HomeMy Public PortalAboutE1 PROGRAM SUMMARY
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
1 of 8
The identification and prioritization of projects to be included in the Capital Improvement
and Replacement Program is a multi-step process, requiring monitoring and updating to ensure
that the highest priority problems within the District are addressed in a timely manner, given
funding limitations. These stages include: project identification, conceptual solution,
preliminary study, final design, and construction.
At each step in the process, the project scope is reevaluated to verify that it continues to
meet regulatory requirements and customers’ needs. The project cost is updated based on
available information, and the project’s priority is assessed with the goal that the highest priority
projects are funded first.
Project cost estimates used in the budget preparation process and shown in the Budget
Supplement are usually based on the preliminary study stage of the process. At this stage there is
typically a minimal amount of detailed information available regarding geotechnical conditions,
utility relocation requirements, easement requirements, and other site-specific issues that have
the potential to significantly affect the project’s construction cost. Preliminary study cost
estimates are intended to be within thirty percent of the design engineer’s final estimates.
Individual projects may vary to a greater degree than the average, due to unanticipated site-
specific conditions that impact the project cost.
New projects are identified on an ongoing basis to ensure that the District is in
compliance with the regulatory requirements of the United States Environmental Protection
Agency and Missouri Department of Natural Resources, to address customer stormwater or
wastewater problems, remedy deficiencies identified through planning studies and hydraulic
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
2 of 8
analysis of the system, and implement required collection system and wastewater treatment plant
maintenance and upgrades.
Upon the initial identification of regulatory issues, localized problems, or system
deficiencies, a conceptual solution is developed, which includes a project scope, cost estimate,
and priority ranking of the project relative to similar projects. This solution and associated cost
estimate are general, based on a single site visit and a “table-top” analysis of the problem. The
project may then be incorporated into the Capital Improvement and Replacement Program in a
specific fiscal year, based on the availability of funds and priority of the project.
Before the year in which funding of the project is anticipated, a preliminary study is
performed. In this study, scope is reevaluated in greater detail to ensure that the conceptual
solution is still viable, given current conditions, regulatory requirements, and updated project
cost estimate and priority ranking. In performing this preliminary study, the District may make
multiple site visits to inspect the problem area and estimate alignment of the sewer or channel to
be constructed. Preliminary survey information may be obtained and a more detailed hydraulic
analysis performed than was done at the conceptual solution level. Preliminary studies are
typically performed by the Engineering Department. However, the District may use engineering
consultants to perform preliminary studies during periods of heavy workload, or for large,
complex projects such as new treatment plants, upgrades to existing treatment plants, tunnel
projects, or major sewer upgrades.
Upon completion of a preliminary study, the project’s priority ranking is reevaluated
relative to other, similar projects. A project may be rescheduled to a later fiscal year within the
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
3 of 8
Capital Improvement and Replacement Program, should its priority ranking be reduced due to
increased project cost estimate or modification of its scope.
The final design of a project is performed by either the District’s Engineering Department
staff or via engineering consultant services. As part of the final design process, topographic and
geotechnical information is collected, utility conflicts are identified, construction plans and
specifications are prepared, and easement and temporary construction license plats are drafted.
In FY 2016, 55 engineering budget items have been or will be procured using the
Watershed Consultant approach, retaining firms for multi-year efforts on a related suite of
projects, in order to increase efficiency, expedite the program and meet Consent Decree
requirements and schedule. Following is a listing of the Watershed Consultant related
engineering projects and associated professional service firms:
Project Number Project Name Page Number Budget
Watershed Program Consultant - 11151 - Construction Management Services - Tank/Treatment/Pump Station Facilities. Consultant: Kennedy Associates / Architects, Inc.
11151 CONSTRUCTION MANAGEMENT SERVICES - TANK/TREATMENT/PUMP STATION FACILITIES 20 4,900,000
Watershed Program Consultant - 11152 - Construction Management Services - Lower and Middle RDP Tunnel Facilities. Consultant: Shannon & Wilson, Inc.
11152 CONSTRUCTION MANAGEMENT SERVICES - LOWER AND MIDDLE RDP TUNNEL FACILITIES 18 1,400,000
Watershed Program Consultant - 11826 - Construction Management Services - Lower Meramec and Deer Creek Tunnels. Consultant: Black & Veatch Corporation
11826 CONSTRUCTION MANAGEMENT SERVICES - LOWER MERAMEC AND DEER CREEK TUNNELS 19 2,600,000
Watershed Program Design Consultant - 11109 - Lower & Middle RDP CSO Controls System Improvements. Consultant: Jacobs Engineering Group, Inc.
12619 HAMBURG AVE TO AL CLAIRE DR TO WEBMORE DR CSO L-181 (I-032) ELIMINATION 47 245,000
11820 LMRDP CSO STORAGE TUNNEL (BROADWAY TO RDP TUBES) 61 8,075,000
11959 LMRDP CSO STORAGE TUNNEL NORTH CONSOLIDATION SEWERS 62 81,000
11958 LMRDP CSO STORAGE TUNNEL SOUTH CONSOLIDATION SEWERS 63 223,000
11816 LMRDP TUNNEL DEWATERING PUMP STATION 64 2,050,000
11109 LOWER & MIDDLE RDP CSO CONTROLS SYSTEM IMPROVEMENTS (WATERSHED CONSULTANT) 65 270,000
11109 LOWER & MIDDLE RDP CSO CONTROLS SYSTEM IMPROVEMENTS (WATERSHED CONSULTANT) 66 527,000
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
4 of 8
11656 MALINE CREEK CSO BP 051 & 052 LOCAL STORAGE FACILITY (CHAIN OF ROCKS DR TO CHURCH DR) 68 211,000
Watershed Program Design Consultant - 11110 - Deer Creek Sanitary System Improvements. Consultant: Parsons Water & Infrastructure, Inc.
10021 DC-02 & DC-03 SANITARY RELIEF (BRENTWOOD BLVD TO CONWAY RD) PHASE I 22 300,000
11110 DEER CREEK SANITARY SYSTEM IMPROVEMENTS (WATERSHED CONSULTANT) 27 150,000
11110 DEER CREEK SANITARY SYSTEM IMPROVEMENTS (WATERSHED CONSULTANT) 28 600,000
11731 DEER CREEK SANITARY TUNNEL (CLAYTON RD TO RDP) 29 500,000
Watershed Program Design Consultant - 11144 - Bissell - Coldwater - Missouri -
Meramec Sanitary System Improvements. Consultant: AMEC Environment & Infrastructure, Inc.
12023 BISSELL - COLDWATER - MISSOURI - MERAMEC PUBLIC I/I REDUCTION (2017) CONTRACT A 4 80,000
12024 BISSELL - COLDWATER - MISSOURI - MERAMEC PUBLIC I/I REDUCTION (2017) CONTRACT B 5 140,000
12025 BISSELL - COLDWATER - MISSOURI - MERAMEC PUBLIC I/I REDUCTION (2017) CONTRACT C 6 60,000
12617 BISSELL - COLDWATER - MISSOURI - MERAMEC PUBLIC I/I REDUCTION (2017) CONTRACT F 7 60,000
11144
BISSELL - COLDWATER - MISSOURI - MERAMEC SANITARY SYSTEM
IMPROVEMENTS (WATERSHED CONSULTANT) 8 3,200,000
11144
BISSELL - COLDWATER - MISSOURI - MERAMEC SANITARY SYSTEM
IMPROVEMENTS (WATERSHED CONSULTANT) 9 800,000
11726 COLDWATER SANITARY RELIEF SECTION B, C & D WET WEATHER STORAGE FACILITY TANK C 14 1,200,000
12125
COLDWATER SOUTHWEST SUBWATERSHED I/I REDUCTION (ST. CHARLES ROCK
RD AND ASHBY RD) 15 3,100,000
12128 CONCORD I/I REDUCTION (TESSON FERRY RD AND E CONCORD RD) 17 280,000
10018 FF-18 VILLA DORADO - LACKLAND - PAGE SANITARY RELIEF (ADIE RD TO VILLA DORADO DR) 32 600,000
12304 HELTA, SAPPINGTON, AND GREGORY COURT I/I REDUCTION (SAPPINGTON RD AND I-270) 48 560,000
12314 KAPPEL (PARTIAL) I/I REDUCTION (EXUMA DR AND GLEN OWEN DR) 50 475,000
12209 SPRINGDALE I/I REDUCTION (ROLLING DR AND SMITHFIELD PL) 76 130,000
Watershed Program Design Consultant - 11145 - Lemay Sanitary System Improvements. Consultant: Burns & McDonnell Engineering Co. Inc.
11993 82ND STREET TO I-170 SANITARY RELIEF (UR-08, UR-09) 1 855,000
12075
AFFTON I/I REDUCTION (HANOVER, HILDESHEIM-WEBER RD, SEIBERT, AND
HAMBURG) 2 565,000
12078 APPLE ORCHARD - SINGERSON - BAYLESS PLACE I/I REDUCTION (LEMAY FERRY RD AND BAYLESS AVE) 3 610,000
11997 DC-09 WEST I/I REDUCTION (S LINDBERGH BLVD AND LADUE RD) 24 320,000
12036 DEER CREEK PUBLIC I/I REDUCTION (2017) CONTRACT A 25 170,000
12037 DEER CREEK PUBLIC I/I REDUCTION (2017) CONTRACT B 26 150,000
11996 FAWN VALLEY, PIONEER PARK, WESTCHESTER I/I REDUCTION (MANCHESTER RD W OF N GEYER RD) 31 530,000
12569 GRAVOIS TRUNK SANITARY STORAGE FACILITY (PARDEE LN AND PARDEE RD) 46 1,500,000
11994 HUNTLEIGH MANOR, OLD WARSON, TIMBERWYCK I/I REDUCTION (S LINDBERGH BLVD SOUTH OF LITZSINGER RD) 49 300,000
12317 KIRKWOOD I/I REDUCTION (BIG BEND BLVD AND S KIRKWOOD RD) 51 780,000
11995
KIRKWOOD MIDDLE SCHOOL, SIMMONS, WILSON, W SARAH I/I REDUCTION
(MANCHESTER RD AND KIRKWOOD RD) 52 560,000
12048 LEMAY PUBLIC I/I REDUCTION (2017) CONTRACT A 53 100,000
12049 LEMAY PUBLIC I/I REDUCTION (2017) CONTRACT B 54 90,000
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
5 of 8
12050 LEMAY PUBLIC I/I REDUCTION (2017) CONTRACT C 55 90,000
12038 LEMAY PUBLIC I/I REDUCTION (2017) CONTRACT D 56 130,000
11145 LEMAY SANITARY SYSTEM IMPROVEMENTS (WATERSHED CONSULTANT) 58 4,750,000
11145 LEMAY SANITARY SYSTEM IMPROVEMENTS (WATERSHED CONSULTANT) 59 760,000
12420 REAVSDALE I/I REDUCTION (MACKENZIE RD AND REAVIS BARRACKS RD) 75 485,000
12240
UNION CREEK I/I REDUCTION (I-55 BETWEEN S LINDBERGH BLVD AND BUCKLEY
RD) 79 565,000
11992 UNIVERSITY CITY SANITARY STORAGE FACILITY (HAFNER CT) 80 3,100,000
12253 VALCOUR AND BURLINGTON RR SANITARY RELIEF AND I/I REDUCTION (VALCOUR RD AND WATSON RD) 81 994,000
11677 WEBSTER GROVES TRUNK E SANITARY REHABILITATION AND I/I REDUCTION PHASE III 82 270,000
Watershed Program Design Consultant - 11153 - RDP Tributaries (Deer Creek) Controls System Improvements. Consultant: HDR Engineering, Inc.
12472 DC-02 & DC-03 SANITARY RELIEF (BRENTWOOD BLVD TO CONWAY RD) PHASE III 23 1,500,000
11746
LOWER MERAMEC RIVER SYSTEM IMPROVEMENTS - BAUMGARTNER TO FENTON
WWTF TUNNEL 67 3,500,000
11153 RDP TRIBUTARIES & UPPER RDP CSO CONTROLS & LOWER MERAMEC SYSTEM IMPROVEMENTS (WATERSHED CONSULTANT) 72 400,000
11153
RDP TRIBUTARIES & UPPER RDP CSO CONTROLS & LOWER MERAMEC SYSTEM
IMPROVEMENTS (WATERSHED CONSULTANT) 73 500,000
12441 RDP TRIBUTARIES (DEER CREEK) CSO TUNNEL 74 600,000
For projects of significant scope and impact, coordination with property owners who will
benefit or who will be affected by the construction of the project is achieved at neighborhood
meetings hosted by the District. For smaller projects, property owners are individually contacted
during the design of the project.
Many projects require that new easements be acquired to enable the project to be
constructed. The time required to acquire these easements is lengthy and may result in delays in
the planned construction schedule. When necessary, the District may condemn for easements in
order to ensure that a project is constructed. Any required condemnation proceedings are
performed in full compliance with state and federal law. Some projects may additionally require
specific permitting from other government agencies, such as the Missouri Department of Natural
Resources, prior to bidding.
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
6 of 8
A project is advertised for public bidding a minimum of 30 days, followed by a formal
bid opening. Bids are evaluated to determine the lowest responsive, responsible bidder.
Appropriation and contract ordinances are submitted to the Board of Trustees for their approval.
Upon ordinance passage, contracts are executed and notices to proceed are issued.
In addition to wastewater and stormwater projects, the District may construct sanitary
sewer sub-district projects at the request of property owners currently served by private systems
or individual septic tank systems. These sub-districts are financed by the benefiting property
owners, using special benefit assessments. The affected property owners initiate the projects by
submitting a petition to the District, which provides design and construction management
assistance. Because of the uncertainty of the viability and/or schedule of sub-district projects,
they are not always listed in the Budget Supplement.
Wastewater projects are funded via revenue from the wastewater user charge paid by
ratepayers. The user charge also supports the sale of revenue bonds to fund the wastewater
program. Generally, Fund 6660, the Sanitary Replacement Fund, is used to pay for capital
wastewater work, while Fund 1101, the General Fund, is used to pay for non-capital wastewater
related work. The allocation of a given project’s costs between these two funds is an accounting
function necessary to facilitate capitalization of District assets. Wastewater projects may also be
funded by various Operation, Maintenance, Construction and Improvement (OMCI) funds,
Construction Funds, Special Funds, or the Improvement Fund.
Stormwater projects may be funded via the General Fund, Construction Funds, Special
Funds, the Improvement Fund, or from various Operation, Maintenance, Construction, and
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
7 of 8
Improvement (OMCI) funds. These OMCI funds are established in certain areas of the District,
are supported by property tax collection, and must be spent only within their specific areas of tax
collection.
The sections included in this Budget Supplement document are:
• Program Summary – summary of budget, and number and type of projects. Includes
general description of the capital program and budgeting process, and a glossary of terms.
• Wastewater Engineering Projects – summary and details on wastewater engineering
consulting services and other professional services necessary to implement the
wastewater program.
• Wastewater Construction Projects – summary and details on wastewater construction
projects and other expenses such as property rights acquisition necessary to implement
the wastewater program.
• Wastewater Continued Projects – summary of wastewater projects continued from previous fiscal years, due to difficulties in easement acquisition, permitting process or
coordination with other agencies, design revisions or status, or other special issues.
• Wastewater Contingency Projects – summary and details on wastewater projects currently budgeted in the next fiscal year, but having the chance to be expedited into the
current fiscal year, if scheduling or budget allow.
• Wastewater Program – annual alphabetical listing of wastewater projects by fund, including the type of service (task) budgeted.
• Stormwater Engineering Projects - summary and details on stormwater engineering
consulting services and other professional services necessary to implement the stormwater program.
• Stormwater Construction Projects - summary and details on stormwater construction
projects and other expenses such as property rights acquisition necessary to implement the stormwater program.
• Stormwater Continued Projects - summary of stormwater projects continued from
previous fiscal years, due to difficulties in easement acquisition, permitting process or coordination with other agencies, design revisions or status, or other special issues.
CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM
SUMMARY
8 of 8
• Stormwater Contingency Projects - summary and details on stormwater projects currently budgeted in the next fiscal year, but having the chance to be expedited into the current
fiscal year, if scheduling or budget allow.
• Stormwater Program - annual alphabetical listing of stormwater projects by fund,
including the type of service (task) budgeted.
• Appendix – list of projects by municipality.
Please note that the detail sheets for each project in this document include approximate
locations and quantities of work to be performed. These maps and quantities are estimates only,
and final location and extent of work may vary depending on final design and/or field conditions
during construction.