HomeMy Public PortalAbout1997_07_22_R188The Town of
Leesburg,
rgtnta
RESOLUTION NO.
A RESOLUTION:
PRESENTED July 22, 1997
97-188 ADOPTED July 22, 1997
AUTHORIZING REIMBURSEMENT FOR SEWER LINE CONSTRUCTION
MIDDLE TUSCARORA CREEK
ATTEST:
Clerk of Council
ljs:FR&O:R106
lem, Mayor
Leesburg
WHEREAS, development of Sycamore Hill by Balfour Holding, Incorporated resulted in deferral
of a portion of the Middle Tuscarora Creek sewer system improvements constructed by the town; and
WHEREAS, Balfour Holding, Inc. designed and constructed the remaining portion of the Middle
Tuscarora Creek Sewer as part of their development under a reimbursement agreement with the town; and
WHEREAS, the town's share of the cost for construction of the sewer by Balfour Holding Inc.,
including manholes and rock excavation has been determined to be reimbursable in the amount of
$119,621.87;
THEREFORE, RESOLVED by the Council of the Town of Leesburg in Virginia as follows:
SECTION I The town manager is hereby authorized and directed to reimburse Balfour
Holding, Incorporated in the amount of $119,621.87 for construction of the Middle Tuscarora Creek
sewer line improvement within their development.
SECTION II An appropriation to account (306)3140.700.741, Middle Tuscarora Creek Sewer
Improvement is hereby made from the unappropriated Utility Fund balance in the amount of $120,000.00.
PASSED this 22nd day of ,luly ,1997.