WASTEWATER CONTINUED PROJECTS - FY17
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
11790 CAULKS CREEK
FORCEMAIN (RIVER
VALLEY RD TO L-52)
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN MAY, 2017.
$6,600,000
11788 CAULKS CREEK PUMP
STATION B FORCEMAIN
PROJECT CONTINUED DUE TO COORDINATION WITH
RAILROAD AND LEVEE DISTRICT. ANTICIPATE BOARD
INTRODUCTION IN JULY, 2016.
$4,000,000
11770 HARLEM - BADEN RELIEF
PHASE IV (HEBERT)
(IMPROVEMENTS FROM
BASIN TO HAMILTON
TRUNK)
PROJECT CONTINUED DUE TO COORDINATION WITH
OTHER PROJECTS. ANTICIPATE BOARD INTRODUCTION IN
MAY, 2017.
$3,900,000
11661 MARTIGNEY I/I
REDUCTION
PROJECT CONTINUED DUE TO COORDINATION WITH
OTHER PROJECTS. ANTICIPATE BOARD INTRODUCTION IN
AUGUST, 2016.
$1,000,000
12616 MISSOURI RIVER WWTF
BERM AND WATER FEED
UPGRADE
PROJECT CONTINUED DUE TO COORDINATION WITH
OTHERS/DELAY IN REGULATORY APPROVAL. ANTICIPATE
BOARD INTRODUCTION IN JULY, 2016.
$1,000,000
12643 MISSOURI RIVER WWTF
SECONDARY TREATMENT
ELECTRICAL /
MECHANICAL
MODIFICATIONS
PROJECT CONTINUED DUE TO SCOPE CHANGE.
ANTICIPATE BOARD INTRODUCTION IN SEPTEMBER, 2016.
$900,000
11701 PUMP STATION
REPLACEMENT PROJECTS
(PHASE I)
PROJECT CONTINUED DUE TO DESIGN REVISIONS.
ANTICIPATE BOARD INTRODUCTION IN DECEMBER, 2016.
$1,700,000
11681 UPPER COLDWATER
SECTION D I/I REDUCTION
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN OCTOBER, 2016.
$100,000
11681 UPPER COLDWATER
SECTION D I/I REDUCTION
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN OCTOBER, 2016.
$1,320,000
TOTAL: $20,520,000