HomeMy Public PortalAbout2006_09_26_r161 The Town of Leesburg, Virginia PRESENTED September 26. 2006 RESOLUTION NO. 2006-161 ADOPTED September 26. 2006 A RESOLUTION: APPROVING DESIGN CHANGE ORDERS NO. 10 AND 11 TO DESIGN SYCOLIN ROAD WIDENING PROJECT PHASE II IN THE TOTAL AMOUNT OF $64,396.65 WHEREAS, the design contract to widen Sycolin Road was awarded to DMJM+Harris, Inc. in the amount of $400,000; and WHEREAS, the Town added safety projects in response to citizen concerns to improve safety at the intersections ofSycolin and Lawson Roads, and also Sycolin Road and Tolbert Lane; and WHEREAS, the Town decided to separate the project into three phases to move improvements forward to deal with areas of major congestion and safety issues; and WHERAS, each change has increased the design cost to accommodate the required changes; and WHEREAS, various change orders have been required on this project totaling $321,500 which results in a total contract amount of $721 ,500; and WHEREAS, the Town has maintained its contractual relationship with DMJM+Harris, Inc. to maintain consistency in the design; and WHEREAS, Change Orders No. 10 and 11 are required to complete the design of this project total $64,396.65; and WHEREAS, the contractual increase by Change Orders No. 10 and 11 cause the contract amount to be exceeded by the greater of25% or $50,000; and -2- A RESOLUTION: APPROVING DESIGN CHANGE ORDERS NO. 10 AND 11 TO DESIGN SYCOLIN ROAD WIDENING PROJECT PHASE II IN THE TOTAL AMOUNT OF $64,396.65 WHERAS, the Virginia Public Procurement Act and the Capital Improvements Policies and Procedures Manual requires that Change Orders that cause the contract to be exceeded by the greater of25% or $50,000 be approved by Town Council; and WHEREAS, the Sycolin Road Widening project has sufficient funds in the budget to cover the associated costs; and WHEREAS, the Director of Capital Projects Management recommends approval ofthese change orders. THEREFORE, RESOLVED by the Council of the Town of Leesburg in Virginia as follows: SECTION I. Change Orders No. 10 and 11 in the amount of 64,396.65 are hereby approved. SECTION II. The Town Manager is authorized to execute Change Orders No. 10 and 11 to the design contract with DMJM+Harris, Inc. for the Sycolin Road Widening Project Phase II in the total amount of$64,396.65. PASSED this 26th day of September 2006. ~\\~ . Um attd, Mayor Town of Lees burg ATTEST: ~,Jd elM erk of CouncIl p:\resolutions\06\SycolinRdWidenChgOrder