ESTABLISHING THE MIDDLE TUSCARORA CREEK SEWER PROJECT IN THE
CURRENT FIVE-YEAR CIP AND AMENDING THE FY 94 AND FY 95 BUDGETS
AND FY 95-99 CIP
WHEREAS, the 1993 Amendment to the Sewer System Master Plan deleted the East Leesburg
Sewer System Project (scheduled for construction in FY 95) through creation of the Cattail Branch Sewer
Project; and
WHEREAS, the East Leesburg Sewer Project included a gravity sanitary sewer outfall through
the Middle Tuscarora Creek watershed, necessary for development within this watershed; and
WHEREAS, the Middle Tuscarora Creek Sewer is included in the FY 95-99 Capital Improvement
Program (CIP) for construction in FY 96; and
WHEREAS, Balfour Holdings, Inc., the contract owner of the Governor's Square property, located
in the Middle Tuscarora Creek watershed, has requested town funding of construction for the Middle
Tuscarora Sewer in FY 95, in consideration of their payment of appropriate pro-rata fees prior to
construction of the project; and
WHEREAS, this request requires amendment of the current CIP and budget for appropriation
of design funds and amendment of the FY 95 Budget and CIP for construction funding;
THEREFORE RESOLVED by the Council of the Town of Leesburg in Virginia as follows:
SECTION I. The FY 94-98 Capital Improvement Program is hereby amended to establish the
Middle Tuscarora Creek Sewer project for design in FY 94 and construction in FY 95 at an estimated cost
of $15,000 and $810,000, respectively.
SECTION II. The FY 94 Utility Fund budget is hereby amended to include an appropriation in
the amount of $15,000.00 from the unappropriated Utility Fund balance to account #306.3140.700.741,
Middle Tuscarora Sewer project.
-2-
A RESOLUTION: ESTABLISHING THE MIDDLE TUSCARORA CREEK SEWER PROJECT IN THE
CURRENT FIVE-YEAR CIP AND AMENDING THE FY 94 AND FY 95 BUDGETS
SECTION III. The FY 95-99 Capital Improvement Program is hereby amended to include the
Middle Tuscarora Sewer project for construction in FY 95 at an estimated cost of $810,000.00.
SECTION IV. The FY 95 Utility Fund budget is hereby amended to include an appropriation
in the amount of $810,000.00 to account 306.3140.700.741 for construction of the Middle Tuscarora Sewer
project.
SECTION V. Construction of this project in FY 95 is conditioned on the prepayment of pro-rata
fees by Balfour Holdings, Inc., contract owner of the Governor's Square property. The pro-rata fees to
be prepaid by Balfour Holdings, Inc., are estimated at $315.00 per townhouse unit, for a total cost of
$116,550.00, based on construction of 370 townhouse units. These fees are to be paid to the Town of
Leesburg prior to award of the construction contract and are subject to change depending on the
construction contract cost.
PASSED this 26th day of April , 1994.
ATTEST:
James Clem, Mayor
Town of Leesburg
Clerk of Council