HomeMy Public PortalAboutWastewater Continued Projects 5 February 2015 WASTEWATER CONTINUED PROJECTS - FY16 PROJECT NUMBER PROJECT NAME REASON PROJECT CONTINUED COST ESTIMATE 11788 CAULKS CREEK PUMP STATION B FORCEMAIN PROJECT CONTINUED DUE TO COORDINATION WITH RAILROAD. ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2015. $3,100,000 10440 FORESTWOOD LATERAL SANITARY RELIEF (SKME- 321) PROJECT CONTINUED DUE TO COORDINATION WITH THE CITY OF FERGUSON AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015. $1,600,000 11768 HARLEM - BADEN RELIEF PHASE IV (HEBERT) (DETENTION BASIN) PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2015. $5,460,000 10716 NEW ENGLAND TOWN QUARRY PUMP STATION (P-307) (SKME-544) IMPROVEMENTS PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015. $4,200,000 12460 OAKLAND COMBINED SEWER DETENTION AND STORAGE (CLAYTON AVE AND OAKLAND AVE) PROJECT CONTINUED DUE TO COORDINATION WITH OTHERS. ANTICIPATE BOARD INTRODUCTION IN MAY, 2016. $1,000,000 10390 RIDGEMOOR DRIVE I/I REDUCTION & STORM IMPROVEMENTS (SKME- 574) PROJECT CONTINUED DUE TO COORDINATION WITH THE CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION IN NOVEMBER, 2015. $100,000 10390 RIDGEMOOR DRIVE I/I REDUCTION & STORM IMPROVEMENTS (SKME- 574) PROJECT CONTINUED DUE TO COORDINATION WITH THE CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION IN NOVEMBER, 2015. $1,200,000 10390 RIDGEMOOR DRIVE I/I REDUCTION & STORM IMPROVEMENTS (SKME- 574) PROJECT CONTINUED DUE TO COORDINATION WITH THE CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE BOARD INTRODUCTION IN NOVEMBER, 2015. $800,000 11069 ROCK HILL SANITARY RELIEF (SKME-618) PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2015. $1,350,000 11918 TELEGRAPH ROAD #2928 I/I REDUCTION PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN OCTOBER, 2015. $132,000 10026 UPPER MALINE TRUNK SANITARY RELIEF PHASE IV SECTION A PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN JUNE, 2015. $7,500,000 5 February 2015 WASTEWATER CONTINUED PROJECTS - FY16 PROJECT NUMBER PROJECT NAME REASON PROJECT CONTINUED COST ESTIMATE 11086 WEBSTER ACRES SANITARY SEWER REPLACEMENT PROJECT CONTINUED DUE TO EASEMENT ACQUISITION. ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015. $1,120,000 TOTAL: $27,562,000