Town Council Committee on Public Works
Wednesday, February 19, 2014 at 5:00 PM
Mastrangelo Council Chambers
The Public Works Committee met at 5:00 PM to continue the discussion of Fiscal Year 2015
Proposed Street and Road Improvements. Councilors Cecilia Lenk (Chair), Steve Corbett (Vice -
Chair) and Tony Palomba (Secretary) were present as was Councilor Vincent Piccirilli, Public
Works Superintendent Gerry Mee, and DPW Clerk Mary Healy.
The Committee discussed a memo and revised listed of potential street and road improvements
presented by Mr. Mee (see attached).
Councilor Corbett made the following recommendation which was seconded by Councilor
Palomba and passed 3 -0.
The Committee on Public Works recommends that the Town Council approve the list of street and road
improvements presented by Superintendent Mee (Attachment A) and approve a selected mill and overlay
permanent patch program valued at approximately $300,000.
Councilor Corbett made a motion to adjourn which was seconded by Councilor Palomba and
passed 3 — 0. The meeting adjourned at 6:00 PM.
Minutes Prepared by Councilor Palomba
February 20, 2014
TOWN OF WATERTOWN
DEPARTMENT OF PUBLIC WORKS
124 ORCHARD STREET
WATERTOWN, MASSACHUSETTS 02472
Tel: 617-972-6420
Fax: 617-972-6402
TO: Michael J. Driscoll, Town Manager
Public Works Sub -Committee Members
FROM: Gerald S. Mee, Jr.
DATE: February 20, 2014
RE: 2014 Final Road Program
Attached you will find a copy of the 2014 roadway candidates chosen utilizing the road management
program.
The total cost for this program will be $2,490,106.43 or say $2.5M. There are 12 streets on this list
with various parameters set for each street as well as various techniques used within selected
parameters. The last item on the road spread sheet will be used for Selective Mill and Overlay of
various short sections in the range of 300 linear feet to address adverse affects from winter conditions.
This is a process we have used in the past which has worked extremely well and has delayed the need
for other construction techniques.
We all know how valuable this road management program is maintaining the Town's infrastructure and
I would like to thank you in advance for your cooperation and assistance in moving this program
forward.
K:\CAPITAL ACCOUNTS\2014 CIP Memo to sum comm 2-20-14.doc
Capital Impr oveme nt Plan 2014
(Roadway Ca ndidates )
Street Name
From
To
Construction
Method
Road Class
COST ESTIMATE (16%
CONTINGENCY
INCLUDED)
POLICE DETAILS
(11% OF
CONSTRUCTION
TOTAL COST
Fifield Street
Irving Street
Perkins School
Reclamation
LO
$ 131,130 .43
$ 14,424 .35
$ 145,554 .78
Avon Road
Belmont Town Line
Dead End
Reclamation
LO
$ 114,991 .30
$ 12,649 .04
$ 127,640 .35
Alden Road
Belmont T own Line
Dead End
Reclamation
LO
$ 104,904.35
$ 11,539 .48
$ 116,443 .83
Salisbury Road
Maplewood Street
Edgecliffe Road
Mill and Overlay
LO
$ 84,730 .43
$ 9,320 .35
$ 94,050.78
Priest Road
Charles River Road
Ri verside Street
Reclamation
LO
$ 163,408 .70
$ 17,974 .96
$ 181,383.65
Loomis Avenue
Orchard Street
Bradshaw Street
Mill and Overlay
LO
Bradshaw Street
Gertrude Street
Mill and Overlay
Gertrude Street
Downey Street
Mill and Overlay
$ 126,086.96
$ 13,869 .57
$ 139,956 .52
Duff Street
Madison Avenue
Grant Avenue
Mill and Overlay
LO
Grant Avenue
Belmont Street
Mill and Overlay
$ 131,130 .43
$ 14,424 .35
$ 145,554 .78
Barnard Avenue
Columbia Street
Orchard Street
Mill and Overlay
LO
Orchard Street
Bellevue Road
Reclamation
$ 449,878 .26
$ 49,486 .61
$ 499,364.87
Lincoln Street
Mount Auburn Street
WaGnut Street
Reclamation
LO
Spruce Street
Reclamation
LO
$ 284,452.17
$ 31,289.74
$ 315,741 .91
Dexter Avenue
Willow Park
Nicho ls Avenue
Reclamation
CO
Nichols Avenue
Oliver Road
Reclamation
Oliver Road
Mount Auburn Street
Reclamation
$ 265,286 .96
$ 29,181 .57
$ 294,468 .52
Katherine Ro ad
Common Street
Church Street
Reclamation
LO
$ 102,886 .96
$ 11,317 .57
$ 114,204 .52
Cushman Street
Oak Place
Fayette Street
Reclamation
LO
$ 88,765 .22
$ 9,764 .17
$ 98,529 .39
Selective Mill & Overlay
$ 217,212 .53
Total
$ 2,047,652.17 $
225,241.74 $ 2,490,106 .44
SAY $ 2,500,000.00