WASTEWATER CONTINUED PROJECTS - FY16
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
11788 CAULKS CREEK PUMP
STATION B FORCEMAIN
PROJECT CONTINUED DUE TO COORDINATION WITH
RAILROAD AND CORPS OF ENGINEERS. ANTICIPATE
BOARD INTRODUCTION IN SEPTEMBER, 2015.
$3,100,000
11809 COLDWATER CREEK
WWTF SCREENINGS &
WASHER/COMPACTOR
IMPROVEMENTS
PROJECT CONTINUED DUE TO SCOPE CHANGE.
ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015.
$3,300,000
10440 FORESTWOOD LATERAL
SANITARY RELIEF (SKME-
321)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF FERGUSON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN AUGUST, 2015.
$2,100,000
10716 NEW ENGLAND TOWN
QUARRY PUMP STATION
(P-307) (SKME-544)
IMPROVEMENTS
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015.
$4,200,000
12460 OAKLAND COMBINED
SEWER DETENTION AND
STORAGE (CLAYTON AVE
AND OAKLAND AVE)
PROJECT CONTINUED DUE TO COORDINATION WITH ST.
LOUIS ZOO. ANTICIPATE BOARD INTRODUCTION IN MAY,
2016.
$1,000,000
10390 RIDGEMOOR DRIVE I/I
REDUCTION & STORM
IMPROVEMENTS (SKME-
574)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN NOVEMBER, 2015.
$100,000
10390 RIDGEMOOR DRIVE I/I
REDUCTION & STORM
IMPROVEMENTS (SKME-
574)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN NOVEMBER, 2015.
$1,200,000
10390 RIDGEMOOR DRIVE I/I
REDUCTION & STORM
IMPROVEMENTS (SKME-
574)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN NOVEMBER, 2015.
$800,000
11069 ROCK HILL SANITARY
RELIEF (SKME-618)
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2015.
$1,350,000
10026 UPPER MALINE TRUNK
SANITARY RELIEF PHASE
IV SECTION A
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN JUNE, 2015.
$7,500,000
TOTAL: $24,650,000