HomeMy Public PortalAboutI2 Wastewater Contingency Projects Detail SheetsFISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
APPLE ORCHARD - SINGERSON - BAYLESS PLACEI/I REDUCTION (LEMAY FERRY RD AND BAYLESSAVE)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
§¨¦55
UNIONKOELN
DAVIS
REAVISBA
R
R
A
CKSWACHTELBAYLESS
ZEISSWILL
H
ALEGREGGGR
ANTCCCMINNESOTAPARDELLAWEBE
R
I O NEVIRGINIATELFORD
FANNIE
ARLEEKAMMERER MILITARYGENTRYFAIN PRIV ATEJOPLINGERMANIARADIOMARCEAU
UNIONPACIFICGR E E N PARK
MOHEGAN
PAULE
LINNORIENT
RIPA
RADIOMKIT
LUNAGRANDGARKLUCIALARK WATERFORMANKAY
OUTER
RAINBOWHOFFME IS T E R
REILLYVA
SEL
SPRINGTIBER
L EMONA
WEMBLEYMOUNT OLIVE
ETTA
PRIMM
PERRINAVENUEHSPOKANEBOUNDARYCATALAN
CAMINOIDAHOHORN
MARCHIJEFFERSONIANLANZENITH GOETZ
LORETTA
SOUTHSHIRE REGINABUCKLEYDANAPILOTCYE
WEISS
MEADOWPHILOHEALY
MANN
FATIMA
COLVIN
BLUE RIDGEEIFFEL
BANISTERGRASSO
ARVIN
CISCOCLEVES
PARK CREST TIFFANYWESTAIRBREUER KASKEWINSTONRUNYONREESNAVAJO
POEPPING
BOXDANAREILLYBUCKLEYWEBER
PR IVAT E
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12078
Wastewater
15
$210,000
Unincorporated
Lemay/RDP
Gravois Creek
Capital
164Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
BRENTMORE PUMP STATION (P-773)REPLACEMENT
Construction
6660 - SanitaryReplacement Fund
PUMP STATION P-773 REQUIRES REPLACEMENT.
REPLACE PUMP STATION P-773.PEPPERM IL L
PEPPERMILLRIDGEPEPPERVIEWPRIVATE
PEPPERFIELDSILVERMILL§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12099
Wastewater
15
$500,000
Wildwood
Missouri
Caulks Creek
Capital
165Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
CAULKS CREEK FORCEMAIN (RIVER VALLEY RDTO L-52)
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
EXISTING FORCEMAIN IS UNDERSIZED AND THIRTY YEARS OLD.
CONSTRUCT 17,000 FEET OF 30-INCH FORCEMAIN AND 1,000 FEET OF36-INCH SANITARY SEWER.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 18. TOTAL BUDGET IS $15,000,000.RIVER VALLEYCENTRAL MIDLANDCRE
V
E
COE
UR
MILLHOG HOLLOWAMIOTW ATE R W O R K S
G L EN COVEWATERWORKSPRIVATE
W HITERIDGECR E S T
R ID G E TRAIL
HIGHVA LLEYWOODSMILLLAKERIVER B E N D
TOREADOR
H IG H L A NDPARKWESTER NMILLC O L IS E U M
PRIVATEOLIVEBLVD
E MO364 HWY
WMO364HWY
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11790
Wastewater
15
$8,400,000
Maryland Heights
Missouri
Caulks Creek
Capital
166Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
CAULKS CREEK FORCEMAIN REHABILITATION
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
FORCEMAIN IS BEING CONVERTED TO A REDUNDANT FORCEMAIN ANDREQUIRES LINING DUE TO AGE AND CONDITION.
REHABILITATE 30,000 FEET OF 20-INCH TO 24-INCH FORCEMAIN FROMPUMP STATION A TO THE 36-INCH FORCEMAIN AT THE MISSOURIAMERICAN WATER PLANT.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 18. TOTAL BUDGET IS $15,000,000.
§¨¦64§¨¦64
THF CEN TR A L M IDLA N DLADUEEDISONW
E
S
T
WILS
O
N
WI L D H O R SEC R E E K RIVER VALLEYAPPALACHIANRHL
NORTH OUTER FORTYHOGHOLLOWPRIVATESWINGLEYRIDGE
WESTMEADE WOODSMILLCHE S T E R FIELDH IG H CROFTGL E N COVE
W
HITE
BAX T E R PETZOLDRAINYLAKENOONING
TREE
LYDIAHILL
BOXFORD
WINEMAW HITE
P
RIV
A
T
E
O LIV E BLVD
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11789
Wastewater
15
$6,000,000
Chesterfield
Missouri
Caulks Creek
Capital
167Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
CEDARCREST PRIVATE I/I REDUCTION (SKME-561)PART 3
Construction, Phase III
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS,OVERCHARGED SEWERS, AND ACTIVATING CONSTRUCTED SSOS.
CONSTRUCT 1,300 FEET OF 12-INCH STORM SEWER, AND REMOVEPRIVATE I/I SOURCES AT 11 PROPERTIES.
PROJECT WAS ORIGINALLY PART OF THE SCOPE OF 11722. OMCI BUDGETFUNDS STORM SEWERS TO BE BUILT AS A PART OF THIS PROJECT.
§¨¦170
PRICELADUEWARSONDIELMAN
CLAYTON
OLD B O N H O M M E
DELMAR
GAYMCKNIGHTWE
N
N
E
K
E
R
LAYENGEL
BARNESCELLAKENTGANNON
G L E N EAG L E S
S T ACY
B A L SON
H
U
NTERB RAEBUR
N BERICKRIO VISTAST A N D REWSGRANADAGRAYBRIDGESTONEYSIDEGROBY
PR IV A TE
BARBYENFIELDHEATHER HILLDROM
A
RALANGTONP IC A R DY BON AIREFO
R
D
Y
CESPOON
A
L
A
NSON
HI
GHDOWNARBORLITTLE
MANSFIELD
LISA
BERKLEYMAYFAIRH A S T IN G S
BON HILLS
FIE L D IN G
TIRRILL FARMSRADFORDWASHINGTON
APPLE TREEBLACK CREEKTERRYDELCRESTRYEBRIAROAKRANDELAYCRIXDALE
VILLA
WHITE ROSELORENZOELKINGTONCHERRI W A T S O N IALYNNELOCUST
PRIVATE
VILLA
PRIVATEMCKNIGHTP
RIV
A
T
E
OLI V E B L V D
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11884
Wastewater
15
$230,000
Various
Lemay/RDP
Deer Creek
Capital
168Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
CEDARCREST PRIVATE I/I REDUCTION (SKME-561)PART 3
Construction, Phase III
5566 - Deer CreekOMCI Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS,OVERCHARGED SEWERS, AND ACTIVATING CONSTRUCTED SSOS.
CONSTRUCT 1,300 FEET OF 12-INCH STORM SEWER, AND REMOVEPRIVATE I/I SOURCES AT 11 PROPERTIES.
PROJECT WAS ORIGINALLY PART OF THE SCOPE OF 11722. OMCI BUDGETFUNDS STORM SEWERS TO BE BUILT AS A PART OF THIS PROJECT.
§¨¦170
PRICELADUEWARSONDIELMAN
CLAYTON
OLD B O N H O M M E
DELMAR
GAYMCKNIGHTWE
N
N
E
K
E
R
LAYENGEL
BARNESCELLAKENTGANNON
G L E N EAG L E S
S T ACY
B A L SON
H
U
NTERB RAEBUR
N BERICKRIO VISTAST A N D REWSGRANADAGRAYBRIDGESTONEYSIDEGROBY
PR IV A TE
BARBYENFIELDHEATHER HILLDROM
A
RALANGTONP IC A R DY BON AIREFO
R
D
Y
CESPOON
A
L
A
NSON
HI
GHDOWNARBORLITTLE
MANSFIELD
LISA
BERKLEYMAYFAIRH A S T IN G S
BON HILLS
FIE L D IN G
TIRRILL FARMSRADFORDWASHINGTON
APPLE TREEBLACK CREEKTERRYDELCRESTRYEBRIAROAKRANDELAYCRIXDALE
VILLA
WHITE ROSELORENZOELKINGTONCHERRI W A T S O N IALYNNELOCUST
PRIVATE
VILLA
PRIVATEMCKNIGHTP
RIV
A
T
E
OLI V E B L V D
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11884
Wastewater
15
$470,000
Various
Lemay/RDP
Deer Creek
Capital
169Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
COLDWATER CREEK WWTF FINAL CLARIFIERSREPLACEMENT
Construction
6660 - SanitaryReplacement Fund
EXISTING FOUR SQUARE FINAL CLARIFIERS ARE 50 YEARS OLD, ANDPAST THEIR USEFUL LIFE.
DEMOLISH EXISTING FOUR SQUARE CLARIFIERS AND CONSTRUCT NEWFOURTH CIRCULAR CLARIFIER. ENLARGE FEED CHANNEL AND PIPINGTO THE EXISTING THREE CIRCULAR CLARIFIERS.
PRIVATE
RICHMOND FORESTROBBINSWAYGLEN ALLEN
PRIVATE
PR IVATE
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12504
Wastewater
15
$5,500,000
Unincorporated
Coldwater
Coldwater Creek
Capital
170Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
CONCORD I/I REDUCTION (TESSON FERRY RD ANDE CONCORD RD)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING OVERCHARGED SEWERS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12023.
§¨¦270
§¨¦270
THEISS
MATTIS
GERALD MUELLERVON TALGETESCORDGATESBURYTHEISSCORDDIERSDORSIETWILIGHTBAPTISTCHURCHLAVINIAGREGORYLINCORDCONCORDSCHOOL
SAKURA
JAMIEJOSSEJAN
CHERYLCONCORDLARKINCONCOR D V IL L A G ER EVEREWINKEL
W ORTHIN GTO N
F I V EOAKSBIMINI
BEHRSUNNY VIEWMARLEYCAROLYNNE ACTONARTHU R
SLEVIN
CHAR WICKMEADOWFIELD
LEONARDKRAMPERS
T
G
E
M
ME
EDGECLIFFE
BRIDLEW O O D
VALLEY
CREST
FAWNWOODD ORCLINWISTERIAJUENGEL
NEELYWOODWORTHCOUWELSROUNDHILL
CONG ER
PRIVATE
CONCORDOA K S
OLDTESSONHUEGEL
SUANISAPPLE GROVEMERITOCONCORDTESSONFERRYRDS LINDBERGH BLVD
SLINDBERGHBLVD
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12128
Wastewater
15
$185,000
St. Louis County
Meramec
Mattese Creek
Capital
171Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
DAMMERT AND BROADWAY SANITARY RELIEF(SKME-551)
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
TWO SSOS AND A PUMP STATION MUST BE ELIMINATED.
CONSTRUCT 10,000 FEET OF 8-INCH TO 24-INCH SANITARY SEWER, ANDREMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS. ELIMINATECONSTRUCTED SSO OUTFALLS BP-515 AND BP-624, AND PUMP STATIONP-327.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 18. TOTAL BUDGET IS $6,825,000. PUBLIC I/IREDUCTION IN PROJECT 11927.
§¨¦55
§¨¦55
WACHTELBAYLESS
ZEISSHOFFMEISTERPARDELLAREED DAVIS
FANNIE
ARLEE MILITARYGENTRYP R IV ATEAVENUE HPAULE
MARCEAU
ORIENT
HURCKGRAND
UNION PACIFICCLYDEERSKINEWEBERMINNESOTAETTA
CATALAN
HORNMOUNT OLIVE
FELTON
NAERTVIRGO MICHIGANDALLASGOETZVEGAS
JOPLINPERRINUNIONLORETTAREGINA LAGRO
KAYSER
WEISS
PLACID MANNCORMAR
VELMARUPRECHTLANDOR
BLUE RIDGEDUMONT
SANT EN
HOLDEN
CLEVES
BOBRING
CATSKILL
WALLER
ESPENSCHIEDIDAHOMAJESTY
POINT
RISCH
CARTWRIGHT
POEPPING
ADELIA
JEFFORDSAVENUE ISUSAN BAUMANNPRIMM
O L D C O U N TY
DAMMERTBARTOLET
ELIAS
FAWN
BAYLESS
DAMMERTVELMA
WALLER
FANNIE
WEISSPAULE
FELTON
HORN
KAYSER
ORIENT
UNIONPACIFICPRIV
A
T
EREGINAWALLER
ETTA
WEISS
LEMAY FERRY RD§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11155
Wastewater
15
$1,825,000
Unincorporated
Lemay/RDP
Martigney Creek
Capital
172Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
DC-02 & DC-03 SANITARY RELIEF (BRENTWOODBLVD TO CONWAY RD) PHASE I
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
BUILDING BACKUPS AND OVERCHARGED TRUNK SEWER.
CONSTRUCT 7,900 FEET OF 6-INCH TO 78-INCH SANITARY SEWER TOALLEVIATE SURCHARGING. FACILITATE FUTURE REMOVAL OF BP-545,BP-170, BP-198, BP-348, BP-349, BP-155, AND BP-591.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FUTURE YEARS. TOTAL BUDGET IS $21,750,000.GLENBELLBRENTWOODELMMADGE
MARYTHORNTON
RUSSELL
MARSHALL
WAYMIRE
FLORENCE
CORNELLUNIONPACIFICPENDLETONPRIVATEBRAZEAU
ATALANTA RUTHLITHIA
M E R R IT T
MANDERLYPOWELL
C R A W F O R D
HILLDALECOLLIERR
O
CKF
OR
D
JOSEPH
MASON
HOLLANDLAWNDELL
ALMENTOR
ALLISONREASNOR
MAGDALEN
WILLIS BOMPARTKIRKHAMBREMERTONC
R
E
V
E
C
O
E
U
R
KEYSTONE
BREMERTONWILLIS
GLENATALANTA
PRIVATE
GLENMARYCOLLIERBOMPARTMANCHESTER RD §¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 10021
Wastewater
15
$4,000,000
Brentwood
Lemay/RDP
Deer Creek
Capital
173Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
DC-02 & DC-03 SANITARY RELIEF (BRENTWOODBLVD TO CONWAY RD) PHASE II
Construction
6660 - SanitaryReplacement Fund
BUILDING BACKUPS AND OVERCHARGED TRUNK SEWER.
CONSTRUCT 5,400 FEET OF 72-INCH SANITARY SEWER TO ALLEVIATESURCHARGING AND TO FACILITATE THE FUTURE REMOVAL OFCONSTRUCTED SSOS.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 19. TOTAL BUDGET IS $33,130,000. OMCI FUNDINGIS FOR PARK LANE STORM SEWER.
§¨¦64 §¨¦170§¨¦64
PINE
MCKNIGHTELMOLD WARSON
LITZSINGER
T R ENTBRENTWOODODAYBELLBISMARK
LAWN
GLENWHITE
EUCLID
SWAN
LITHIADANIELBENNETT
BACON UNION PACIFICHUDSON
KIRKHAMHIGHSCHOOLCLARK
MADGE
ANDREWROANGILBERTEULALIE
CORNELLTUXEDO
WRENWOOD
ST CLAIRMARYEAG E R
SOUTHFORTY
FAIRVI EWMCKINLEYMADISON
NORTH RUSSELL
URBAN
ROCK HILLGODWIN
RENDERERKORTWRIGHTROSE
R
O
C
K
F
ORDPARKRIDGEFLORENCELAY
WILDDEER
YO RKMORITZ
D E S PERESWAYMIRE
ELLSWORTH
ROCKMANLOGC A B I N
PAR KCOPP E R HILL
JOANNA OVERBROOKRIDGELINEMANI
T
OUPRIVA T E
WILD ROSE
WATE RBURYLEONARDF
A
I
R
D
A
L
E OAK BENDLIN DW O RTHHILLGLEN ELM COLLIERBERRYHELENHOCHRARITAN HATTONALLISON
NOLAN ROBINPATTONTHRUSHROCK HILLPRIVATE
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12471
Wastewater
15
$17,000,000
Various
Lemay/RDP
Deer Creek
Capital
174Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
DC-02 & DC-03 SANITARY RELIEF (BRENTWOODBLVD TO CONWAY RD) PHASE II
Construction
5566 - Deer CreekOMCI Fund
BUILDING BACKUPS AND OVERCHARGED TRUNK SEWER.
CONSTRUCT 5,400 FEET OF 72-INCH SANITARY SEWER TO ALLEVIATESURCHARGING AND TO FACILITATE THE FUTURE REMOVAL OFCONSTRUCTED SSOS.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 19. TOTAL BUDGET IS $33,130,000. OMCI FUNDINGIS FOR PARK LANE STORM SEWER.
§¨¦64 §¨¦170§¨¦64
PINE
MCKNIGHTELMOLD WARSON
LITZSINGER
T R ENTBRENTWOODODAYBELLBISMARK
LAWN
GLENWHITE
EUCLID
SWAN
LITHIADANIELBENNETT
BACON UNION PACIFICHUDSON
KIRKHAMHIGHSCHOOLCLARK
MADGE
ANDREWROANGILBERTEULALIE
CORNELLTUXEDO
WRENWOOD
ST CLAIRMARYEAG E R
SOUTHFORTY
FAIRVI EWMCKINLEYMADISON
NORTH RUSSELL
URBAN
ROCK HILLGODWIN
RENDERERKORTWRIGHTROSE
R
O
C
K
F
ORDPARKRIDGEFLORENCELAY
WILDDEER
YO RKMORITZ
D E S PERESWAYMIRE
ELLSWORTH
ROCKMANLOGC A B I N
PAR KCOPP E R HILL
JOANNA OVERBROOKRIDGELINEMANI
T
OUPRIVA T E
WILD ROSE
WATE RBURYLEONARDF
A
I
R
D
A
L
E OAK BENDLIN DW O RTHHILLGLEN ELM COLLIERBERRYHELENHOCHRARITAN HATTONALLISON
NOLAN ROBINPATTONTHRUSHROCK HILLPRIVATE
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12471
Wastewater
15
$30,000
Various
Lemay/RDP
Deer Creek
Capital
175Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
DC-09 WEST I/I REDUCTION (S LINDBERGH BLVDAND LADUE RD)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12036.
§¨¦64§¨¦64
LADUE WARSONSPOEDEGRAESERC LA Y TO NMOSLEY BARNESVOUGANORTH FOR T Y
T E A L W OOD
BEAVER
ST ACY
LOG CABINC LERM O N T STONEYSIDEOAKPARKOLDBONHOMME
RONDELAY
P R IVATECONWAYALDE N
B
R
O
OKTRAIL HEATHER HILLMAGNOLIAS
PRINGWOOD
ARTHUR
P IC A RDY
FO
R
D
Y
CEMOR WOODTUREEN
HI
GHDOWNTUCKERLADUEESTATESWHITEBRIDGE
ANZEIGER
LISA
MAYFAIRA L LE G ROLYLEWOOD
SHERWYNTRILANE
LAWRENCE
M A R Y HILL
CLERBROOK APPLE TREEQUA I L W A Y S
RANDELAYOAK GATE
CAPITOL
CHERRI
COUNTR YVIEW
NOTRE DAMED O G W O O D
L Y N N B R O O K
SUNDOWN
PRIVATEP
RI
VATEPRIVATEPRIVATE
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11997
Wastewater
15
$305,000
Ladue
Lemay/RDP
Deer Creek
Capital
176Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
DEER CREEK SANITARY TUNNEL (CLAYTON RD TORDP)
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING OVERCHARGED SEWERS ANDACTIVATING CONSTRUCTED SSOS.
CONSTRUCT 20,000 FEET OF 19 FOOT DIAMETER STORAGE TUNNEL ANDDIVERSION STRUCTURES.
PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FUTURE YEARS. TOTAL BUDGET IS $216,000,000.PUMP STATION CONSTRUCTED UNDER 12615.
§¨¦44
§¨¦64
§¨¦170
§¨¦170
DALE
M
E
T
R
OLI
N
K
CLAYTON
PINELAY
ELMU N IO NPACIFICFOLKMCKNIGHT
NEWPORT
MARSHALL YALECLARK McCAUSLANDLITZSINGER LACLEDESTATIONIVANHOEBELLEVUEBRENTWOODHANLEYKIRKHAMPERNOD
DAVIS
ETHEL
WHITE
BELLBREDELLBOLANDSUTTONLAWN
OLEATHA
EULALIE
GLENFYLERCLAYTONIA
LEE
ARUNDEL
EUCLID
SWAN
PAR KLITHIA
PACIFICFOREST
ABERDEEN
LOUISDELNORTEPLATEAU
WILL IA MS
ALAMO
MARDEL
MADGE
HANCOCKMCCUTCHEONWISE
ARSENALFLORASALEMB
U
C
K
HICKSWRENWOOD
ST CLAIRMARYGOR
E AUDUBONBRUNO
FAIRVIEW M A NHATTANPRATHERBARTOLDRUSSELL
YEATMANROCK HILLEA G E R
ROSE
FLORENCE MARTINIOXFOR D
GODWI N
C O M M ONWEALTHMOORLANDSY ORKBACON LYLEDESPERESANNA
WAYMIRE SOUTHELLSWORTH
JAMES
SUFFOLKMAPLE
PRIVATE
CIRCLEARLINGTONCOLLINS
GREELEY ECOFFKUHLMAN
ARBOR
HALIFAX
PORTERHORNER
WARNER
B E R R Y RICHERTHATTONSANBONITA
OAKLAND
GLENWISE
UNIONPACIFIC FORESTELM
OXFORD
EAGER PRIVATEMARYWHITE
YORK
M AN C H E S T E R RD
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11731
Wastewater
15
$104,000,000
Various
Lemay/RDP
Deer Creek
Capital
177Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
FAWN VALLEY, PIONEER PARK, WESTCHESTER I/IREDUCTION (MANCHESTER RD W OF N GEYERRD)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS,OVERCHARGED SEWERS, AND ACTIVATING CONSTRUCTED SSOS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12036.GEYERBALLASBOPPRUTHWOODGATESIMMONSOAK VALLEY
TWINPINENANALINDEMANJEWELTALLIELINWOODCLAYCHESTER CLEVELANDDOUGHE R T Y F E RRY
TWIN FAWNS
LINDGATE MEIERKIRKSHIRE
GRUPPKEND
O
NMISSOURIDUNMORR
LILLIAN
CREEKHAVEN
SUN NY FOLGERL
OCKETTBLASELINDEMANN PAMELA
KINSTERNSERAMA
VINETTALAVENDELHARWOODBAMBURY
TIMBER
F E D ERAL
CHRISTINEWILSON
ROCHDALEMANHATTAN
B A YBER RYBROOKCREEK
SCOTTSDALE
MOZARTBORCHERDING
WHIT ECLIFFMISTLETOE
BRIAR RIDGE
LYNKIRK
TIMBERWYCK
HAVERSHAMFAW NRIDGE
PLAZATRAIL C R E S T
A
PP LEWOODPINEGATEDELCHESTERDAWNINGBANSBACHWEDGETON
MONTOUR
MIDDLEVIEW
DES PERESDOMINION
JASMINLIN MANOR
BELVA
IRENE
ST CROIXBALLAS
JEWEL
SUNNY BOPPSIMMONSLYN K IR K
MANCHESTER RD
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11996
Wastewater
15
$205,000
Des Peres
Lemay/RDP
Deer Creek
Capital
178Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
FF-16 SCHUETZ - MEADOWSIDE TO PAGESANITARY RELIEF
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
BUILDING BACKUPS AND OVERCHARGED SEWERS.
CONSTRUCT 8,880 FEET OF 8-INCH TO 42-INCH SANITARY SEWERS.ELIMINATE CONSTRUCTED SSO BP-076.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 18. TOTAL BUDGET IS $8,890,000.
PAGE
ADIE
SCHUETZL A C K L A N D
B
A
L
L
B O RM ANC
E
N
T
R
A
L
MIDLAND
SCHAEFER
W
E
L
DONGRISSOMGRAELERFEE FEED O R S ETTMILLPARK
C H IE F T A I N
VIL L A D O R A D OCHAFFEE
GAND YT I V OLI
SCHULTECONCOURSEDECORAH
MEADOWSIDEPRI V AT E
W E S T L IN E INDUSTRIAL
MONT
A
UKNORFOL K S O U TH E RN
ME DIAGOLDLEAFLIMETREE WESTPORTCENTERARC
C H A N DELLAY
PAGESERVICE
ALTOMS
H
A
LLOW B R O O KCONGRESSIONAL M U E LL E R
L IN F R E DVERNABRO
NCOWOODLAND LACKLAND HILL
PRIVATEPAGE PRIVATEPRIVATEPRIVATEMEDIA§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 10601
Wastewater
15
$3,890,000
Maryland Heights
Missouri
Fee Fee Creek
Capital
179Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
GASLIGHT SQUARE SEWER IMPROVEMENTS
Construction
6660 - SanitaryReplacement Fund
OVERCHARGED COMBINED SEWERS CAUSING WET WEATHERBUILDING BACKUPS.
CONSTRUCT 6,300 FEET OF 8-INCH TO 24-INCH SANITARY SEWER ANDONE PUBLIC WET WEATHER PUMP STATION.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 19. TOTAL BUDGET IS $14,500,000.
OLIVE
SARAHBOYLELINDELL
DELMAR
MCPHERSONWHITTIERWASHINGTON
WESTMINSTER
ENRIGHT
WEST PINE
MARYLAND PENDLETONWHITTIERWESTMINSTER
MCPHERSON
MARYLAND
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11137
Wastewater
15
$7,500,000
St. Louis City
Bissell
Western Mill Creek
Capital
180Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
GLENDALE SECTION D SANITARY RELIEF PHASE V(SKME-624) I/I REDUCTION
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING OVERCHARGED SEWERS.
CONSTRUCT 1,675 FEET OF 12-INCH TO 18-INCH STORM SEWERS ANDREMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS. ELIMINATECONSTRUCTED SSO OUTFALL BP-496 AFTER POST CONSTRUCTIONMONITORING.
OMCI BUDGET FUNDS STORM SEWERS TO BE BUILT AS A PART OF THISPROJECT.
KIRKHAM
GRAYDICKSONSWON
OLD WARSON
GORELOCKWOOD
LEE
ELMESSEX UNIONPACIF IC
JACKSONSAPPINGTONWOOD MAPLEODAYTAYLORBELLBISMARK
BROWNELL
QUAN
FOOTE
EDWINEUCLID
LITHIABENNETT
BACON
GILL
PAR
HUDSON
ANDREWBODLEY JEFFERSONOA KGILBERT CORNELLHILLDEACON
AUSTINM E D I N A MCKINLEYADAMS PARKLANDMADISON
IOLANORTH
LONGVIE
W ROCK HILLMARK
RENDERERPAPINKORTWRIGHTPARKFLANDERSCURRANPA C I FIC
DWYER
WILDDEER
BOGEY
D E S PERESHILLARD ROCKMANCOPP E R H ILL
JOANNARIDGE LINED
E
VONCHELSEA
P RIV A T E
BREMERTONHIGHHAMPT O NMANI
TOUJULIAN
VICTORIA
WARWICK
WATE R BURYMOODYLEONARD
OAKSFOX
BARRONGLENMOOR
HULLF
A
I
R
D
AL
E
WINGFIELD
PARKWOODSMCDONALDHARTGREENVIEWCOLL
E
G
E
ALGONQUIN
CEDAR
B E R R Y
HI
L
L
SI
DEWOODLAWNBELLEVIEW
BEAUFORD
HOCHBERRYWOOD
RARITAN
GASLITE
ALFRED
NOLAN
FUHRMANN
RUSSELLSTURGISELMROCK HILLLOCKWOOD
CHELSEA IOLAALGONQUIN
PAR CEDAR
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12177
Wastewater
15
$2,900,000
Glendale
Lemay/RDP
Deer Creek
Capital
181Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
GLENDALE SECTION D SANITARY RELIEF PHASE V(SKME-624) I/I REDUCTION
Construction
5566 - Deer CreekOMCI Fund
INFLOW AND INFILTRATION CAUSING OVERCHARGED SEWERS.
CONSTRUCT 1,675 FEET OF 12-INCH TO 18-INCH STORM SEWERS ANDREMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS. ELIMINATECONSTRUCTED SSO OUTFALL BP-496 AFTER POST CONSTRUCTIONMONITORING.
OMCI BUDGET FUNDS STORM SEWERS TO BE BUILT AS A PART OF THISPROJECT.
KIRKHAM
GRAYDICKSONSWON
OLD WARSON
GORELOCKWOOD
LEE
ELMESSEX UNIONPACIF IC
JACKSONSAPPINGTONWOOD MAPLEODAYTAYLORBELLBISMARK
BROWNELL
QUAN
FOOTE
EDWINEUCLID
LITHIABENNETT
BACON
GILL
PAR
HUDSON
ANDREWBODLEY JEFFERSONOA KGILBERT CORNELLHILLDEACON
AUSTINM E D I N A MCKINLEYADAMS PARKLANDMADISON
IOLANORTH
LONGVIE
W ROCK HILLMARK
RENDERERPAPINKORTWRIGHTPARKFLANDERSCURRANPA C I FIC
DWYER
WILDDEER
BOGEY
D E S PERESHILLARD ROCKMANCOPP E R H ILL
JOANNARIDGE LINED
E
VONCHELSEA
P RIV A T E
BREMERTONHIGHHAMPT O NMANI
TOUJULIAN
VICTORIA
WARWICK
WATE R BURYMOODYLEONARD
OAKSFOX
BARRONGLENMOOR
HULLF
A
I
R
D
AL
E
WINGFIELD
PARKWOODSMCDONALDHARTGREENVIEWCOLL
E
G
E
ALGONQUIN
CEDAR
B E R R Y
HI
L
L
SI
DEWOODLAWNBELLEVIEW
BEAUFORD
HOCHBERRYWOOD
RARITAN
GASLITE
ALFRED
NOLAN
FUHRMANN
RUSSELLSTURGISELMROCK HILLLOCKWOOD
CHELSEA IOLAALGONQUIN
PAR CEDAR
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12177
Wastewater
15
$610,000
Glendale
Lemay/RDP
Deer Creek
Capital
182Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
HARLEM - BADEN RELIEF PHASE IV (HEBERT)(IMPROVEMENTS FROM BASIN TO HAMILTONTRUNK)
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
STREET FLOODING AND BUILDING BACKUPS DUE TO OVERCHARGEDCOMBINED SEWERS.
CONSTRUCT 5,550 FEET OF 12-INCH TO 108-INCH STORM SEWERS, 540FEET OF SANITARY SEWERS, AND 3,240 FEET OF SEWER LINING IN THECITY OF ST. LOUIS.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 18. TOTAL BUDGET IS $7,800,000.
ST LOUIS CLARATERRY
T E R M IN A LGREER
LABADIE
GOODFELLOWMAFFITT
ROOSEVELT
HERBERT
SE
L
B
E
R
BURDBELTASHLAND
HAMILTONKENNERLY
ELMBANK
ROWANBLACKSTO NEGREER
ASHLAND
TERRY
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11770
Wastewater
15
$3,900,000
St. Louis City
Bissell
Harlem
Capital
183Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
HUNTLEIGH MANOR, OLD WARSON,TIMBERWYCK I/I REDUCTION (S LINDBERGHBLVD SOUTH OF LITZSINGER RD)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS,OVERCHARGED SEWERS, AND ACTIVATING CONSTRUCTED SSOS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12037.
§¨¦64
§¨¦64
GEYERCLAYTON
KIRKHAMWOODLAWNOLDWARSON
LEE
T R ENTRUTHWOODWARSONODAYBROWNELL
BISMARK
TAYLORWILSON
LITZSINGER
WOODGATENORTH F ORTY
DANIELBENNETTS
QUIRES
OAK VALLEY
DICKSONBACON
SOUTHFORTY
ANDREWROANOVE
RHILLS
GILBERTDEACONEVANSSIMMONSBRIDLEHARRISONO A KNANAMEDINAMCKINLEYTALLIENORTH
PORTLAND
LINWOODFIRETHORN D E N NY
KORTWRIGHTEASTKIRKSHIRE
BERNICEC H IP PE R
CLAYFOLGERHICKORYWINDI N G R I D GE
LOGCAB IN
IOLAJOANNA OVERBROOKTREGARON
HIGHHAMP TONMANI
TOUSERAMA
TWINSPRINGS
JULIAN
VICTORIA
WARWICK
P R IV ATE
SWAN
HUNTLEIGH LINDWORTHFOX RIDGE LEAGRAMLOCKETTHICKOR Y WARSONOAKCLAYLITZSINGERSLINDBERGHBLVD §¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11994
Wastewater
15
$515,000
Ladue
Lemay/RDP
Deer Creek
Capital
184Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
JEFFERSON BARRACKS TUNNEL (LEMAY WWTPTO MARTIGNEY PS)
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
EXISTING COLLECTION SYSTEM IS UNDERSIZED FOR CURRENTCONDITIONS. PORTIONS OF THE SYSTEM ARE VULNERABLE TODAMAGE IN HIGH RIVER CONDITIONS.
CONSTRUCT 17,000 FEET OF 7 FOOT DIAMETER DEEP TUNNEL,ELIMINATING THE MARTIGNEY (P-306) AND JEFFERSON BARRACKS(P-305) PUMP STATIONS.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FUTURE YEARS. TOTAL CONSTRUCTION BUDGET IS$106,900,000.
§¨¦255
§¨¦55
§¨¦255
§¨¦55
UNIONPACIFICKOCHRIVERKINSWOOD GREGGREAVIS
B
A
R
R
ACK
SFORDER CCCGRANTLIND TELFO R D
HOFFM
EIS
TE
R
ARLEE
SHERMAN
MILDGENTRYFAIN
IONE
PRIVATEJOPLINCLIFFR IN G E R
SHER ID A NPOTTLE
ORIENT
RIPA
LUNAPOPLAR
GARK
WILL LARKCLAGEROUTE R
VICTORY AVENUE HBOUNDARYHORN
JEFFERSONIAN
PAULE
HAL S EYFIRSTPECAN
A
SHROCK
JACINTO
SOUTHSHIRE
ARRAS
J
E
FFERSONBLUE RIDGEBANISTERALLEN
LISIE
U
X KASKEBUNKERBIRCHPR
IVATETELEGRAPHR DLEMAYFERRYRD§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11711
Wastewater
15
$35,200,000
Unincorporated
Lemay/RDP
Martigney Creek
Capital
185Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
JEFFERSON BARRACKS TUNNEL (LEMAY WWTPTO MARTIGNEY PS)
Engineering DuringConstruction Services
6660 - SanitaryReplacement Fund
EXISTING COLLECTION SYSTEM IS UNDERSIZED FOR CURRENTCONDITIONS. PORTIONS OF THE SYSTEM ARE VULNERABLE TODAMAGE IN HIGH RIVER CONDITIONS.
CONSTRUCT 17,000 FEET OF 7 FOOT DIAMETER DEEP TUNNEL,ELIMINATING THE MARTIGNEY (P-306) AND JEFFERSON BARRACKS(P-305) PUMP STATIONS.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FUTURE YEARS. TOTAL CONSTRUCTION BUDGET IS$106,900,000.
§¨¦255
§¨¦55
§¨¦255
§¨¦55
UNIONPACIFICKOCHRIVERKINSWOOD GREGGREAVIS
B
A
R
R
ACK
SFORDER CCCGRANTLIND TELFO R D
HOFFM
EIS
TE
R
ARLEE
SHERMAN
MILDGENTRYFAIN
IONE
PRIVATEJOPLINCLIFFR IN G E R
SHER ID A NPOTTLE
ORIENT
RIPA
LUNAPOPLAR
GARK
WILL LARKCLAGEROUTE R
VICTORY AVENUE HBOUNDARYHORN
JEFFERSONIAN
PAULE
HAL S EYFIRSTPECAN
A
SHROCK
JACINTO
SOUTHSHIRE
ARRAS
J
E
FFERSONBLUE RIDGEBANISTERALLEN
LISIE
U
X KASKEBUNKERBIRCHPR
IVATETELEGRAPHR DLEMAYFERRYRD§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11711
Wastewater
11
$705,000
Unincorporated
Lemay/RDP
Martigney Creek
Capital
186Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
KAPPEL (PARTIAL) I/I REDUCTION (EXUMA DRAND GLEN OWEN DR)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING OVERCHARGED SEWERS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12024.
HORDLUCASNHUNTELIZABETHNORFOLK SOUTHERN
BERMUDAWOODSTOCK
FERGUSON
S
H
A
N
N
O
N
KAP PEL
STEIN
M
A
R
YDAYBARATVICKIEPAULGLENOWEN NOLTEDARST IMPERIALLORNADELLWOODJACOBI
L E E
T H A T CHER
E X U MA
L ANGKIRK
T
Y
R
E
LL
NEMNICHFORESTWOOD
HALEYGAGEAMESVENTURAELLI
SONM C L ARAN
BLANDING JETTRANDCLARIONKRO E G E R
ST CY RCLAIRMONTMEDFORDHEYDTDELLRIDGECROWNPOINT
B OYCEGLADECAPITOL
MAYBRAN D
CHAMPLIN
HI GHMONT VENI
CEELKAN MAYFAIRAVERILLSMI
THCLAYBEHLESCOTTDALEPAYNELARKIN
WINKLERS U M T ER
STLO
UIS
A D A MS
CHURCHTESTON SCHLUETERC A N FIELD
F I R BON OAKWEDGEWESTDELLD A MANMILLMAN
AVIE PRIVATEBALLMANW ILBERTGREENVALLEYFERMO
AKINS
FENW
I
CKPANNELLD A R T M O O R DUNNIDEERPEPPERINAG
U
ABALBOAJ
E
N
D
A
L
EMAYAMEADOWLARKELMDALESUMMITROBERTKNOLLCRESTWYLINHEC H T
ELTA
R
OSE
TILFORDBON OAKWI
NKLER§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12314
Wastewater
15
$195,000
Various
Bissell
Maline Creek
Capital
187Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
KIRKWOOD MIDDLE SCHOOL, SIMMONS, WILSON,W SARAH I/I REDUCTION (MANCHESTER RD ANDKIRKWOOD RD)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS,OVERCHARGED SEWERS, AND ACTIVATING CONSTRUCTED SSOS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12037.GEYERWOODLAWNDICKSONBOPPESSEXRUTHEVANSWOOD
WAY CLAYSIMMONSHARRISONWILSON QUANWOODGATE
DOUGHERTYFE R R Y
BODLEY BENNETTOAKSQUIRES
SARAH
OAK V ALLEY
PAR
IRISTRENT
TAYLORDEACONHILLNANAMEDINA
G RAYCENTRALTALLIE OLD WARSON
LINWOOD
MAPLEFIRETHORN
LONGVIE
W
DE N NY
MARK
JEWEL RENDERERTWIN FAWN S
LINDGATE
KIRKSHIRE
FLA N D E R S
CURRANCLA YC HESTER
GOETHEKEND
ONBOGEYMISSOURIFOLGERHICKORY B R O W NELLLINDEMANNPAMELA
HIGHHAMPT O N
SERAMA
JULIANVINETTA CHELSEA
VICTORIA
W ARWICK
BAMBURY
PRIV A TETIMBER
CHRISTINESWAN
HUNTLEIGH
PEARLSCOTTSDALE
MOZARTBEAUFORDBRIAR RIDGE
LYNKIRK HAVERSHAMGASLITE
DUNLORA
SYLVANFUHRMANN
LINDEMANEARLSTURGISCLAYBOPPPRIVATEHICKOR Y
PARJEWELPRIVATE
BODLEY
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11995
Wastewater
15
$455,000
Kirkwood
Lemay/RDP
Deer Creek
Capital
188Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
MALINE CREEK CSO BP 051 & 052 LOCAL STORAGEFACILITY (CHAIN OF ROCKS DR TO CHURCH DR)
Construction(SupplementalAppropriation)
6660 - SanitaryReplacement Fund
CONTROL OF COMBINED SEWER OVERFLOW IS REQUIRED BY THECONSENT DECREE.
CONSTRUCT A 28-FOOT DIAMETER UNDERGROUND COMBINED SEWERSTORAGE FACILITY 3,000 FEET IN LENGTH, A 12.5 MGD PUMP STATION,AND ASSOCIATED COLLECTOR SEWERS. BUDGET INCLUDES $525,000FOR AMEREN FACILITY RELOCATION AND SERVICE TO THE NEWFACILITY.
SUPPLEMENTAL FUNDING FOR A PROJECTED FIVE YEARCONSTRUCTION PROJECT. TOTAL CONSTRUCTION BUDGET IS$86,200,000.HALLFONTAINE
GUSTAVMELV IN
JORDANLOWELLCHAIN OF ROCKS
NASSAU
HARLAN
LOGAN
DONNELL
RAFORD
JENNINGS STATION
CHURCH
G
A
ST
O R A N
JACKSON
FREMONT RIVERRUNRIVER TRAIL
P O R T L A N D
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11656
Wastewater
15
$29,000,000
St. Louis City
Bissell
Maline Creek
Capital
189Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
MALINE CREEK CSO BP 051 & 052 LOCAL STORAGEFACILITY (CHAIN OF ROCKS DR TO CHURCH DR)
Engineering DuringConstruction Services
6660 - SanitaryReplacement Fund
CONTROL OF COMBINED SEWER OVERFLOW IS REQUIRED BY THECONSENT DECREE.
CONSTRUCT A 28-FOOT DIAMETER UNDERGROUND COMBINED SEWERSTORAGE FACILITY 3,000 FEET IN LENGTH, A 12.5 MGD PUMP STATION,AND ASSOCIATED COLLECTOR SEWERS. BUDGET INCLUDES $525,000FOR AMEREN FACILITY RELOCATION AND SERVICE TO THE NEWFACILITY.
SUPPLEMENTAL FUNDING FOR A PROJECTED FIVE YEARCONSTRUCTION PROJECT. TOTAL CONSTRUCTION BUDGET IS$86,200,000.HALLFONTAINE
GUSTAVMELV IN
JORDANLOWELLCHAIN OF ROCKS
NASSAU
HARLAN
LOGAN
DONNELL
RAFORD
JENNINGS STATION
CHURCH
G
A
ST
O R A N
JACKSON
FREMONT RIVERRUNRIVER TRAIL
P O R T L A N D
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11656
Wastewater
11
$485,000
St. Louis City
Bissell
Maline Creek
Capital
190Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
MISSISSIPPI FLOODWALL ORS PUMP STATIONSREHABILITATION
Construction
6660 - SanitaryReplacement Fund
FLOODWALL ORS PUMP STATIONS, GATES, AND STRUCTURES ARE OVER50 YEARS OLD, AND ARE IN NEED OF REHABILITATION.
REHABILITATE FLOODWALL PUMP STATIONS, GATES, AND STRUCTURES.
THIS PROJECT RECEIVES PARTIAL FUNDING / SUPPLEMENTALAPPROPRIATION IN FY 19. TOTAL CONSTRUCTION BUDGET IS $5,000,000.
§¨¦70
§¨¦270
§¨¦64
§¨¦44
§¨¦55
§¨¦170
§¨¦70
§¨¦170
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12483
Wastewater
15
$2,500,000
St. Louis City
Various
Various
Capital
191Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
PADDOCK CREEK I/I REDUCTION (PRIVATE) PART2
Construction, Phase II
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
CONSTRUCT 300 FEET OF 12-INCH STORM SEWER, AND REMOVEPRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 11923.
DERHAKE
N
E
W H
A
L
L
S F
E
R
R
Y
ST ANTHONY
ST CATHERINE
WATERFORD
P
A
DDOCK
W
A
S
HIN
G
T
O
N NEROAVON
NARA
STLOUIS
CATOALLEN
PRIVATE
AQUEDUCTAUBUCHONOLD
HALL
S
F
ERRYHUMES
POHLMANTROTTERMARIETTASADDLEKINGSLEYLISACASTELLO DANUBETHUNDERBIRD
STDENI SH E L MKAMPF
FAIRW A Y
PAPALS
TEUGENE TINARIDGESEVENHILLS
MILETUS
ESTATE S
LARRYTREMONT
VAND ALSPYRENEESSORRELL
SEVILLE
STIR RUP
CARL A
BAYMEADOWSFOX RUN
GREENGRASS
RHINECAPRII N DIANC
U
PBELCROFT
PIMLI
CO
F
LORVALRENEEFAIRMOUNTBON AIREBROWN
GALLOPSTEED
WILSHIREDAUPHIN
MOHAN
DENISEWINDSOR
LILA
R O B INWOODNARRAGANSET
S T L U K E
PENHURST
KAEL VALENCIAEADSTONEDANABROADMEREHOLLY
BELAIRKELLY
ST STEPHEN
PRIVA TEBROWNPRIVATE
PRIVATELINDBERGH §¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11696
Wastewater
15
$120,000
Various
Coldwater
Coldwater Creek
Capital
192Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
PRIVATE INFLOW AND INFILTRATION REDUCTIONPROGRAM
Work Order Repair Costs(Capital)
6660 - SanitaryReplacement Fund
PRIVATE SOURCES OF INFLOW AND INFILTRATION ARE OVERCHARGINGSANITARY SEWERS.
CONTINUE PROGRAM TO REDUCE PRIVATE INFLOW AND INFILTRATIONFLOW SOURCES FROM THE SANITARY SYSTEM.
PROJECT MAY INCLUDE BOTH CAPITAL AND NON-CAPITAL SERVICES.
§¨¦44
§¨¦55
§¨¦64
§¨¦70
§¨¦270
§¨¦170
§¨¦255§¨¦44
§¨¦70
§¨¦55
§¨¦170
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11877
Wastewater
17
$500,000
Various
Various
Various
Non-recurring
193Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
REAVSDALE I/I REDUCTION (MACKENZIE RD ANDREAVIS BARRACKS RD)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
§¨¦55HALEMACKENZIEIONE UNIONRADIORADIOM
REAVIS TIBERLEMONA
REAVISBARR
A
C
KS
SOUTHVIEW
NEMO
ZEN ITHBRENDABURLINGTONNORTHERNSANTAFEERIEPORTFORMAN
RIPA
MOHEGAN
DANAEV
ANDALE
AVILATALBOT
JEFFLEIGHUPLAND
KOERBER
SHAPFIELDPANCHO MONTBROOKDORISANN
EIFFEL
ANCHOR
LYDELL
ARVIN
PRIVATEPAPOOSEVILLARIDGECISCOARROW HOWERTONSEQUOIA
MADAFORDBLACKHAWK
CAYUGA
CASAROSA
BL A C K P O OL
BONTONBREUERATWOOD
VASEL
HUNTINGDONJUDITH
DAMS O NJACHURST
BERWICK
SONTAG
ALPINE
AFFTON WARRIORASTERWILMA
MARYVALECHAMBLINNIGER
SHUFFLEVIAVENETO
EUCALYPTUS ZANECHESTERTONPAULINE
WAGER
APLEYLABETTELENARD
AMONA
HALLOCK
CITADEL
BUNK ERHILLFLAGLERALPINE
P R IV ATE
ARVIN
ZENITHDANADANA§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12420
Wastewater
15
$130,000
Unincorporated
Lemay/RDP
Gravois Creek
Capital
194Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
ROXBURY I/I REDUCTION PART 2
Construction, Phase II
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
CONSTRUCT 1,600 FEET OF 12-INCH STORM SEWERS, AND REMOVEPRIVATE I/I SOURCES AT 15 PROPERTIES.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 11849. OMCI BUDGETFUNDS STORM SEWERS TO BE BUILT AS A PART OF THIS PROJECT.
§¨¦170
§¨¦170
HANLEYCLAYTON BRENTWOODME
T
R
OL
I
N
K
DAVIS
FORSYTH
WENNEKERFOREST PAR K
MARYLAND
F
RA
N
CI
S
S H A W P A R K
CENTRALLOUWENMERAMECBEMISTONP
OLOHUNTERBONHOMME
WESTWOODLANGTONTOP
T
ON
GAY
WATKINS
DR
O
M
A
R
A
BERKSHIRECARONDELET
LINDENP A RK
T
A
N
G
L
E
WO
O
D
WYDOWNCARSWOLD
MCCUTCHEONDAYTONA EDGEWOODRE AR
GALLERIA
HALI F A XPOINTER
YORKBRIG
HTON
VENETIAN
C O L M A R
CRESC
E
N
T
BYRONOAKLEYORLANDOBLACKCREEK
ROSILINE
LAKEFO R E S TSUDBURYP
RI
VATE LYLEWALINCA
WHITBURN MOHAWK
BILTMORECENTRAL M E T R O L IN K
FOREST PARK
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11680
Wastewater
15
$330,000
Clayton
Lemay/RDP
Black Creek
Capital
195Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
ROXBURY I/I REDUCTION PART 2
Construction, Phase II
5566 - Deer CreekOMCI Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
CONSTRUCT 1,600 FEET OF 12-INCH STORM SEWERS, AND REMOVEPRIVATE I/I SOURCES AT 15 PROPERTIES.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 11849. OMCI BUDGETFUNDS STORM SEWERS TO BE BUILT AS A PART OF THIS PROJECT.
§¨¦170
§¨¦170
HANLEYCLAYTON BRENTWOODME
T
R
OL
I
N
K
DAVIS
FORSYTH
WENNEKERFOREST PAR K
MARYLAND
F
RA
N
CI
S
S H A W P A R K
CENTRALLOUWENMERAMECBEMISTONP
OLOHUNTERBONHOMME
WESTWOODLANGTONTOP
T
ON
GAY
WATKINS
DR
O
M
A
R
A
BERKSHIRECARONDELET
LINDENP A RK
T
A
N
G
L
E
WO
O
D
WYDOWNCARSWOLD
MCCUTCHEONDAYTONA EDGEWOODRE AR
GALLERIA
HALI F A XPOINTER
YORKBRIG
HTON
VENETIAN
C O L M A R
CRESC
E
N
T
BYRONOAKLEYORLANDOBLACKCREEK
ROSILINE
LAKEFO R E S TSUDBURYP
RI
VATE LYLEWALINCA
WHITBURN MOHAWK
BILTMORECENTRAL M E T R O L IN K
FOREST PARK
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11680
Wastewater
15
$700,000
Clayton
Lemay/RDP
Black Creek
Capital
196Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
SPRINGDALE I/I REDUCTION (ROLLING DR ANDSMITHFIELD PL)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING OVERCHARGED SEWERS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12025.
§¨¦70
§¨¦70
HANLEYSHIRLEYRAMONA
METROLINK
LADAL I N K
MALINESPRINGDALESARGENTBOSTON
JANE
ALVA
SPUR CRANBERRYT O R I I
JEN N Y
WELD O N
BELFORET
O
RCHLAMP
HIGGINSON
GEIGER
SEV E R IN
APPLEBERRYELAINE
T
ORCHLIT EROZI
ERL
OGANBERRY
PAR K
M E D O R ARICKEYSMITHFIELD GARVIN
KATHERINE
R
U
SSETRANCHSNOWHILL MEDORAC R A N B E R R Y
METROLINK
G A R V I N
NATURALBRIDGERD
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12209
Wastewater
15
$82,000
Bel-Ridge
Bissell
Maline Creek
Capital
197Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
STERLING PLACE SEPARATE SEWER I/I REMOVALPART 2
Construction, Phase II
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS,OVERCHARGED SEWERS, AND ACTIVATING CONSTRUCTED SSOS.
CONSTRUCT 3,900 FEET OF 12-INCH TO 30-INCH STORM SEWER, ANDREMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS. PART 2 SCOPEIS TO CONSTRUCT 700 FEET OF 12-INCH STORM SEWER, AND REMOVEPRIVATE I/I SOURCES.
PUBLIC I/I REDUCTION INCLUDED IN PROJECT 12061 AND PROJECT11927.
WEBER MACKENZIEHEEGE
VALCOURMATHILDAROCKHILL
I
VYREAVIS
ALICETONLACLEDE STATIONSTAELY
HALENEW HAMPSHIREGRAMOND
KITLUCIAVITA
TIBERAL
T
H
EAVASEL PILOTRADIOBONNIE
NIL
E
SBRENDAMAXWELLMAYLORELSA
AFFTONEDEN
ERIEELGINLANGLEY
PORTDELMA
RAMBLERNEIERASTEREVANDALEKIDDERSTERLING TALMAARDALE DARLOWCRAIGHILL
AVILAARVIN
TALBOT
LAWNSIDE
UPLAND
B ERWICK JOELG R A CE
BRINKERIDAMOR
PRIVATEL A V E R N
HOSMER
DA
R
L
E
N
E
CHESHIRE CHIVVISM ARLENEPROVOGENERALSHERMAN
ALPINE
YORKSHIRE
BIXBY
LETA CHARLTONCREEKVIEW
PONTIACMCGEEPALMETTONIGER
ZANEFORESTA TEBLUEWATER
VILLATONDEXTER
PAULINECONSULRAYWOODIRENEGRASSO JONMARHE RITA G ECYRUSAFFTON
ALPINE RADIOWEBERVASEL
ARVINVA
SEL
CHESHIRE
G R A V O IS R D
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11667
Wastewater
15
$400,000
Unincorporated
Lemay/RDP
Gravois Creek
Capital
198Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
UNION CREEK I/I REDUCTION (I-55 BETWEEN SLINDBERGH BLVD AND BUCKLEY RD)
Construction
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
REMOVE PRIVATE I/I SOURCES FROM SANITARY SEWERS.
§¨¦55
§¨¦270
§¨¦255§¨¦55 §¨¦255 UNIONWILL
GREEN PARK
VO NTALGECORDESBURLINGTONNORTHERNS A NTAFEKINSWOOD CLIFFFAIN
T
H
EIS
S MUELLERKOHRSPOPLAR
MUSICK
CONCORD
ANTIGO
ELIFLORIALIX SPOKANECAMINOLAN
SEDANTIMM
BARRACKSVIEW
JAN
DILLONPECANCHEVRON
YUMA
JACINTO
LAURABUCKLEYPE A LPEACE
HAVENJEFFLEIGHHAWKSTONE
SOUTHSHIRE
MCCORRY
REVEREVICTORYANITAFIVEOAKSBEHRSUNNYVIEW
H U BERTBELLEWOOD
BERVIEWSLEVIN
MANOR
EIFFEL
BANISTERCOACHELLA
HERPEL
MALUS
SOLAR
CRESCENTCALEFGREENPARKINDUST
RIA
L
ELM PARKGUEHRING DOLPHGLORIARITZ
OPAL BIRCHGRA D IE N T
LOIS
SAXON
GAPSCH
PINE HILL GENEFITE
BOXPASCHALVICTORY
BUCKLEYLEMAY FERRY RD§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 12240
Wastewater
15
$240,000
Unincorporated
Lemay/RDP
Gravois Creek
Capital
199Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
WEBSTER GROVES TRUNK E SANITARYREHABILITATION AND I/I REDUCTION PHASE IVPART 3
Construction, Phase III
5566 - Deer CreekOMCI Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
CONSTRUCT 3,200 FEET OF 12-INCH TO 21-INCH STORM SEWER, ANDREMOVE PRIVATE I/I SOURCES AT 40 PROPERTIES.
OMCI BUDGET FUNDS STORM SEWERS TO BE BUILT AS A PART OF THISPROJECT.
§¨¦44BERRYUNIONPACIFIC
LOCKWOOD
KIRKHAM
GRAYDICKSONEDGARLACLEDESTATIONGOREOLDWARSON
NEWPORT
GLENDALE
B U R L IN G T O N N O R T H E R N S A N T A F E
LEE
ELMCLARK
BOMPARTHANL
EYSAPPINGTONESSEX
HOLMESMAPLEODAYLILACBELLBAKER
BISMARK
JACKSON
BROWNELL
ARGONNE
ATALANTAGL ENBRENTWOOD
OAK TREE
EUCLID
LITHIABENNETTMADISON
P ACIFIC
PLANTBACON
SUMMITJOYLOUISADAMS
MADGE
ANDREWJEFFERSONSYLVESTERSCOTT OA KGILBERT
OAK L A N D SALEMPARKMARYAUSTINFAIRVIEWHOLLANDMCKINLEY
IOLAREAVISNORTH
YEATMANGAR D E NROCK HILLG
R
A
NTPAPIN
IMSEKORTWRIGHTSPRINGFO R ESTCLARAHOLLYWOODDESPERES WILSHUSENWAYMIRE
ALMASELMAJOANNA
EUNICE
D OBBI N
RAVENSRIDGE
HIGHHAMP T O NFIELDSTON
VICTORIA
WARWICK
MOODY
ARBOR
HULLRUTHBUSCHTYLEREASTP ORTERG R O V E
COLLEGE HILLDALELOCKSLEYCEDARWOODLAWNGASLITE
MABELMINTURN ROCK HILLOAKSELMAELMB E R R Y
ELMELMSUMMIT
M
A
P
L
E
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11678
Wastewater
15
$100,000
Webster Groves
Lemay/RDP
Deer Creek
Capital
200Page
2018
FISCAL YEAR:
Description of Problem/Issue
Scope of Project
Comments/Remarks
Metropolitan St. Louis Sewer District
TASK NO:
TASK NAME:
BUDGET:
FUND:
MUNICIPALITY:
MAJOR SERVICE AREA:
WATERSHED:
PROJECT TYPE:
EXPENSE TYPE:
WEBSTER GROVES TRUNK E SANITARYREHABILITATION AND I/I REDUCTION PHASE IVPART 3
Construction, Phase III
6660 - SanitaryReplacement Fund
INFLOW AND INFILTRATION CAUSING BUILDING BACKUPS ANDOVERCHARGED SEWERS.
CONSTRUCT 3,200 FEET OF 12-INCH TO 21-INCH STORM SEWER, ANDREMOVE PRIVATE I/I SOURCES AT 40 PROPERTIES.
OMCI BUDGET FUNDS STORM SEWERS TO BE BUILT AS A PART OF THISPROJECT.
§¨¦44BERRYUNIONPACIFIC
LOCKWOOD
KIRKHAM
GRAYDICKSONEDGARLACLEDESTATIONGOREOLDWARSON
NEWPORT
GLENDALE
B U R L IN G T O N N O R T H E R N S A N T A F E
LEE
ELMCLARK
BOMPARTHANL
EYSAPPINGTONESSEX
HOLMESMAPLEODAYLILACBELLBAKER
BISMARK
JACKSON
BROWNELL
ARGONNE
ATALANTAGL ENBRENTWOOD
OAK TREE
EUCLID
LITHIABENNETTMADISON
P ACIFIC
PLANTBACON
SUMMITJOYLOUISADAMS
MADGE
ANDREWJEFFERSONSYLVESTERSCOTT OA KGILBERT
OAK L A N D SALEMPARKMARYAUSTINFAIRVIEWHOLLANDMCKINLEY
IOLAREAVISNORTH
YEATMANGAR D E NROCK HILLG
R
A
NTPAPIN
IMSEKORTWRIGHTSPRINGFO R ESTCLARAHOLLYWOODDESPERES WILSHUSENWAYMIRE
ALMASELMAJOANNA
EUNICE
D OBBI N
RAVENSRIDGE
HIGHHAMP T O NFIELDSTON
VICTORIA
WARWICK
MOODY
ARBOR
HULLRUTHBUSCHTYLEREASTP ORTERG R O V E
COLLEGE HILLDALELOCKSLEYCEDARWOODLAWNGASLITE
MABELMINTURN ROCK HILLOAKSELMAELMB E R R Y
ELMELMSUMMIT
M
A
P
L
E
§¨¦ 64
§¨¦ 44
§¨¦ 55
§¨¦ 64
§¨¦ 70
§¨¦270
§¨¦170
§¨¦255§¨¦ 44
§¨¦ 70
PROJECT NO: 11678
Wastewater
15
$2,360,000
Webster Groves
Lemay/RDP
Deer Creek
Capital
201Page
2018