HomeMy Public PortalAboutN Contents of Stormwater Continued ProjectsREASON PROJECT CONTINUEDMUNICIPALITY COST ESTIMATEPROJECT NAME
CONTINUED STORMWATER PROJECTS
PROJECT CONTINUED DUE TO DESIGN CONCERNS.
ANTICIPATE BOARD INTRODUCTION IN FEBRUARY,
2012.
SUNSET HILLSEAST WATSON AND KATHY CT. STORM
IMPROVEMENT (FY11)
1 $65,000
PROJECT CONTINUED DUE TO EASEMENT
ACQUISTION. ANTICIPATE BOARD INTRODUCTION IN
NOVEMBER, 2011.
KIRKWOODFILLMORE - ELLIOT BANK STABILIZATION
(GCKC-130) (FY08)
2 $235,000
PROJECT CONTINUED DUE TO EASEMENT
ACQUISITION. ANTICIPATE BOARD INTRODUCTION
IN NOVEMBER, 2011.
UNINCORPORATEDHARDWICK COURT CHANNEL IMPROVEMENTS
AND SANITARY SEWER PROTECTION
(MCMB-510) (FY10)
3 $900,000
PROJECT CONTINUED DUE TO DESIGN DELAYS.
ANTICIPATE BOARD INTRODUCTION IN JANUARY,
2012.
FERGUSONMABLE AVE. AND CARSON ROAD STORM SEWER
(FY11)
4 $172,000
PROJECT CONTINUED DUE TO COORDINATION WITH
OTHERS. ANTICIPATE BOARD INTRODUCTION IN
JULY, 2011.
BRENTWOODMARY AVENUE FLOOD MITIGATION (FY11)5 $500,000
PROJECT CONTINUED DUE TO SCOPE CHANGE.
ANTICIPATE BOARD INTRODUCTION IN DECEMBER,
2011.
FERGUSONSHIREFORD LANE STORM IMPROVEMENT (FY11)6 $123,000
PROJECT CONTINUED DUE TO EASEMENT
ACQUISITION. ANTICIPATE BOARD INTRODUCTION
IN DECEMBER, 2011.
HAZELWOODWHITE BIRCH WAY - QUEEN ANN DRIVE STORM
SEWER (FY11)
7 $120,000
$2,115,000TOTAL:
116