Loading...
HomeMy Public PortalAboutE1 Program Summary Table 22 April 2016 CAPITAL IMPROVEMENT AND REPLACEMENT PROGRAM SUMMARY - FY17 TYPE OF PROJECT NUMBER OF PROJECTS PROJECT COST Wastewater Engineering 81 $67,765,000 Wastewater Construction 82 $265,995,000 Stormwater Engineering 7 $7,730,000 Stormwater Construction 26 $13,283,000 TOTAL:196 $354,773,000 Wastewater Continued 9 $20,520,000 Stormwater Continued 7 $3,187,000 TOTAL:16 $23,707,000 GRAND TOTAL:212 $378,480,000