HomeMy Public PortalAboutResolution 2020-43. Approving Partial Payment To Brandt Construction For Work Performed On The Havens Acres Rehabilitation Road ProjectRESOLUTION 2020-43
A RESOLUTION APPROVING PARTIAL PAYMENT TO BRANDT CONSTRUCTION
FOR WORK PERFORMED ON THE HAVENS ACRES ROADWAY REHABILITATION PROJECT
FOR THE CITY OF RIVERDALE, IOWA
WHEREAS, The City of Riverdale, Iowa ("City") is a Municipal Corporation, organized and
operating under the laws of the State of Iowa, and;
WHEREAS, Brandt Construction Company, of Milan, IL, was awarded a contract by the
City of Riverdale to rehabilitate Kensington Street and parts of Wisteria Lane in the
Havens Acres neighborhood for a price not to exceed $223,881.00, and;
WHEREAS, on April 14, 2020, a change order in the amount of $1,450.00 was approved
to allow the contractor to make extensive repairs to a storm water intake gutter
located on Kensington Street, and;
WHEREAS, Brandt Construction has substantially completed this project and is entering
the final stages of inspection with the City's engineering consultant, MSA Professional
Services; and
WHEREAS, Brandt Construction has submitted a payment request (EXHIBIT A) in the
amount of $205,241.56 for work performed, to -date; and
WHEREAS, the City's engineering consultant, MSA Professional Services, recommends
making payment.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF RIVERDALE,
IOWA.
Section 1. The City Council of Riverdale hereby authorizes the payment request.
Passed and approved this 26th day of May 2020.
APPROVED
Michael Baw:en, Mayor
ATTEST
Mary.
Frances Blevins, Clerk
City of Riverdale, Iowa 110 Manor Drive, Riverdale, Iowa 52722 • (563) 355-2511 • www.riverdaleiowa.com
( 4-0l3►T'A
To (Owner): CITY OF RIVERDALE
Contractor's Application For Payment No. 1
Project. HAVENS ACRES ROADWAY REHABILITATION
Owner's Contract No. N/A
Application Period: 3/19/2020-5/22/2020
From (Contractor): BRAND 'f CONSI
Contract: 10876067
Contractor's Project No.
Application Date: May 20, 2020
Notice to Proceed Date: February 18, 2020
MSA PROFESSIONAL SERVICES, INC.
Engineer's Project No.: 10876067
Application for Payment
Change Order Summary
Approved Change Orders
Number
Additions
Deductions
1
$1,450.00
$0.00
TOTALS
NE f CHANGE BY
CHANGE ORDERS
$ I ,450.00
$0.00
$1,450.00
Contractor's Certification
'the undersigned Contractor certifies that: (I) all previous progress payments received
from Owner on account of Work done under the Contract have been applied on account
to discharge Contractor's legitimate obligations incurred in connection with Work
covered by prior Applications for Payment: (2) title of all Work, materials and
equipment incorporated in said Work or otherwise listed in or covered by this
Application for Payment will pass to Owner at time of payment free and clear of all
Liens; security interests and encumbrances (except such as are covered by a Bond
acceptable to Owner indemnifying Owner against any such Liens, security interest or
encumbrances): and (3) all Work covered by this Application for Payment is in
accord nice with the Contract Documents and is not defective.
B
Date
S-Zo — Zo to
1. ORIGINAL CONTRACT PRICE
2. Net change by Change Orders
3. CURRENT CONTRACT PRICE (Line I ± 2)
4. TOTAL COMPLETED AND STORED TO DATE
(Column G on Progress Estimate)
5. RETAINAGE:
a. 5 % x S 167,969.44
b. % x S Stored Material
c. Total Retaivage (Line 5a + Line 5b)
6. AMOUNT ELIGIBLE TO DATE (Line 4 - Line 5c)
7. LESS PREVIOUS PAYMENTS (Line 6 from prior Application)
8. AMOUNT DUE THIS APPLICATION
9. BALANCE TO FINISH, PLUS RETAINAGE
(Column I on Progress Estimate + Line 5 above)
Payment ot:
is recommended by:
Payment of
is approved by:
Approved by:
S205,241.56
(Line 8 or other - attach explanation of other amount)
(ja finer)
S205,241.56
(Line 8 or other - attach explanation of other amount)
(Owner)
Funding Agency (if applicable)
EJCDCNo. C-620 (2007 Edition)
Prepared by the Engineers' Joint Contract Documents Committee and endorsed by the Associated General Contractors of America and the Construction Specifications Institute.
5
Yi
5
S
5
5
S
5
5
'l
S223,881.00
1,450.00
$225,331.00
$216,043.75
$10, 802.19
$10,802.19
$205,241.56
0.00
$205,241.56
$9,287.25
(Date)
(Date)
Page 1 of 2
00 62 76-1
10876067 200519 Pay Application 1
Progress Estimate
A r .
-.--....r.w., wars o a arra.Lartrtrrl IIll. l
For
(contract): Havens Acres Roadway Rehabilitation
Application
Application Number 1
Period: 4/6 2020 - 5/22/2020
Application Date 05/2212020
A
B
C D E
F
G )I
I
Item
Bid
Units
Unit
Price
Bid
Value
Work Completed P
Materials Presently
'Total Completed and Stored to Date
Bid Item
No
Description
Quantity
From Previous
Quantity this
Value this
Stored
$
°A
Balance to Finisn
1
Application
Period
Application
(not in C or E)
(C + E F)
(G / B)
G)
1
2
Traffic Maintenance-SUDAS 8030.104
Traffic Maintenance-TC 419
1
LS
$3,500 00
$3,500.00
1
$3,500.00
$0.00
$3,500.00
100,0%
(B -
$0 00
3
Abandon Sanitary Cleanout
1
LS
$2,000.00
$2,000 00
1
$2,000,00
$0.00
$2,000,00
100 0%
$0.00
4
Sawcut Breakout Line
1
EA
$1,100.00
$1,10000
1
$1,10000
$000
$1,100.00
1000%
$000
602
FT
$5 00
$3,010.00
655
$3,275.00
$0 00
$3,275.00
108, 8%
-$265.00
5
Sawcut Curb Cut
466
FT
$25 00
$1 1,660 00
504
$12,600 00
$0.00
$12,600.00
108, I %
-$940 00
6
7
Sawcut Curb and Gutter
Remove Curb Gutter
8
FT
$11 00
$88 00
0
$0,00
$0.00
$0 00
0 0%
$88.00
8
and
Driveway Pavement Removal
16
Ff
$30.00
$480.00
0
$0.00
$0.00
$0 00
0 0%
$480 00
9
Pavement Rernaval, Milling 75"
286
SY
$40 00
$11,440 00
313
$12,520.00
$0.00
$12,520 00
109 4%
-$1,080.00
10
- 1
Pavement Removal, Milling 2"
5,000
SY
$3 50
$17,500.00
4908
$17,178.00
$0,00
$17,178.00
98.2%
$322 00
II.
-
Grind Butt Joint
196
SY
$15,00
$2,940 00
211
$3,165.00
$0.00
S3,165 00
107.7%
-$225,00
12
Curb and Gutter, Special
165
LF
$10.00
$1,650.00
170
$1,700.00
$0.00
$1,700,00
103 0%
-$50 00
13
PCC Driveway, 6"
16
LF
$1 15,00
$1,840.00
0
$0 00
$0 00
$0 00
0 0%
$1,840 00
14
Furnish Manhole Castings, SW-601
260
SY
$62 00
$16,120.00
255
$15,810.00
$0.00
$15,810.00
98.1%
$310.00
15
Exterior Chimney Seal
8
EA
$1,000.00
$8,000.00
8
$8,000.00
$0.00
$8,000 00
100.0%
$0 00
16
Granular Subbase,
8
EA
$625.00
$5,000.00
0
$0.00
$0,00
$0.00
0 0%
$5,000 00
17
10"
Granular Subbase, 6"
60
TON
$52 00
$3,120 00
66.3
$3,447.60
$0.00
$3,447.60
110,5%
-$327 60
101
TON
$57,00
S5,757.00
91.4
$5,209 80
$0.00
$5,209.80
90 5%
$547 20
18
Class 13 Excavation
23
CY
$35 00
$805 00
23
$805,00
$0 00
$805.00
100 0%
$0 00
19
Class 10 Excavation
100
CY
$35.00
$3,500 00
100
$3,500 00
$0,00
$3,500.00
100 0%
$0.00
20.
Valve Box Adjustment Riser, 1"
1
EA
5400 00
$400 00
5
$2,000.00
$0 00
$2,000 00
500 0%
-$1,600.00
21
22
Valve Box Adjustment Riser, 4"
Water Meter Box,
1
EA
$400 00
$400.00
1
$400 00
$0.00
$400 00
100 0%
$0 00
23.
Modified
Schedule 80
3
EA
$1,500.00
$4,500.00
3
$4,500.00
$0.00
$4,500.00
100 0%
$0 00
24.
PVC, 6"
PVC
206
LF
$41,00
$8,446 00
210
$8,610.00
$0.00
$8,610 00
101.9%
-$164.00
25
Assembly
Connect
3
EA
$1,000.00
$3,000.00
4
$4,000.00
$0 00
$4,000 00
133.3%
-$1,00000
26
Mainline to 6xt'a Structure
Area Intake
3
EA
$530.00
$1,590 00
3
$1,590 00
$0.00
$1,590.00
100 0%
$0 00
27.
with Grate, 2' Dia
1
EA
$1,500 00
$1,500.00
1
$1,500.00
$0 00
$1,500 00
100.0%
$0 00
28
Intake Top Removal
Intake
6
EA
$550 00
$3,300.00
6
$3,300 00
$0 00
$3,300.00
100.0%
$0 00
29
Tops
170
SF
$7000
$11,900.00
170
$11,900.00
$0.00
$11,900 00
100 0%
$0.00
30.
Clans I or Class 11 Backlit]
Asphalt
64
TON
$15 00
$960,00
$0.00
$0.00
$0.00
0.0%
S960.00
31
Overlay Fabric
5,000
SY
$4.00
$20,000.00
4908
$19,632.00
$0.00
$19,632.00
98.2%
$368.00
32
HMA LT Surface, 1/2" PG 58-28S
'Fackcoat
645
TON
92
$59,340.00
621 6
$57,187,20
$0.00
$57,187.20
96.4%
$2,152.80
33
1,150
GAL
$010
$115.00
1141.5
$114.15
5000
$114.15
99.3%
50,85
OMite Topsoil
125
SY
$8 00
$1,00000
$0 00
$000
$0.00
0.0%
$1,000.00
34.
Type I Seed Mixture
140
SY
$3 00
$420.00
$0.00
$0 00
$0.00
0 0%
$420.00
35.
Mobilization
1
LS
$7,500.00
$7,500,00
1
$7,500 00
$0,00
$7,500 00
100 0%
$0.00
I
Items 1-35
$223,881.00
$216,043.75
$216,043 75
$7.837 25
C
Change Order Number 1
1
LS
S 1.450 00
$ ),450 00
0 00
S0 00
$0 00
S0.00
0,0%
$1,45000
$0 00
Total
$225,331.00
S216,043.75
EJCDC Na C-62012007 Fdu:owt - -
$216,043.75
$9,287 25
Prepared by the Engineers' Joint Contract Doeuaaeats Committee and endorsed by the Associated General Contractors ofAmcrica and the Construction Specifications Institute.
Page 2 of2
00 62 76-2
10676067 200519 Pay Application 1 Progress Estimate