RESOLUTION NO. 2007-74
ADOPTED April 24. 2007
A RESOLUTION: AWARDING THE IDA LEE INDOOR TENNIS FACILITY
CONSTRUCTION CONTRACT
WHEREAS, the Ida Lee Indoor Tennis Facility is a funded capital project; and
WHEREAS, in response to a public solicitation for construction bids due April 11, 2007,
the Town received two bids; and
WHEREAS, the bids were evaluated by the Director of the Department of Capital Projects
Management and the Chief Purchasing Officer in accordance with the Town's Purchasing Policy;
and
WHEREAS, Tessa Construction & Tech Company, LLC was determined to be the lowest
responsive and responsible bidder with a base bid of $2,472,692; and
WHEREAS, Capital Construction Corporation was determined to be a non-responsive
bidder; and
WHEREAS, the lowest responsive and responsible bid received exceeded the available
budget; and
WHEREAS, staff negotiated both the scope and unit prices with Tessa Construction in
accordance with the bid documents; and
WHEREAS, the negotiated price will include the construction of the four court indoor
tennis facility and the related site work; and
-2-
A RESOLUTION: A WARDING THE IDA LEE INDOOR TENNIS FACILITY
CONSTRUCTION CONTRACT
WHEREAS, the winterization of the existing pavilion and site lighting will not be
constructed at this time but may be bid separately as smaller projects for better pricing at a later
date; and
WHEREAS, the final negotiated price for this contract is $1,791,340; and
WHEREAS, this is a unit price contract and the estimated quantities multiplied by the unit
price have established the not to exceed contract price; and
WHEREAS, change order procedures are detailed in the bid specifications; and
WHEREAS, sufficient funding is available to award this contract.
THEREFORE, RESOLVED by the Council of the Town of Leesburg in Virginia that the
Town Manager is authorized to execute a contract, in a form approved by the Town Attorney, with
Tessa Construction & Tech Company, LLC, in the amount of$1,791,340 for the construction of