STORMWATER CONTINUED PROJECTS - FY16
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
10348 CONWAY - CLERBROOK
STORM CHANNEL
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION
AND COORDINATION WITH OTHERS. ANTICIPATE BOARD
INTRODUCTION IN JANUARY, 2016.
$1,100,000
11216 FIRETHORN DRIVE #1901
STORM IMPROVEMENTS
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION
AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION
IN AUGUST, 2015.
$180,000
10360 FORCEE LANE STORM
SEWER
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION
AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION
IN SEPTEMBER, 2015.
$148,000
11076 LACLEDE STATION -
CHAMBERLAIN STORM
SEWER
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN OCTOBER, 2015.
$230,000
10731 PARK LANE #9568 - #9572
STORM SEWER
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015.
$30,000
TOTAL: $1,688,000