HomeMy Public PortalAboutM1 Stormwater Continued 16 22 April 2015 STORMWATER CONTINUED PROJECTS - FY16 PROJECT NUMBER PROJECT NAME REASON PROJECT CONTINUED COST ESTIMATE 10348 CONWAY - CLERBROOK STORM CHANNEL PROJECT CONTINUED DUE TO EASEMENT ACQUISITION AND COORDINATION WITH OTHERS. ANTICIPATE BOARD INTRODUCTION IN JANUARY, 2016. $1,100,000 11216 FIRETHORN DRIVE #1901 STORM IMPROVEMENTS PROJECT CONTINUED DUE TO EASEMENT ACQUISITION AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015. $180,000 10360 FORCEE LANE STORM SEWER PROJECT CONTINUED DUE TO EASEMENT ACQUISITION AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2015. $148,000 11076 LACLEDE STATION - CHAMBERLAIN STORM SEWER PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN OCTOBER, 2015. $230,000 10731 PARK LANE #9568 - #9572 STORM SEWER PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015. $30,000 TOTAL: $1,688,000