038.28 $5,500.00 $11,000.00
12 Type C Inlet(6'x 4') EA 1 $4,500.00 $4,500.00 $5,000.00 $5,000.00 $4,574.14 $4,574.14 $4,500.00 $4,500.00
13 Modify Ex. Inlet Invert& Pipe EA 1 $3,000.00 $3,000.00 $1,350.00 $1,350.00 $1,122.27 $1,122.27 $1,000.00 $1,000.00
Connection
14 Curb and Gutter(Remove& Replace) LF 220 $35.00 $7,700.00 $32.00 $7,040.00 $44.23 $9,730.60 $34.00 $7,480.00
15 6.0"thick Driveway; (Remove& SY 13 $90.00 $1,170.00 $105.00 $1,365.00 $128.86 $1,675.18 $75.00 $975.00
Replace)
16 7.5"thick Street Patch; (Remove& SY 275 $65.00 $17,875.00 $53.00 $14,575.00 $46.66 $12,831.50 $55.00 $15,125.00
Replace)
17 Earthwork; Site 1 LS 1 $4,000.00 $4,000.00 $800.00 $800.00 $1,328.97 $1,328.97 $3,000.00 $3,000.00
18 Earthwork; Site 2 LS 1 $2,000.00 $2,000.00 $800.00 $800.00 $1,328.97 $1,328.97 $2,500.00 $2,500.00
19 Final Site Seeding AC 0.1 $10,000.00 $1,000.00 $10,000.00 $1,000.00 $1,169.03 $116.90 $15,000.00 $1,500.00
20 Temporary Site Stabilization SY 225 $4.75 $1,068.75 $1.50 $337.50 $5.20 $1,170.00 52:00 $450.00
21 Duel Cleanout EA 2 $300.00 $600.00 $175.00 8350.00 $206.06 $412.12 $150.00 $300.00
22 04"dia. Schedule 40, Lateral LF 40 $30.00 $1,200.00 $14.25 $570.00 $6.24 $249.60 $10.00 $400.00
23 Extra Excavation & Backfill for Sewer CY 4 $150.00 $600.00 $115.00 $460.00 $352.23 $1,408.92 $150.00 $600.00
Lateral Work
TOTAL BASE BID $89,993.75 $74,922.50 $80,480.48 $86,480.00
-16.7% -10.6% -3.9%
%OVER/UNDER ENGINEER'S EST.
Page 2 of 3 CITY OF JEFFERSON
Date: 08/03/2016 BID TABULATION
Bid No. WESTWOOD DRIVE STORMWATER
PROJECT NO.33081
Ken Kauffman and Sons B&P Patterson Concrete Ed Laubinger Excavating Concret Solutions LLC
ITEM APPROX.
NO. DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 Project Mobilization LS 1 $4,000.00 $4,000.00 $3,800.00 $3,800.00 $7,500.00 $7,500.00 $10,600.00 $10,600.00
2 Construction Signage/Traffic Control EA 4 $500.00 $2,000.00 $330.00 $1,320.00 $1,000.00 $4,000.00 $500.00 $2,000.00
3 Inlet Protection EA 4 $150.00 $600.00 $50.00 • $200.00 $160.00 $640.00 $200.00 $800.00
4 Sediment Barrier LF 200 $3.00 $600.00 $4.50 $900.00 $4.50 $900.00 $3.00 $600.00
5 Removals •
LS 1 $4,000.00 $4,000.00 $3,000.00 $3,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00
6 Rock Excavation CY 20 $25.00 $500.00 $150.00 $3,000.00 $150.00 $3,000.00 $100.00 $2,000.00
7 Subgrade Stabilization Ton 50 $30.00 $1,500.00 $50.00 $2,500.00 $28.00 $1,400.00 $50.00 $2,500.00
8 15"dia RCP Class III LF 30.5 $150.00 $4,575.00 $90.00 $2,745.00 $70.00 $2,135.00 $88.32 $2,693.76
9 48"dia RCP Class III • LF 29.4 $250.00 $7,350.00 $300.00 $8,820.00 $295.00 $8,673.00 $191.00 $5,615.40
10 Concrete Flowline for ex. Pipe CY 1.6 $2,000.00 $3,200.00 $2,150.00 $3,440.00 $3,800.00 $6,080.00 $1,718.00 $2,748.80
11 Type C Inlet(8' x 3') EA 2 $5,000.00 $10,000.00 $5,500.00 $11,000.00 $5,600.00 $11,200.00 $8,950.00 $17,900.00
12 Type C Inlet(6'x 4') EA 1 $4,000.00 $4,000.00 $4,000.00 $4,000.00 $4,200.00 $4,200.00 $6,900.00 $6,900.00
13 Modify Ex. Inlet Invert& Pipe EA 1 $1,000.00 $1,000.00 $1,500.00 $1,500.00 $1,500.00 $1,500.00 $300.00 $300.00
Connection
14 Curb and Gutter(Remove& Replace) LF 220 $46.00 $10,120.00 $34.00 $7,480.00 $28.00 $6,160.00 $25.00 $5,500.00
15 6.0"thick Driveway; (Remove& SY 13 $230.00 $2,990.00 $290.00 $3,770.00 $120.00 $1,560.00 $50.00 $650.00
Replace)
16 7.5"thick Street Patch; (Remove& SY 275 $70.00 $19,250.00 $75.00 $20,625.00 $74.00 $20,350.00 $58.84 $16,181.00
Replace)
17 Earthwork; Site 1 LS 1 $4,000.00 $4,000.00 $5,500.00 $5,500.00 $1,500.00 $1,500.00 $500.00 $500.00
18 Earthwork; Site 2 LS 1 $4,000.00 $4,000.00 $4,400.00 $4,400.00 $1,000.00 $1,000.00 $500.00 $500.00
19 Final Site Seeding AC 0.1 $10,000.00 $1,000.00 $6,000.00 $600.00 $15,000.00 $1,500.00 $10,000.00 $1,000.00
20 Temporary Site Stabilization SY 225 $5.00 $1,125.00 $6.20 $1,395.00 $2.00 $450.00 $25.00 $5,625.00
21 Duel Cleanout EA 2 $100.00 $200.00 $200.00 $400.00 $200.00 $400.00 $50.00 $100.00
22 04"dia. Schedule 40, Lateral LF 40 $25.00 $1,000.00 $25.00 $1,000.00 $40.00 $1,600.00 • $42.00 $1,680.00
23 Extra Excavation& Backfill for Sewer CY 4 $100.00 $400.00 $100.00 $400.00 $40.00 $160.00 $50.00 $200.00
Lateral Work
TOTAL BASE BID $87,410.00 $91,795.00 $95,908.00 $96,593.96
-2.9% 2.0% 6.6% 7.3%
%OVER/UNDER ENGINEER'S EST.
ERROR ERROR
•
/
Page 3 of 3 CITY OF JEFFERSON
Date: 08/03/2016 BID TABULATION
Bid No. WESTWOOD DRIVE STORMWATER
PROJECT NO. 33081
Twehous Excavating Sam Gaines Construction, Lamke Trenching and
Company Inc. Excavating
ITEMAPPROX.
NO. DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
1 Project Mobilization LS 1 $1,849.79 $1,849.79 $2,000.00' $2,000.00 $14,000.00 $14,000.00
2 Construction Signage/Traffic Control EA 4 $4,250.00 $17,000.00 $500.00 $2,000.00 $1,500.00 $6,000.00
3 Inlet Protection EA 4 $395.00 $1,580.00 $200.00 $800.00 $250.00 $1,000.00
4 Sediment Barrier LF 200 $9.00 $1,800.00 $8.00 $1,600.00 $5.50 $1,100.00
5 Removals LS 1 $3,500.00 $3,500.00 $20,000.00 $20,000.00 $11,500.00 $11,500.00
6 Rock Excavation CY 20 $55.00 $1,100.00 $200.00 $4,000.00 $300.00 $6,000.00
7 Subgrade Stabilization Ton 50 $41.50 $2,075.00 $45.00 $2,250.00 $18.00 $900.00
8 15"dia RCP Class III LF 30.5 $111.00 $3,385.50 $180.00 $5,490.00 $283.00 $8,631.50
9 48"dia RCP Class III LF 29.4 $222.00 $6,526.80 $300.00 $8,820.00 $417.00 $12,259.80 .
10 Concrete Flowline for ex. Pipe CY 1.6 $2,750.00 $4,400.00 $1,250.00 $2,000.00 $1,465.00 $2,344.00
11 Type C Inlet(8'x 3') EA 2 $4,000.00 $8,000.00 $8,000.00 $16,000.00 $8,186.00 $16,372.00
12 Type C Inlet(6'x 4') EA 1 $5,750.00 $5,750.00 $6,000.00 $6,000.00 $7,200.00 $7,200.00 .
13 Modify Ex. Inlet Invert& Pipe EA 1 $2,500.00 $2,500.00 $3,000.00 $3,000.00 $750.07 $750.07
Connection
14 Curb and Gutter(Remove& Replace) LF 220 $55.55 $12,221.00 $46.00 $10,120.00 $64.00 $14,080.00
15 6.0"thick Driveway; (Remove& SY 13 $95.25 $1,238.25 $230.00 $2,990.00 $160.00 $2,080.00
Replace)
16 7.5"thick Street Patch; (Remove& SY 275 $76.95 $21,161.25 $70.00 $19,250.00 $95.00 $26,125.00
Replace)
17 Earthwork; Site 1 LS 1 $1,250.00 $1,250.00 $2,000.00 $2,000.00 $2,500.00 $2,500.00
18 Earthwork; Site 2 LS 1 $1,250.00 $1,250.00 $2,000.00 $2,000.00 $2,500.00 $2,500.00
19 Final Site Seeding AC 0.1 $7,500.00 $750.00 $12,000.00 $1,200.00 $10,000.00 $1,000.00
20 Temporary Site Stabilization SY 225 $2.50 $562.50 $50.00 $11,250.00 $5.00 $1,125.00
21 Duel Cleanout EA 2 $0.00 $0.00 $850.00 $1,700.00 $450.00 $900.00
22 04"dia. Schedule 40, Lateral LF 40 $0.00 $0.00 $15.00 $600.00 $65.00 $2,600.00
23 Extra Excavation& Backfill for Sewer CY 4 $0.00 $0.00 $1,000.00 $4,000.00 $400.00 . $1,600.00
Lateral Work
TOTAL BASE BID $97,900.09 $129,070.00 $142,567.37
8.8% 43.4% 58.4%
%OVER/UNDER ENGINEER'S EST. .
ERROR .