11790 CAULKS CREEK
FORCEMAIN (RIVER
VALLEY RD TO L-52)
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN FEBRUARY, 2018.
$6,600,000
11788 CAULKS CREEK PUMP
STATION B FORCEMAIN
PROJECT CONTINUED DUE TO REBIDDING REQUIRED
AFTER LOW BID WITHDRAWL. ANTICIPATE BOARD
INTRODUCTION IN SEPTEMBER, 2017.
$6,000,000
10601 FF-16 SCHUETZ -
MEADOWSIDE TO PAGE
SANITARY RELIEF
PROJECT CONTINUED DUE TO MAJOR SCOPE REVISION.
ANTICIPATE BOARD INTRODUCTION IN JULY, 2017.
$12,300,000
12635 JAGUAR TO CAROLINE
LOW PRESSURE SEWER
SYSTEM (LPSS)
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN MAY, 2018.
$650,000
12502 MISSOURI RIVER WWTF
POWER FEEDER
REPLACEMENT
PROJECT CONTINUED DUE TO MAJOR SCOPE REVISION.
ANTICIPATE BOARD INTRODUCTION IN FEBRUARY, 2018.
$750,000
11698 PICKWICK - BERNADINE -
BIMINI SANITARY RELIEF
PROJECT CONTINUED DUE TO DESIGN REVISIONS.
ANTICIPATE BOARD INTRODUCTION IN NOVEMBER, 2017.
$441,000
11992 UNIVERSITY CITY
SANITARY STORAGE
FACILITY (HAFNER CT)
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN DECEMBER, 2017.
$3,700,000
TOTAL: $30,441,000