WASTEWATER CONTINUED PROJECTS - FY16
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
11788 CAULKS CREEK PUMP
STATION B FORCEMAIN
PROJECT CONTINUED DUE TO COORDINATION WITH
RAILROAD. ANTICIPATE BOARD INTRODUCTION IN
SEPTEMBER, 2015.
$3,100,000
10440 FORESTWOOD LATERAL
SANITARY RELIEF (SKME-
321)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF FERGUSON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN AUGUST, 2015.
$1,600,000
11768 HARLEM - BADEN RELIEF
PHASE IV (HEBERT)
(DETENTION BASIN)
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2015.
$5,460,000
10716 NEW ENGLAND TOWN
QUARRY PUMP STATION
(P-307) (SKME-544)
IMPROVEMENTS
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015.
$4,200,000
12460 OAKLAND COMBINED
SEWER DETENTION AND
STORAGE (CLAYTON AVE
AND OAKLAND AVE)
PROJECT CONTINUED DUE TO COORDINATION WITH
OTHERS. ANTICIPATE BOARD INTRODUCTION IN MAY,
2016.
$1,000,000
10390 RIDGEMOOR DRIVE I/I
REDUCTION & STORM
IMPROVEMENTS (SKME-
574)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN NOVEMBER, 2015.
$100,000
10390 RIDGEMOOR DRIVE I/I
REDUCTION & STORM
IMPROVEMENTS (SKME-
574)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN NOVEMBER, 2015.
$1,200,000
10390 RIDGEMOOR DRIVE I/I
REDUCTION & STORM
IMPROVEMENTS (SKME-
574)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF CLAYTON AND SCOPE CHANGE. ANTICIPATE
BOARD INTRODUCTION IN NOVEMBER, 2015.
$800,000
11069 ROCK HILL SANITARY
RELIEF (SKME-618)
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2015.
$1,350,000
11918 TELEGRAPH ROAD #2928 I/I
REDUCTION
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN OCTOBER, 2015.
$132,000
10026 UPPER MALINE TRUNK
SANITARY RELIEF PHASE
IV SECTION A
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN JUNE, 2015.
$7,500,000
5 February 2015
WASTEWATER CONTINUED PROJECTS - FY16
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
11086 WEBSTER ACRES
SANITARY SEWER
REPLACEMENT
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN AUGUST, 2015.
$1,120,000
TOTAL: $27,562,000