HomeMy Public PortalAbout1992_11_10_R222The Town of
Lfesburg,
virginia
RESOLUTION NO. 92-222
A RESOLUTION:
PRESENTED November 10, 1992
ADOPTED November 10, 1992
APPROVING CONTRACT AMENDMENT NO. 3 WITH CH2M I-IILL
SOUTHEAST, INC., FOR SERVICES DURING CONSTRUCTION OF THE
WATER POLLUTION CONTROL FACILITY UPGRADE/EXPANSION
WHEREAS, the town is currently under contract with CH2M Hill Southeast, Inc., for design and
construction engineering services relating to the upgrade and expansion of the Water Pollution Control
Facility to a capacity of 4.85 MGD; and
WHEREAS, CH2M Hill recently completed final design services and preparation of construction
documents; and
WHEREAS, a request for prequalification of bidders was issued November 2, 1992; and
WHEREAS, amendment of the September 12, 1989 contract with CH2M Hill is necessary in
order to proceed with construction phase services; and
WHEREAS, CH2M Hill has submitted a contract amendment proposal on a cost plus fixed fee
basis, detailing services to be provided by CH2M Hill during construction at an estimated cost of
$1,775,859.00; and
WHEREAS, the proposed engineering services cost is within programed costs for the project:
THEREFORE, RESOLVED by the Council of the Town of Leesburg in Virginia as follows:
The town manager is hereby authorized and directed to execute Contract Amendment No. 3 to
the September 12, 1989 engineering services agreement with CH2M Hill Southeast, Inc., in a form
approved by the town attorney, in the amount not to exceed $1,775,859.00 based on a nine hundred (900)
day contract period for the Water Pollution Control Facility upgrade and expansion.
PASSED this 10th day of November, 1992.
· Clem, Mayor
Town of Leesburg
ATTEST:
C~lerk of Couhcil 0