STORMWATER CONTINUED PROJECTS - FY18
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
11364 ALTHEA - ASTER STORM
SEWER
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION
AND REDESIGN. ANTICIPATE BOARD INTRODUCTION IN
FEBRUARY, 2018.
$829,000
10350 STONINGTON - GEORGIAN
ACRES STORM SEWER
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF FRONTENAC. ANTICIPATE BOARD
INTRODUCTION IN MAY, 2018.
$370,000
TOTAL: $1,199,000