HomeMy Public PortalAboutORD15532 BILL NO. 2016-9
SPONSORED BY COUNCILMAN Henry
ORDINANCE NO. 15-5 ,;Z
AN ORDINANCE OF THE CITY OF JEFFERSON, MISSOURI, AUTHORIZING THE MAYOR
AND CITY CLERK TO EXECUTE AN AGREEMENT WITH FERCON CONSTRUCTION CO. IN
THE AMOUNT OF $210,772.00 FOR THE JEFFERSON CITY WAYFINDING PROJECT.
BE IT ENACTED BY THE COUNCIL OF THE CITY OF JEFFERSON, MISSOURI, AS
FOLLOWS:
WHEREAS, Fercon Construction Co. has become the apparent lowest and best bidder on the
Jefferson City Wayfinding project.
NOW, THEREFORE, BE IT ENACTED BY THE COUNCIL OF THE CITY OF JEFFERSON,
MISSOURI, AS FOLLOWS:
Section 1. The bid of Fercon Construction Co. is declared to be the lowest and best bid
and is hereby accepted.
Section 2. The Mayor and City Clerk are hereby authorized to execute an agreement
with Fercon Construction Co. for the Jefferson City Wayfinding project.
Section 3. The agreement shall be substantially the same in form and content as that
agreement attached hereto as Exhibit A.
Section 4. This Ordinance shall be in full force and effect from and after the date of its
passage and approval.
Passed: ,rte p Y O/4 Approved: 914/14-61 2v 6
dijitAAL .viii,u.- (v-z..ar„ -
Presiding Officer Mayor Carrie TerginT�
ATTEST:--- -- -' - ` - APPROVED AS TO FORM:
19 ::::7:1---"-- :-\-- *:
/LAW' : ‘-'- - , /,/i-_-_ r tci., € .ift.
-ity;Cle k. ,, ---1:- `- city Counselor
i
_' _ -
FINANCE DEPARTMENT
PURCHASING DIVISION
SUBJECT: Bid 2852— Project 32137—Jefferson City Wayfinding
Public Works, Engineering —Opened April 26, 2016
RECOMMENDATION:
Staff recommends award of the bid to the lowest and best bid meeting specifications as submitted
by Fercon Construction of Jefferson City, Missouri in the amount of$210,772.00.
BIDS RECEIVED:
Fercon Construction, Jefferson City, MO $210,772.00
Takeform, Medina, NY $231,428.00
Collins & Hemann, Inc., St. Louis, MO $274,382.04
Architectural Graphics, Inc., Virginia Beach, VA $297,689.00
The bid was advertised in News Tribune, posted on the city web site, and sent to seven plan
houses. Two additional firms purchased plans but did not respond.
FISCAL NOTE:
10-990-577054 44-990-577054
Wayfinding (General Fund) Wayfinding (Sales Tax F)
2015-16 Budget 235,955.31 2015-16 Budget $16,846.26
Expenses 31,865.98 Expenses -0-
Encumbered 10,034.36 Encumbered -0-
Bid 2852 194.054.97 Bid 2852 16.717.03
Balance -0- Balance $ 129.23
PAST PERFORMANCE:
Fercon Construction has completed projects in the past as specified and bid.
ATTACHMENTS - SUPPORTING DOCUMENTATION
/ i
Signature
qu'UlGe- �� ±'. '
, . �/7� -nr- r (.?. \-�--
Purch inPA ent Director of Public c W orks
4.1.oil ,F =th t••4
..,,e,.. „,,,,,L,,,,,,,„,t, 2
a - E
Department of Public Works Memorandum
320 E. McCarty Street •Jefferson City, Missouri 65101 • P 573-634-6410 • F 573-634-6562 • www.ieffcitvmo.orq
Date: May 10, 2016
To: Terry Stephenson, Purchasing Director, Finance
From: David Bange, City Engineer vp-6
Subject: Jefferson City Wayfinding
Project No. 32137
Bid No. 2852
Public Works has completed a review of the bids opened at 1:30 P.M. on April 26, 2016 for the
above noted project. As part of the review all the bids were tabulated to check for math errors
and to compare unit price quotes of the various contractors. Attached to this memo is the
tabulation of the Four(4) bids that were received for the project, as well as a listing of the
registered plan holders.
Based on our review, we recommend acceptance of the bid from the low bidder Fercon
Construction, 2014 Clara Drive, Jefferson City, MO 65101. The total amount of the contract will
be $210,772.00.
The project will be expensed as follows:
Fercon Construction ($210,772.00):
Account Number: Amount Available: Required: Remaining:
10-990-577054 $194,054.97 $194,054.97 $0.00
44-990-577054 $16,846.26 $16,717.03 $129.23
If you need any other information please feel free to contact me at extension 6433.
DB:db
Attachments: Bid Tabulation Sheet, Plan Holders List
cc: Project file
Writer's file
v
Page 1 CITY OF JEFFERSON
Date:4/26/16 BID TABULATION
Bid No.2852 JEFFERSON CITY WAYFINDING
STATE PROJECT NO.TAP-9901(501)
PROJECT NO.32137
ENGINEERS ESTIMATE Fergon Construction Takeform Collins and Hermann
APPROX. UNIT UNIT UNIT UNIT
ITEM NO. DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
1 Mobilization LS 1 $10,000.00 $10,000.00 $50,000.00 $50,000.00 $17,460.00 $17,460.00 $34,474.94 $34,474:94
2 Site Preparation and Restoration(Concrete) EA 16 $1,000.00 $16,000.00 $600.00 $9,600.00 $679.00 $10,864.00 $1,824.71 $29,195.36
3 Site Preparation and Restoration(Exposed EA 10 $1,500.00 $15,000.00 $900.00 $9,000.00 $1,292.00 $12,920.00 $1,875.85 $18,758.50
Aggregate Concrete)
4 Site Preparation and Restoration(Turf) EA 27 $250.00 $6,750.00 $125.00 $3,375.00 $535.00 $14,445.00 $395.41 $10,676.07
5 Major Boulevard Vehicular Directional Sign EA 1 $5,500.00 $5,500.00 $4,678.00 $4,678.00 $6,447.00 $6,447.00 $4,280.52 $4,280.52
6 District Vehicular Directional Sign EA 11 $2,800.00 $30,800.00 $1,848.00 $20,328.00 $2,697.00 $29,667.00 $2,154.89 $23,703.79
7 Street Parking Directional Sign EA 12 $900.00 $10,800.00 $388.00 $4,656.00 $912.00 $10,944.00 $582.82 $6,993.84
8 Pedestrian Directional Sign EA 6 $2,000.00 $12,000.00 $612.00 $3,672.00 $2,033.00 $12,198.00 $1,403.19 $8,419.14
9 Information IGosk/Directory Cabinet EA 2 $1,700.00 $3,400.00 $3,920.00 $7,840.00 $7,688.00 $15,376.00 $9,730.83 $19,461.66
10 Area Map Sign(Small) EA 6 $800.00 $4,800.00 $816.00 $4,896.00 $525.00 $3,150.00 $1,628.72 $9,772.32
11 Area Map Insert(Insert for existing sign frame) EA 1 $500.00 $500.00 $321.00 $321.00 $215.00 $215.00 $1,553.70 $1,553.70
12 Bikeway Directional Sign EA 16 $800.00 $12,800.00 $398.00 $6,368.00 $366.00 $5,856.00 $523.98 $8,383.68
13 Bikeway ArrowSign(nodestinations) EA 3 $700.00 $2,100.00 $382.00 $1,146.00 $292.00 $876.00 $387.18 $1,161.54
14 Subdistrict ID Sign EA 1 $900.00 $900.00 $1,010.00 $1,010.00 $1,238.00 $1,238.00 $1,031.15 $1,031.15
15 Existing Pole Mount Installations(or Additional EA 0 $100.00 $0.00 $816.00 $0.00 $2,132.00 $0.00
New Sign on Other New Post)
16 Decorative Post(Large) EA 1 $2,000.00 $2,000.00 $1,582.00 $1,582.00 $1,722.00 $1,722.00 $1,528.10 $1,528.10
17 Decorative Post(Small) EA 13 $1,500.00 $19,500.00 $1,338.00 $17,394.00 $1,418.00 $18,434.00 $1,458.97 $18,966.61
18 Structural Post(W6x9) EA 2 $1,000.00 $2,000.00 $1,853.00 $3,706.00 $1,525.00 $3,050.00 $1,535.46 $3,070.92
19 Pipe Post(3") EA 2 $900.00 $1,800.00 $960.00 $1,920.00 $1,114.00 $2,228.00 $743.40 $1,486.80
20 Pipe Post(3")with System G Coating EA 3 $1,200.00 $3,600.00 $985.00 $2,955.00 $1,392.00 $4,176.00 $1,015.54 $3,046.62
21 Pipe Post(4") EA 5 $1,250.00 $6,250.00 $1,117.00 $5,585.00 $1,429.00 $7,145.00 $900.80 $4,504.00
22 Pipe Post(4")with System G Coating EA 5 $1,600.00 $8,000.00 $1,087.00 $5,435.00 $1,786.00 $8,930.00 $1,215.60 $6,078.00
23 Perforated Square Steel Tube Post EA 19 $500.00 $9,500.00 $199.00 $3,781.00 $147.00 $2,793.00 $484.50 $9,205.50
24 Perforated Square Steel Tube Post with System EA 6 $700.00 $4,200.00 $204.00 $1,224.00 $214.00 $1,284.00 $698.90 $4,193.40
G Coating
25 Concrete Footing for Decorative Post EA 14 $600.00 $8,400.00 $700.00 $9,800.00 $839.00 $11,746.00 $880.48 $12,326.72
26 Concrete Footing for Structural Post EA 2 $300.00 $600.00 $3,000.00 $6,000.00 $1,959.00 $3,918.00 $954.03 $1,908.06
27 Concrete Footing for Pipe Post EA 15 $300.00 $4,500.00 $1,000.00 $15,000.00 $839.00 $12,585.00 $954.03 $14,310.45
28 Concrete Footing for PSST Post EA 19 $200.00 $3,800.00 $500.00 $9,500.00 $619.00 $11,761.00 $836.35 $15,890.65
TOTAL BASE BID $205,500.00 $210,772.00 $231,428.00 $274,382.04
%OVERIUNDER ENGINEER'S EST. 2.6% 12.6% 33.5%1
Page 2 CITY OF JEFFERSON
Date:4/26116 BID TABULATION
Bid No.2852 JEFFERSON CITY WAYFINDING
STATE PROJECT NO.TAP-9901(501)
PROJECT NO.32137
AGI Signs
APPROX UNIT UNIT UNIT UNIT
ITEM NO. DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
1 Mobilization LS 1 $4,712.00 $4,712.00
2 Site Preparation and Restoration(Concrete) EA 16 $1,262.00 $20,192.00
3 Site Preparation and Restoration(Exposed EA 10 $1,737.00 $17,370.00
Aggregate Concrete)
4 Site Preparation and Restoration(Turf) EA 27 $112.00 $3,024.00
5 Major Boulevard Vehicular Directional Sign EA 1 $3,417.00 $3,417.00
6 District Vehicular Directional Sign EA 11 $1,612.00 $17,732.00
7 Street Parking Directional Sign EA 12 $436.00 $5,232.00
8 Pedestrian Directional Sign EA 6 $981.00 $5,886.00
9 Information Idosk/Directory Cabinet EA 2 $2,968.00 $5,936.00
10 Area Map Sign(Small) EA 6 $837.00 $5,022.00
11 Area Map Insert(Insert for existing sign frame) EA 1 $799.00 $799.00
12 Bikeway Directional Sign EA 16 $404.00 $6,464.00
13 Bikeway Arrow Sign(no destinations) EA 3 $351.00 $1,053.00
14 Subdistrict ID Sign EA 1 $1,377.00 $1,377.00
15 Existing Pole Mount Installations(or Additional EA 0 $0.00 $0.00
New Sign on Other New Post)
16 Decorative Post(Large) EA 1 $3,239.00 $3,239.00
17 Decorative Post(Small) EA 13 $2,730.00 $35,490.00
18 Structural Post(W6x9) EA 2 $2,495.00 $4,990.00
19 Pipe Post(3") EA 2 $2,603.00 $5,206.00
20 Pipe Post(3")with System G Coating EA 3 $2,643.00 $7,929.00
21 Pipe Post(4") EA 5 $2,906.00 $14,530.00
22 Pipe Post(4")with System G Coating EA 5 $2,952.00 $14,760.00
23 Perforated Square Steel Tube Post EA 19 $974.00 $18,506.00
24 Perforated Square Steel Tube Post with System EA 6 $988.00 $5,928.00
G Coating
25 Concrete Footing for Decorative Post EA 14 $2,065.00 $28,910.00
26 Concrete Footing for Structural Post EA 2 $1,927.00 $3,854.00
27 Concrete Footing for Pipe Post EA 15 $2,065.00 $30,975.00
28 Concrete Footing for PSST Post EA 19 $1,324.00 $25,156.00
TOTAL BASE BID $297,689.00
%OVER/UNDER ENGINEER'S EST. 44.9%