HomeMy Public PortalAbout1996_04_09_R069The Town of Leesburg, .rg ma RESOLUTION NO. A RESOLUTION: PRESENTED April 9, 1996 96-69 ADOPTED April 9, ].996 AUTHORIZING THE EXECUTION OF A CHANGE ORDER FOR EXCAVATION OF NON-RIPPABLE ROCK ON ROUTE 15 BYPASS WIDENING, PHASE 2 PROJECT AND PROVIDING FUNDING FOR COMPLETION OF PROJECT WHEREAS, in July 1995, the Town of Leesburg entered into a contract in the amount of $1,386,500 with Shirley Contracting Corporation for construction of the Route 15 Bypass Widening, Phase 2 project; and WHEREAS, an appropriation was made in the amount of $1,38.6,500 to fund the project without an allowance tbr contingencies; and WHEREAS, plans and specifications and a soil profile for the project were prepared by the engineering firm of Bengston, DeBell & Elkin, Ltd.; and WHEREAS, based on the Soil Profile prepared, the town was provided with an estimated quantity of rock excavation of 529 cubic yards; and WHEREAS, the contractor's bid provided for a unit price of $100 per cubic yard for the excavation of non-rippable rock, if encountered; and WHEREAS, the quantity of rock encountered and removed by the contractor, and verified by the engineer was 4,131 cubic yards; and WHEREAS, due to the properties of the rock when blasted, it was necessary to direct the removal of an additional two feet of shattered and displaced rock to achieve a regular and stable subgrade on which to construct the pavement section; and WHEREAS, the additional quantity of rock removed, and verified by Bengston, DeBell & Elkin, Ltd., was 2,559 cubic yards; and WHEREAS, by negotiating with the contractor, staffwas able to reduce the cost of the additional quantity of rock removed to $40.25 per cubic yard; and RESOLUTION: -2- AUTHORIZING THE EXECUTION OF A CHANGE ODER FOR EXCAVATION OF NON-RIPPABLE ROCK ON ROUTE 15 BYPASS WIDENING, PHASE 2 PROJECT AND PROVIDING FUNDING FOR COMPLETION OF PROJECT WHEREAS, the total cost of excavation of non-rippable rock'is $516,099; and WHEREAS, the amount of this change order is in excess of 25% of the original contract amount and exceeds the amount which staff is authorized to approve, and exceeds the appropriation made to fund the project; and WHEREAS, the cost of additional work not yet completed but required to complete the project, is estimated not to exceed $100,000; and WHEREAS, additional funds for the project are available in the amount of $329,015 from available gas tax funds and in the amount of $359,374 from available proffer funds. THEREFORE, RESOLVED by the Council of the Town of Leesburg in Virginia as follows: SECTION I. An appropriation is made in the amount of $329,015 from Loudoun County gas tax funds to Budget Account 902-9207-700-725. SECTION II. An appropriation is made in the amount of $359,374 from transportation proffer funds to Budget Account 902-9207-700-725. SECTION III. The Town Manager is authorized to sign on behalf of the town Contract Change Order No. 2 for excavation of non-rippable rock in the amount of $516,099.00. SECTION IV. The Town Manager is directed to return any unused funds to the transportation proffer account after final payment is made to the contractor. PASSED this 9th day of Apr±l AT'ES.T: Clerk of Council , 1996. o meS E. Clem, Mayor wn of Leesburg R:lSchgord.res