APPROVING A DESIGN CHANGE ORDER FOR FORT EVANS
ROAD CIP IN EXCESS OF 25% OF THE ORIGINAL CONTRACT
AMOUNT.
WHEREAS,
$94,904 to provide the civil engineering
improvements on Fort Evans Road; and
in July 2000, the town contracted with Michael Baker Engineering for
design of a 44' wide road with storm drainage
WHEREAS, a scoping meeting was held in December 2004 with the Town Manager and
the Planning, Urban Forestry, Engineering, Utilities, and Capital Projects Management
Departments to revisit the 44' wide pavement design; and
WHEREAS, the decision was made to revise the design to a 34' wide pavement with
parking on one side to better suit the character of both the residential and commercial
components along the road; and
WHEREAS, the decision was also made to increase the pipe size of the storm drainage
system to accommodate the stormwater management requirements for the undeveloped
commercial property on the east side of the road. The increased pipe size will be paid for through
the creation of a pro-rata share district that will allow developers to pay their share of the cost of
the storm sewer upgrade in lieu of constructing on-site stormwater management facilities, if so
desired; and
A RESOLUTION:
-2-
APPROVING A DESIGN CHANGE ORDER FOR FORT EVANS
ROAD CIP IN EXCESS OF 25% OF THE ORIGINAL CONTRACT
AMOUNT
WHEREAS, the Capital Improvement Project (CIP) Policies and Procedures Manual
requires that Town Council approve change orders if the cumulative total of the change orders
exceeds 25% of the original contract amount; and
WHEREAS, Michael Baker Engineering's change order #4 is in the amount of $62,210
for the redesign of Fort Evans Road and the storm drainage system, and that amount is greater
that 25% of the original contract amount of $94,904; and
WHEREAS, this change order increases the total design contract with Michael Baker
Engineering from the current contract amount of $132,558 (including all currently executed
change orders) to $194,768; and
WHEREAS, funds in the amount of $1,255,000 are appropriated towards this project's
design; and
WHEREAS, the Director of the Office of Capital Projects Management recommends
approving this change order for the work noted.
THEREFORE, RESOLVED by the Council of the Town of Leesburg in Virginia that the
Town Manager is authorized to execute design change order #4 in the amount of $62,210 to
Michael Baker Engineering for redesign of Fort Evans Road.
PASSED this 22ua day of March 2005.
-3-
A RESOLUTION:
APPROVING A DESIGN CHANGE ORDER FOR FORT EVANS
ROAD CIP IN EXCESS OF 25% OF THE ORIGINAL CONTRACT
AMOUNT
ATTEST:
erk of Council
R05: Fort Evans Rd Change Order