WASTEWATER CONTINUED PROJECTS - FY14
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
10407 BAUMGARTNER & BLACK
FOREST SANITARY
REPLACEMENT PHASE II
PROJECT CONTINUED DUE TO COORDINATION WITH ST.
LOUIS COUNTY DEPT. OF HIGHWAYS AND TRAFFIC.
ANTICIPATE BOARD INTRODUCTION IN JUNE, 2014.
$2,500,000
10429 CSO - JEFFERSON
BARRACKS SUBSYSTEM
NO. 72 INTERCEPTOR (I-
122) SEPARATION
PROJECT CONTINUED DUE TO COORDINATION WITH
OTHERS (STATE HISTORIC PRESERVATION OFFICE).
ANTICIPATE BOARD INTRODUCTION IN JULY, 2013.
$2,100,000
10496 GRAVOIS TRUNK
(WHITECLIFF TO RDP)
SANITARY RELIEF PHASE
III (SKME -521)
PROJECT CONTINUED DUE TO COORDINATION WITH
AMEREN AND UNION PACIFIC RAILROAD. ANTICIPATE
BOARD INTRODUCTION IN MAY, 2014.
$1,000,000
10496 GRAVOIS TRUNK
(WHITECLIFF TO RDP)
SANITARY RELIEF PHASE
III (SKME -521)
PROJECT CONTINUED DUE TO COORDINATION WITH
AMEREN AND UNION PACIFIC RAILROAD. ANTICIPATE
BOARD INTRODUCTION IN MAY, 2014.
$8,200,000
11706 INFRASTRUCTURE
REPAIRS
(REHABILITATION) (FY
2013) CONTRACT A
PROJECT CONTINUED DUE TO MWBE UTILIZATION
CONCERNS. ANTICIPATE BOARD INTRODUCTION IN JULY,
2013.
$5,000,000
11845 INFRASTRUCTURE
REPAIRS
(REHABILITATION)
(FY2013) CONTRACT B
PROJECT CONTINUED DUE TO MWBE UTILIZATION
CONCERNS. ANTICIPATE BOARD INTRODUCTION IN JULY,
2013.
$5,000,000
11846 INFRASTRUCTURE
REPAIRS
(REHABILITATION)
(FY2013) CONTRACT C
PROJECT CONTINUED DUE TO MWBE UTILIZATION
CONCERNS. ANTICIPATE BOARD INTRODUCTION IN
AUGUST, 2013.
$5,000,000
11794 LEMAY WWTP ASH
LAGOON ACCESS ROAD
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2013.
$50,000
11132 LEMAY WWTP OUTFALL
002 ELIMINATION
PROJECT CONTINUED DUE TO SCOPE CHANGE.
ANTICIPATE BOARD INTRODUCTION IN JULY, 2013.
$4,500,000
11655 MALINE CREEK CSO 051
TREATMENT FACILITY
PROJECT CONTINUED DUE TO SCOPE CHANGE.
ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2013.
$2,400,000
10722 OLD MILL CREEK SEWER
REHABILITATION PHASE
III - 14TH TO 2ND STREET
PROJECT CONTINUED DUE TO COORDINATION WITH
CORPS OF ENGINEERS. ANTICIPATE BOARD
INTRODUCTION IN JUNE, 2014.
$2,800,000
7 June 2013
WASTEWATER CONTINUED PROJECTS - FY14
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
10199 TOPPING SANITARY
RELIEF (SKME -421)
PROJECT CONTINUED DUE TO EASEMENT
ACQUISITION/CONDEMNATION. ANTICIPATE BOARD
INTRODUCTION IN AUGUST, 2013.
$1,450,000
TOTAL: $40,000,000