WASTEWATER CONTINUED PROJECTS - FY19
PROJECT
NUMBER
PROJECT NAME REASON PROJECT CONTINUED COST
ESTIMATE
11790 CAULKS CREEK
FORCEMAIN (RIVER
VALLEY RD TO L-52)
PROJECT CONTINUED DUE TO COORDINATION WITH
PREVIOUS PHASE. ANTICIPATE BOARD INTRODUCTION IN
JUNE, 2018.
$15,000,000
12794 CITY LAKES STORAGE
MODIFICATIONS FOR CSO
CONTROL
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF ST. LOUIS. ANTICIPATE BOARD INTRODUCTION
IN OCTOBER, 2018.
$325,000
11155 DAMMERT AND
BROADWAY SANITARY
RELIEF (SKME-551) PART 2
PROJECT CONTINUED DUE TO COORDINATION WITH
COUNTY PARKS AND PORT AUTHORITY. ANTICIPATE
BOARD INTRODUCTION IN DECEMBER, 2018.
$4,500,000
12841 ENGELHOLM RELIEF
SANITARY STORAGE
FACILITY (ENGELHOLM
AVENUE AND ST.
CHARLES ROCK ROAD)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF PAGEDALE. ANTICIPATE BOARD INTRODUCTION
IN MAY, 2019.
$2,000,000
11737 FERGUSON SEWER RELIEF
SANITARY STORAGE
FACILITY (ELTORA AVE
AND PENNSYLVANIA AVE)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF PAGEDALE. ANTICIPATE BOARD INTRODUCTION
IN MAY, 2019.
$800,000
10018 FF-18 VILLA DORADO -
LACKLAND - PAGE
SANITARY RELIEF (ADIE
RD TO VILLA DORADO DR)
PROJECT CONTINUED DUE TO COORDINATION WITH
PREVIOUS PHASE. ANTICIPATE BOARD INTRODUCTION IN
JANUARY, 2019.
$7,075,000
11667 STERLING PLACE
SEPARATE SEWER I/I
REMOVAL PART 2
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN JULY, 2018.
$150,000
11667 STERLING PLACE
SEPARATE SEWER I/I
REMOVAL PART 2
PROJECT CONTINUED DUE TO EASEMENT ACQUISITION.
ANTICIPATE BOARD INTRODUCTION IN JULY, 2018.
$300,000
11992 UNIVERSITY CITY
SANITARY STORAGE
FACILITY (HAFNER CT)
PROJECT CONTINUED DUE TO COORDINATION WITH THE
CITY OF UNIVERSITY CITY. ANTICIPATE BOARD
INTRODUCTION IN MAY, 2019.
$3,700,000
TOTAL: $33,850,000