STORMWATER CONTINUED PROJECTS - FY13
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
10588 EAST WATSON AND
KATHY CT. STORM
IMPROVEMENT
PROJECT CONTINUED DUE TO DESIGN CONCERNS.
ANTICIPATE BOARD INTRODUCTION IN FEBRUARY, 2013.
$65,000
10229 WINDOM #8721 SEWER
REHABILITATION
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN JULY, 2012.
$254,000
TOTAL: $319,000