WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
1101 - GENERAL FUND
11144 Professional
Services
BISSELL - COLDWATER - MISSOURI -
MERAMEC SANITARY SYSTEM
IMPROVEMENTS (WATERSHED
CONSULTANT)
Various $650,000
12000 Vendor
Services
CCTV INSPECTION AND PHYSICAL
INSPECTION OF SEWERS (2020)
Various $2,500,000
11146 Construction CSO VOLUME REDUCTION GREEN
INFRASTRUCTURE
Various $5,000,000
12759 Vendor
Services
FLOW METERING AND MONITORING (2017)Various $2,500,000
12382 Appraisal
Services
GENERAL SERVICES AGREEMENT -
PROPERTY APPRAISAL (2018) CONTRACT A
Various $60,000
12383 Appraisal
Services
GENERAL SERVICES AGREEMENT -
PROPERTY APPRAISAL (2018) CONTRACT B
Various $60,000
12384 Appraisal
Services
GENERAL SERVICES AGREEMENT -
PROPERTY APPRAISAL (2018) CONTRACT C
Various $60,000
12385 Appraisal
Services
GENERAL SERVICES AGREEMENT -
PROPERTY APPRAISAL (2018) CONTRACT D
Various $60,000
12010 Work Order
Repair Costs
(Non-Capital)
INFRASTRUCTURE REPAIRS
(WASTEWATER) (2020)
Various $1,500,000
11145 Professional
Services
LEMAY SANITARY SYSTEM
IMPROVEMENTS (WATERSHED
CONSULTANT)
Various $650,000
11109 Professional
Services
LOWER & MIDDLE RDP CSO CONTROLS
SYSTEM IMPROVEMENTS (WATERSHED
CONSULTANT)
Various $375,000
12006 Vendor
Services
RADAR RAINFALL DATA (2020)Various $150,000
11153 Professional
Services
RDP TRIBUTARIES & UPPER RDP CSO
CONTROLS & LOWER MERAMEC SYSTEM
IMPROVEMENTS (WATERSHED
CONSULTANT)
Various $800,000
10766 Vendor
Services
STREAM FLOW GAUGE OPERATION AND
MAINTENANCE (USGS)
St. Louis City And
County
$625,000
12004 Vendor
Services
STREAM FLOW WATER QUALITY
SAMPLING (2020)
Various $300,000
FUND TOTAL: $15,290,000
4102 - IMPROVEMENT FUND
12897 Work Order
Repair Costs
(Capital)
INFRASTRUCTURE REPAIRS (FACILITIES)
(2020)
Various $3,000,000
11 April 2017
WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
FUND TOTAL: $3,000,000
6660 - SANITARY REPLACEMENT FUND
11993 Construction 82ND STREET TO I-170 SANITARY RELIEF
(UR-08, UR-09)
University City $4,000,000
12847 Construction BADEN CITYSHED MITIGATION BASINS
(CALVARY, FREDERIK, PARTRIDGE AND
TILLIE)
St. Louis City $10,000,000
12092 Construction BELLEFONTAINE #2 SANITARY RELIEF
(CHAMBERS RD TO COBURG LANDS DR)
Bellefontaine
Neighbors
$2,465,000
12027 Construction BISSELL - COLDWATER - MISSOURI -
MERAMEC PUBLIC I/I REDUCTION (2019)
CONTRACT B
Various $7,869,000
12033 Construction BISSELL - COLDWATER - MISSOURI -
MERAMEC PUBLIC I/I REDUCTION (2020)
CONTRACT A
Various $1,815,000
12030 Construction BISSELL - COLDWATER - MISSOURI -
MERAMEC PUBLIC I/I REDUCTION (2020)
CONTRACT B
Various $6,826,000
12508 Design Services BISSELL - COLDWATER - MISSOURI -
MERAMEC PUBLIC I/I REDUCTION (2021)
CONTRACT A
Various $190,000
12509 Design Services BISSELL - COLDWATER - MISSOURI -
MERAMEC PUBLIC I/I REDUCTION (2021)
CONTRACT B
Various $340,000
11144 Professional
Services
BISSELL - COLDWATER - MISSOURI -
MERAMEC SANITARY SYSTEM
IMPROVEMENTS (WATERSHED
CONSULTANT)
Various $1,040,000
12492 Construction BISSELL POINT WWTF BELT FILTER PRESS
CONVEYOR REPLACEMENT
St. Louis City $3,400,000
12493 Construction BISSELL POINT WWTF SOUTH ASH LAGOON
FLOOR REPLACEMENT
St. Louis City $3,200,000
12100 Construction BRENTWOOD FOREST, FAIR OAKS,
MIDDLESEX I/I REDUCTION (I-64 AND LAY
RD)
Brentwood $493,000
12103 Design Services BRINWOOD SANITARY RELIEF (SHARON DR
TO CORTEZ DR AND SHACKELFORD RD TO
DANNELLE DR)
Florissant $500,000
12104 Construction BROOKSHIRE SANITARY RELIEF
(BROOKSHIRE DR TO COUGAR DR)
Unincorporated $3,821,000
12110 Design Services CANTERBURY DRIVE LATERAL SANITARY
RELIEF (NELSON DR TO CANTERBURY DR)
Northwoods $370,000
12111 Construction CAPILIA SANITARY RELIEF (GRANT RD TO
CAPILIA DR)
Crestwood $1,463,000
12112 Construction CARSON VILLA I/I REDUCTION (MARCELLA
AVE AND WALES AVE)
Bel-Ridge $1,000,000
11 April 2017
WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
11789 Construction
(Supplemental
Appropriation)
CAULKS CREEK FORCEMAIN
REHABILITATION
Chesterfield $8,000,000
11917 Construction CELLA - ROLLING ROCK - GLEN CREEK
SANITARY SEWER AND PUBLIC I/I
REDUCTION
Ladue $2,170,000
12851 Design Services CHATHAM MANOR PUMP STATION (P-520)
ELIMINATION
Unincorporated $250,000
12121 Design Services CHRISTOPHER DR I/I REDUCTION
(ENGLAND TOWN RD TO BECKER RD)
Unincorporated $20,000
11152 Professional
Services
CONSTRUCTION MANAGEMENT SERVICES -
LOWER AND MIDDLE RDP TUNNEL
FACILITIES
Various $5,000,000
11826 Professional
Services
CONSTRUCTION MANAGEMENT SERVICES -
LOWER MERAMEC AND DEER CREEK
TUNNELS
Various $7,500,000
11151 Professional
Services
CONSTRUCTION MANAGEMENT SERVICES -
TANK/TREATMENT/PUMP STATION
FACILITIES
Various $7,300,000
12131 Construction CONWAY VILLAGE SANITARY RELIEF
(CONWAY RD TO I-64)
Town And Country $2,710,000
12432 Construction CREVE COEUR CREEK PUBLIC I/I
REDUCTION SOUTH
Various $5,280,000
12138 Construction CROSSROADS, HANLEY INDUSTRIAL,
LITZSINGER EAST I/I REDUCTION (SW I-64
AND S HANLEY RD)
Brentwood $206,000
12139 Design Services CSO - BRENTWOOD AND RED BUD AVE CSO
INTERCEPTOR (I-118)/OUTFALL (L-111)
ELIMINATION AND SEWER SEPARATION
Richmond Heights $2,000,000
12144 Construction DARTMOUTH AVENUE SEWER SEPARATION University City $1,600,000
12472 Construction
(Supplemental
Appropriation)
DC-02 & DC-03 SANITARY RELIEF
(BRENTWOOD BLVD TO CONWAY RD)
PHASE III AND PHASE IV
Various $20,000,000
11731 Engineering
During
Construction
Services
DEER CREEK SANITARY TUNNEL
(CLAYTON RD TO RDP)
Various $1,000,000
11731 Construction
(Supplemental
Appropriation)
DEER CREEK SANITARY TUNNEL
(CLAYTON RD TO RDP)
Various $20,000,000
12615 Engineering
During
Construction
Services
DEER CREEK SANITARY TUNNEL
(CLAYTON RD TO RDP) - PUMP STATION
Various $1,000,000
12615 Construction
(Supplemental
Appropriation)
DEER CREEK SANITARY TUNNEL
(CLAYTON RD TO RDP) - PUMP STATION
Various $15,000,000
11 April 2017
WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
12146 Design Services DENNIS HILLS I/I REDUCTION (MAY
VALLEY LN AND GREENMAR DR)
Unincorporated $20,000
12148 Design Services DIX SANITARY RELIEF (DIX AVE TO
AIRWAY AVE)
Breckenridge Hills $290,000
12516 Property Rights
Acquisition
EASEMENT ACQUISITION FOR
WASTEWATER PROJECTS (2020)
Various $1,000,000
12160 Construction EDNA-THURSBY I/I REDUCTION (HIGHLAND
AVE TO BIG BEND BLVD)
Various $95,000
12161 Construction ELINOR AVE. TEMPORARY SANITARY
STORAGE FACILITY
Richmond Heights $770,000
12164 Construction ESSEX I/I REDUCTION (W. ADAMS AVE AND
SUGAR CREEK RIDGE DR)
Kirkwood $147,000
12376 Design Services EVA WABASH I/I REDUCTION (I-170 AND
FROST AVE)
Various $2,000,000
12166 Design Services FENTON CREEK PUMP STATION (P-425)
ELIMINATION
Unincorporated $200,000
12173 Design Services FISHPOT TRUNK WEST I/I REDUCTION
(SMITH DR AND VLASIS DR)
Ballwin $110,000
12843 Pre-Design
Services
FOREST VIEW SANITARY TRUNK SEWER Sunset Hills $250,000
12183 Design Services FOX CREEK SANITARY RELIEF (HOLLOWAY
RD TO CLAYMONT DR)
Ballwin $270,000
12184 Design Services FRANCES I/I REDUCTION (NORTHEAST OF I-
270 AND DOUGHERTY FERRY RD)
Kirkwood $30,000
12845 Design Services FRIENDSHIP VILLAGE PUMP STATION (P-
516) ELIMINATION
Sunset Hills $350,000
11137 Construction
(Supplemental
Appropriation)
GASLIGHT SQUARE SEWER
IMPROVEMENTS
St. Louis City $7,000,000
12386 General
Services -
Construction
Inspection
GENERAL SERVICES AGREEMENT -
CONSTRUCTION MANAGEMENT (2019)
Various $250,000
12397 GSA - (Design)
CIRP Funds
GENERAL SERVICES AGREEMENT -
FACILITY & SEWER DESIGN (2020)
Various $300,000
12391 GSA -
Geotechnical
CIRP Funds
GENERAL SERVICES AGREEMENT -
GEOTECHNICAL (2020) CONTRACT A
Various $50,000
12392 GSA -
Geotechnical
CIRP Funds
GENERAL SERVICES AGREEMENT -
GEOTECHNICAL (2020) CONTRACT B
Various $50,000
12393 GSA -
Geotechnical
CIRP Funds
GENERAL SERVICES AGREEMENT -
GEOTECHNICAL (2020) CONTRACT C
Various $50,000
12398 GSA - (Design)
CIRP Funds
GENERAL SERVICES AGREEMENT - SEWER
AND CHANNEL DESIGN (2019) CONTRACT A
Various $150,000
12413 GSA - (Survey)
CIRP Funds
GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2020) CONTRACT A
Various $50,000
11 April 2017
WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
12416 GSA - (Survey)
CIRP Funds
GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2020) CONTRACT B
Various $50,000
12417 GSA - (Survey)
CIRP Funds
GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2020) CONTRACT C
Various $50,000
12418 GSA - (Survey)
CIRP Funds
GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2020) CONTRACT D
Various $50,000
12419 GSA - (Survey)
CIRP Funds
GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2020) CONTRACT E
Various $50,000
12175 Construction GEYER SANITARY RELIEF AND WINDSOR
SPRINGS P-521 STORAGE (BIG BEND BLVD
TO WINDSOR SPRINGS DR)
Kirkwood $2,680,000
12272 Design Services GRAND GLAIZE TRUNK SANITARY RELIEF
(BALLWIN GOLF CLUB TO CLAYMONT
COVE CT)
Ballwin $140,000
12844 Design Services GRAND MARINER PUMP STATION (P-446)
ELIMINATION
Sunset Hills $65,000
10496 Construction
(Supplemental
Appropriation)
GRAVOIS TRUNK (WHITECLIFF TO RDP)
SANITARY REHABILITATION (FANNIE AVE
TO PARDEE LANE)
Various $15,000,000
12569 Construction
(Supplemental
Appropriation)
GRAVOIS TRUNK SANITARY STORAGE
FACILITY (PARDEE LN AND PARDEE RD)
Crestwood $20,000,000
12569 Engineering
During
Construction
Services
GRAVOIS TRUNK SANITARY STORAGE
FACILITY (PARDEE LN AND PARDEE RD)
Crestwood $500,000
11798 Design Services HARLEM BADEN RELIEF PHASE IV
(HEBERT) - HODIAMONT TO CHERRY
TRUNK SEWER B
Various $800,000
12301 Design Services HEIMOS PUMP STATION (P-503) FORCEMAIN
REPLACEMENT
Unincorporated $130,000
12311 Design Services HUNTERS FIELD I/I REDUCTION
(DOUGHERTY FERRY RD TO MANCHESTER
RD NEAR I-270)
Des Peres $150,000
12020 Construction INFRASTRUCTURE REPAIRS
(REHABILITATION) (2020) CONTRACT A
St. Louis City And
County
$2,500,000
12021 Construction INFRASTRUCTURE REPAIRS
(REHABILITATION) (2020) CONTRACT B
St. Louis City And
County
$2,500,000
12010 Work Order
Repair Costs
(Capital)
INFRASTRUCTURE REPAIRS
(WASTEWATER) (2020)
Various $5,500,000
11711 Construction
(Supplemental
Appropriation)
JEFFERSON BARRACKS TUNNEL (LEMAY
WWTP TO MARTIGNEY PS)
Unincorporated $5,000,000
11957 Construction JEFFERSON BARRACKS TUNNEL
CONSOLIDATION SEWERS
Various $1,825,000
11 April 2017
WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
11957 Engineering
During
Construction
Services
JEFFERSON BARRACKS TUNNEL
CONSOLIDATION SEWERS
Various $40,000
12319 Design Services LADUE ESTATES SANITARY RELIEF (DEER
CREEK TRUNK SEWER TO S LADUE
ESTATES DR)
Westwood $60,000
12322 Design Services LAFAYETTE SANITARY RELIEF (STRECKER
RD TO DURANGO PASS CT)
Wildwood $516,000
11817 Construction LEMAY NO. 3 PUMP STATION AND FORCE
MAIN
Unincorporated $12,170,000
11817 Engineering
During
Construction
Services
LEMAY NO. 3 PUMP STATION AND FORCE
MAIN
Unincorporated $190,000
12057 Construction LEMAY PUBLIC I/I REDUCTION (2020)
CONTRACT A
Various $5,050,000
12054 Construction LEMAY PUBLIC I/I REDUCTION (2020)
CONTRACT B
Various $2,579,000
12059 Design Services LEMAY PUBLIC I/I REDUCTION (2021)
CONTRACT A
Various $230,000
12328 Design Services LINDBERGH PARK COMBINED SEWER
RELIEF (BREDELL AVE TO PRINCETON PL)
Maplewood $650,000
11820 Engineering
During
Construction
Services
LMRDP CSO STORAGE TUNNEL
(BROADWAY TO RDP TUBES)
St. Louis City $1,215,000
11820 Miscellaneous
Services
LMRDP CSO STORAGE TUNNEL
(BROADWAY TO RDP TUBES)
St. Louis City $310,000
11820 Construction LMRDP CSO STORAGE TUNNEL
(BROADWAY TO RDP TUBES)
St. Louis City $66,755,000
12333 Design Services LOHMEYER COMBINED SEWER RELIEF
(BENTLEY DR TO BREDELL AVE)
Maplewood $170,000
12489 Design Services LOUISA AND ARSENAL PUMP STATIONS (P-
112 AND P-113) UPGRADES
St. Louis City $1,000,000
11109 Professional
Services
LOWER & MIDDLE RDP CSO CONTROLS
SYSTEM IMPROVEMENTS (WATERSHED
CONSULTANT)
Various $320,000
12255 Design Services LOWER MERAMEC WWTF EXPANSION
PHASE II
Unincorporated $3,000,000
12336 Construction MACKENZIE I/I REDUCTION
(RESURRECTION CEMETERY, WEHNER
PARK, KENRICK SEMINARY, AND NERINX
HALL)
Shrewsbury $441,000
11656 Engineering
During
Construction
Services
MALINE CREEK CSO BP 051 & 052 LOCAL
STORAGE FACILITY (CHAIN OF ROCKS DR
TO CHURCH DR)
St. Louis City $500,000
11 April 2017
WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
11656 Construction
(Supplemental
Appropriation)
MALINE CREEK CSO BP 051 & 052 LOCAL
STORAGE FACILITY (CHAIN OF ROCKS DR
TO CHURCH DR)
St. Louis City $8,200,000
12339 Design Services MANCHESTER RD AND S BIG BEND BLVD
COMBINED SEWER RELIEF (HAMPTON
CREEK TO LYNDOVER PL)
Maplewood $930,000
12342 Construction MARK TWAIN I/I REDUCTION
(MANCHESTER RD AND BOMPART AVE)
Brentwood $1,935,000
10024 Design Services MC-02 WATSON TO EDGAR RD SANITARY
RELIEF (SKME-580A)
Various $1,100,000
12348 Construction MEACHAM AND SPELLMAN I/I REDUCTION
(I-44 AND S KIRKWOOD RD)
Kirkwood $29,000
12850 Design Services MERAMEC BLUFFS (RIVER RIDGE P-501,
PINE TREE ESTATES P-466, AND SUNSET
RIDGE P-504) PUMP STATION ELIMINATIONS
Unincorporated $245,000
12352 Design Services MIDLAND SANITARY RELIEF (MIDLAND
BLVD TO SIMS AVE)
Overland $320,000
12484 Construction MISSISSIPPI FLOODWALL ORS PUMP
STATIONS REHABILITATION PHASE II
St. Louis City $2,600,000
10715 Construction NEW ENGLAND TOWN CLIFF CAVE PUMP
STATION (P-323) IMPROVEMENTS
Unincorporated $4,500,000
10716 Construction NEW ENGLAND TOWN QUARRY PUMP
STATION (P-307) (SKME-544)
IMPROVEMENTS
Unincorporated $3,500,000
12364 Design Services OAKWOOD FARMS PUMP STATION (P-470)
ELIMINATION
Ballwin $60,000
11877 Work Order
Repair Costs
(Capital)
PRIVATE INFLOW AND INFILTRATION
REDUCTION PROGRAM
Various $500,000
12698 Professional
Services
PUMP STATION REPAIR AND
IMPROVEMENT DESIGN (CONTRACT B)
Various $50,000
12441 Design Services RDP TRIBUTARIES (DEER CREEK) CSO
TUNNEL
Various $4,000,000
12188 Construction RIVERPORT 6 PUMP STATION (P-781)
REPLACEMENT
Maryland Heights $655,000
12530 Construction ROSARY LANE SANITARY RELIEF
(CLAUDINE DRIVE TO MAKIN AVE)
Unincorporated $501,000
12192 Design Services ROSEDALE AVE SANITARY RELIEF
(NEWPORT AVE TO ARBOR LN)
Webster Groves $30,000
12196 Design Services S GORE AVE SANITARY RELIEF (GRAY AVE
TO OAK TERR)
Webster Groves $140,000
12200 Design Services SAYLESVILLE SANITARY RELIEF
(SAYLESVILLE DR TO S GREENTRAILS DR)
Chesterfield $430,000
10161 Design Services SCHUETZ ROAD SANITARY RELIEF (FOREST
BROOK LN TO SUNNY WOOD CT)
Creve Coeur $70,000
12205 Construction SOUTH COUNTY SANITARY RELIEF (P-419
TO CRIPPLE CREEK DR)
Unincorporated $3,845,000
12207 Construction SPIRIT OF ST. LOUIS 2 PUMP STATION (P-
736) REPLACEMENT
Chesterfield $754,000
11 April 2017
WASTEWATER PROJECTS - FY20
PROJECT
NUMBER
TASK DESC PROJECT NAME MUNICIPALITY COST
ESTIMATE
12212 Design Services ST. GEORGE CREEK SANITARY RELIEF
(DAISY LN TO GRAVOIS RD TO NEW
HAMPSHIRE AVE)
Unincorporated $560,000
12218 Construction STONINGTON PLACE SANITARY RELIEF
(CLAYTON RD TO GEORGIAN ACRES ST)
Frontenac $1,252,000
12228 Construction TESSON CREEK I/I REDUCTION (TESSON
FERRY RD AND TIFFANY SQUARE PKY)
Unincorporated $270,000
12229 Construction THURSTON I/I REDUCTION (CHURCH ST
AND N FLORISSANT RD)
Ferguson $62,000
12230 Construction TILLES PARK, LITZSINGER AND PARKRIDGE
I/I REDUCTION (LITZSINGER RD AND S
MCKNIGHT RD)
Ladue $597,000
12232 Design Services TM-03 TWO MILE CREEK SANITARY RELIEF
(TWO MILE TRUNK TO FIRETHORN DR)
Des Peres $30,000
12238 Construction TREASURE COVE I/I REDUCTION (RIES RD
AND BROOKSIDE LN)
Ballwin $153,000
11992 Construction UNIVERSITY CITY SANITARY STORAGE
FACILITY (HAFNER CT)
University City $20,000,000
12244 Construction UPPER LADUE CREEK I/I REDUCTION (NE
QUAD OF S WARSON RD AND LADUE RD)
Ladue $375,000
12247 Construction UPPER MALINE TRUNK SANITARY RELIEF
PHASE IV SECTION C PUBLIC I/I REDUCTION
Berkeley $4,100,000
12249 Design Services UPPER MATTESE TRUNK SANITARY RELIEF
(THEISS RD TO LIBERTY TRAIL RD)
St. Louis County $1,433,000
12440 Design Services UPPER RDP (UNIVERSITY CITY) CSO
STORAGE TUNNEL
University City $4,000,000
12252 Design Services UR-11 BALSON AVENUE SANITARY RELIEF University City $1,000,000
12507 Design Services VALLEY PUBLIC I/I REDUCTION
(CLARKSON RD AND KEHRS MILL RD)
Clarkson Valley $110,000
12490 Construction VANCE RD PUMP STATION (P-472)
UPGRADES
Valley Park $4,000,000
11676 Design Services VILLA COUBLAY SANITARY RELIEF Creve Coeur $80,000
10794 Design Services WEBSTER GROVES TRUNK E SANITARY
RELIEF (SKME-628)
Brentwood $1,000,000
11212 Construction WHITE AND ROSALIE STORM SEWER
IMPROVEMENTS AND SEWER SEPARATION
Brentwood $2,733,000
12583 Construction WHITE BIRCH PUMP STATION (P-725)
REHABILITATION OR ELIMINATION
Hazelwood $1,160,000
12289 Design Services WINCHESTER DRIVE LATERAL SANITARY
RELIEF (ROLAND BLVD TO COLONIAL AVE)
Northwoods $140,000
12302 Design Services WW-2 AND WW-3 WARSON WOODS
SANITARY RELIEF
Warson Woods $760,000
12309 Construction YARNELL CREEK WEST I/I REDUCTION
(BOWLES AVE AND 141)
Unincorporated $32,000
FUND TOTAL: $391,687,000
GRAND TOTAL:$409,977,000