HomeMy Public PortalAboutO-Project Index By Municipality 17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
11593 BAXTER ROAD #273 AND #301 STORM SEWER STORMWATER BALLWIN 191
12096 BISSELL HILLS SANITARY RELIEF (ST CYR RD
TO LEETON AVE)
WASTEWATER BELLEFONTAINE
NEIGHBORS
7
12349 MEAD SANITARY RELIEF (LANDWEHR LN TO
HEMLOCK DR)
WASTEWATER BELLEFONTAINE
NEIGHBORS
62
12140 CSO - MARY AVENUE SOUTH OF MANCHESTER.
CSO INTERCEPTOR (I-132)/OUTFALL (L-106)
ELIMINATION
WASTEWATER BRENTWOOD 20
12363 NORTH WEBSTER CC, POCAHONTAS, SOUTH
BRENTWOOD I/I REDUCTION (S BRENTWOOD
BLVD AND MANCHESTER)
WASTEWATER BRENTWOOD 133
11420 SAXONHALL - VENUS - BRISTOL HALL STORM
SEWER
STORMWATER BRIDGETON 210
11592 SUMMER LAKE DR. #15637 STORM SEWER STORMWATER CHESTERFIELD 217
11729 CREVE COEUR CREEK SANITARY TRUNK
SEWER RELIEF PHASE VI (SKME-021)
WASTEWATER CHESTERFIELD 94
11789 CAULKS CREEK FORCEMAIN REHABILITATION WASTEWATER CHESTERFIELD 90
12248 CAULKS CREEK A PUMP STATION (P-750)
REPLACEMENT
WASTEWATER CHESTERFIELD 9
12152 E. WATSON SANITARY RELIEF (RUDSON LN TO
RICHVIEW DR)
WASTEWATER CRESTWOOD 24
12569 GRAVOIS TRUNK SANITARY STORAGE
FACILITY (PARDEE LN AND PARDEE RD)
WASTEWATER CRESTWOOD 46
12569 GRAVOIS TRUNK SANITARY STORAGE
FACILITY (PARDEE LN AND PARDEE RD)
WASTEWATER CRESTWOOD 111
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12325 LANG ROYCE SANITARY RELIEF (FARGO DR TO
FLORIDALE CT)
WASTEWATER DELLWOOD 49
12840 RIVERSIDE AND YARNELL SANITARY RELIEF
REPLACEMENT
WASTEWATER FENTON 138
13079 RIVERSIDE AND YARNELL SANITARY RELIEF
REHABILITATION
WASTEWATER FENTON 137
11791 UPPER MALINE TRUNK SANITARY RELIEF
PHASE IV SECTION B
WASTEWATER FERGUSON 142
12444 N CLARK AVE 49 SANITARY SEWER
REPLACEMENT
WASTEWATER FERGUSON 130
12179 FLORLAND SANITARY RELIEF PHASE II (N.
LINDBERGH BLVD TO MANRESA LN)
WASTEWATER FLORISSANT 25
12213 ST. JACQUES SANITARY RELIEF (ST. JACQUES
ST TO N LAFAYETTE ST)
WASTEWATER FLORISSANT 73
12786 N HIGHWAY 67 AT COLDWATER CREEK
SANITARY SEWER REPLACEMENT
WASTEWATER FLORISSANT 131
10863 HERMITAGE SANITARY RELIEF (SKME-615)WASTEWATER FRONTENAC 115
11224 TIMBER TRAIL - BRIAR RIDGE CHANNEL
IMPROVEMENTS
STORMWATER FRONTENAC 218
11239 STEEPLECHASE STORM SEWER
IMPROVEMENTS (FRONTENAC 3-3)
STORMWATER FRONTENAC 213
12767 QUEEN ANNE PLACE AT SAPPINGTON STORM
IMPROVEMENTS
STORMWATER GLENDALE 208
10210 CORONA PARK STORM SEWER PHASE 2B STORMWATER KIRKWOOD 194
11299 DICKENS AVENUE #470 STORM SEWER STORMWATER KIRKWOOD 197
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12073 ADAMS I/I REDUCTION (SOUTHEAST OF I-270
AND DOUGHERTY FERRY RD)
WASTEWATER KIRKWOOD 85
12223 SUGAR CREEK I/I REDUCTION (W ADAMS AVE
AND COUCH AVE)
WASTEWATER KIRKWOOD 139
12278 WESTBOROUGH - LUTHER - MERMOD PLACE I/I
REDUCTION (N KIRKWOOD RD TO I-44 AND
BERRY RD)
WASTEWATER KIRKWOOD 147
12186 FRONTENAC, WINDING RIDGE, DEER CREEK
HILL I/I REDUCTION (S QUAD I-64 AND
CLAYTON RD)
WASTEWATER LADUE 107
12938 WILLOW HILL STORM SEWER (LADUE 1614A)STORMWATER LADUE 219
11600 BROOKVALE TERRACE - PARKFIELD TERRACE
STORM IMPROVEMENTS
STORMWATER MANCHESTER 193
12334 LOWER BLACK CREEK AND HAMPTON CREEK
SANITARY RELIEF (DEER CREEK TRUNK TO
OXFORD DR) PHASE I
WASTEWATER MAPLEWOOD 58
10601 FF-16 SCHUETZ - MEADOWSIDE TO PAGE
SANITARY RELIEF
WASTEWATER MARYLAND
HEIGHTS
105
11016 ROLAND BLVD STORM SEWER STORMWATER NORTHWOODS 209
11026 WINCHESTER DRIVE 7120 BANK
STABILIZATION
STORMWATER NORTHWOODS 220
11476 KENWOOD - JUNE CREEK BANK
STABILIZATION
STORMWATER NORTHWOODS 201
12110 CANTERBURY DRIVE LATERAL SANITARY
RELIEF (NELSON DR TO CANTERBURY DR)
WASTEWATER NORTHWOODS 8
12191 ROLAND SANITARY RELIEF (NELSON DR TO
ROLAND BLVD)
WASTEWATER NORTHWOODS 70
11304 LACKLAND RD. - UCEYLE AVE. STORM SEWER STORMWATER OVERLAND 202
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
11306 LIBERTY AVE. 10000 BLOCK STORM SEWER STORMWATER OVERLAND 203
11450 MIRIAM AND BURNS STORM SEWER STORMWATER OVERLAND 206
12352 MIDLAND SANITARY RELIEF (MIDLAND BLVD
TO SIMS AVE)
WASTEWATER OVERLAND 63
12139 CSO - BRENTWOOD AND RED BUD AVE CSO
INTERCEPTOR (I-118)/OUTFALL (L-111)
ELIMINATION AND SEWER SEPARATION
WASTEWATER RICHMOND
HEIGHTS
19
12161 ELINOR AVE. TEMPORARY SANITARY
STORAGE FACILITY
WASTEWATER RICHMOND
HEIGHTS
103
12327 LAY RD - GALLERIA I/I REDUCTION (CLAYTON
RD AND LAY RD)
WASTEWATER RICHMOND
HEIGHTS
122
12201 SHREWSBURY SANITARY RELIEF SEWER AND
I/I REDUCTION (WEIL AVE AND I-44)
WASTEWATER SHREWSBURY 71
12511 MACKENZIE PUBLIC I/I REDUCTION
(RESURRECTION CEMETERY, WEHNER PARK,
KENRICK SEMINARY, AND NERINX HALL)
WASTEWATER SHREWSBURY 127
10070 HALL STREET STORM SEWERS STORMWATER ST. LOUIS CITY 184
10856 ERA AVE. 5800 BLOCK SEWER SEPARATION WASTEWATER ST. LOUIS CITY 104
11136 DEGIVERVILLE COMBINED SEWER
IMPROVEMENTS
WASTEWATER ST. LOUIS CITY 99
11142 JENNINGS STATION ROAD / NORTH BADEN
BASIN
WASTEWATER ST. LOUIS CITY 121
11621 SCHAEFFER PLACE 2000 BLOCK STORM SEWER STORMWATER ST. LOUIS CITY 211
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
11656 MALINE CREEK CSO BP 051 & 052 LOCAL
STORAGE FACILITY (CHAIN OF ROCKS DR TO
CHURCH DR)
WASTEWATER ST. LOUIS CITY 61
11656 MALINE CREEK CSO BP 051 & 052 LOCAL
STORAGE FACILITY (CHAIN OF ROCKS DR TO
CHURCH DR)
WASTEWATER ST. LOUIS CITY 128
11769 HARLEM - BADEN RELIEF PHASE IV (HEBERT)
(GOODFELLOW TO HAMILTON)
WASTEWATER ST. LOUIS CITY 114
11820 LMRDP CSO STORAGE TUNNEL (BROADWAY
TO RDP TUBES)
WASTEWATER ST. LOUIS CITY 55
12483 MISSISSIPPI FLOODWALL ORS PUMP STATIONS
REHABILITATION
WASTEWATER ST. LOUIS CITY 64
12483 MISSISSIPPI FLOODWALL ORS PUMP STATIONS
REHABILITATION
WASTEWATER ST. LOUIS CITY 129
12565 BISSELL & LEMAY WWTF FLUIDIZED BED
INCINERATORS
WASTEWATER ST. LOUIS CITY 1
12693 CITYSHED MITIGATION PROGRAM DESIGN
(CONTRACT A)
WASTEWATER ST. LOUIS CITY 11
12694 CITYSHED MITIGATION PROGRAM DESIGN
(CONTRACT B)
WASTEWATER ST. LOUIS CITY 12
12695 HARLEM BADEN RELIEF SYSTEM
IMPROVEMENT DESIGN (CONTRACT A)
WASTEWATER ST. LOUIS CITY 47
12702 OLIVE / WASHINGTON - GRAND TO
VANDEVENTER COMBINED SEWER RELIEF
WASTEWATER ST. LOUIS CITY 134
12828 BISSELL POINT WWTF REDUNDANT SLUDGE
ACCEPTANCE AND BELT FILTER PRESS
REPLACEMENT
WASTEWATER ST. LOUIS CITY 89
12836 CLARA 523 COMBINED SEWER IMPROVEMENT WASTEWATER ST. LOUIS CITY 91
12901 RDP FOULWATER SEWER GRIT CHAMBER
ELIMINATION (DEER CREEK)
WASTEWATER ST. LOUIS CITY 136
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12922 WATKINS CREEK PUMP STATION (P-101)
FORCEMAIN REPLACEMENT (COAL BANK RD
TO SPRING GARDEN DR)
WASTEWATER ST. LOUIS CITY 81
13041 LEMAY 1 PUMP STATION (P-301) SLUICE GATE
REPLACEMENT
WASTEWATER ST. LOUIS CITY 123
10766 STREAM FLOW GAUGE OPERATION AND
MAINTENANCE (USGS)
UNALLOCATED ST. LOUIS CITY
AND COUNTY
74
12017 INFRASTRUCTURE REPAIRS (REHABILITATION)
(2019) CONTRACT A
WASTEWATER ST. LOUIS CITY
AND COUNTY
117
12018 INFRASTRUCTURE REPAIRS (REHABILITATION)
(2019) CONTRACT B
WASTEWATER ST. LOUIS CITY
AND COUNTY
118
10282 MAINTENANCE YARD VEHICLE STORAGE
BUILDING (MINTERT)
STORMWATER ST. LOUIS
COUNTY
185
11514 CRESTWICK DRIVE #9733 AND 9741 STORM
SEWER (SUNSET HILLS 11)
STORMWATER SUNSET HILLS 195
12296 WOODS MILL SANITARY RELIEF (I-64 TO
BROOK MILL LN)
WASTEWATER TOWN AND
COUNTRY
148
10380 BROGAN DALE CIRCLE STORM SEWER STORMWATER UNINCORPORAT
ED
192
11018 PATRINA COURT BANK STABILIZATION STORMWATER UNINCORPORAT
ED
207
11033 STONE HILL DR 4701 STORM SEWER STORMWATER UNINCORPORAT
ED
214
11392 BARKMAN STORM SEWER IMPROVEMENTS STORMWATER UNINCORPORAT
ED
190
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
11488 MAR ANN CT. #9819 STORM IMPROVEMENT STORMWATER UNINCORPORAT
ED
204
11511 SCHUETZ ROAD AND WILLOW BROOK COVE
STORM SEWERS
STORMWATER UNINCORPORAT
ED
212
11594 MARTYRIDGE CT. #4307 STORM SEWER
(MGMB-170)
STORMWATER UNINCORPORAT
ED
205
11647 HOFFMEISTER - PARDELLA STORM SEWER
IMPROVEMENTS
STORMWATER UNINCORPORAT
ED
199
11669 SUB-TRUNK #3 SANITARY RELIEF (MURIEL DR
TO JENNER LN)
WASTEWATER UNINCORPORAT
ED
77
11711 JEFFERSON BARRACKS TUNNEL (LEMAY WWTP
TO MARTIGNEY PS)
WASTEWATER UNINCORPORAT
ED
48
11711 JEFFERSON BARRACKS TUNNEL (LEMAY WWTP
TO MARTIGNEY PS)
WASTEWATER UNINCORPORAT
ED
120
11724 COLDWATER SANITARY RELIEF SECTION B, C
& D - SECTION B REHABILITATION
WASTEWATER UNINCORPORAT
ED
14
11766 GRAVOIS TRUNK (WHITECLIFF TO RDP)
SANITARY RELOCATION PHASE VI (BUCKLEY
RD TO UNION RD)
WASTEWATER UNINCORPORAT
ED
110
11817 LEMAY NO. 3 PUMP STATION AND FORCE MAIN WASTEWATER UNINCORPORAT
ED
50
12075 AFFTON I/I REDUCTION (HANOVER,
HILDESHEIM-WEBER RD, SEIBERT, AND
HAMBURG)
WASTEWATER UNINCORPORAT
ED
86
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12126 COLDWATER UPSTREAM PUMP STATION (P-180)
STORAGE
WASTEWATER UNINCORPORAT
ED
93
12142 DACEY BRANCH SANITARY RELIEF (BELLA
CLARE DR TO PRIOR DR)
WASTEWATER UNINCORPORAT
ED
21
12154 EARTH CITY LAKE FRONT NORTH PUMP
STATION (P-711) REPLACEMENT
WASTEWATER UNINCORPORAT
ED
100
12155 EARTH CITY SHORELINE PUMP STATION (P-704)
REPLACEMENT
WASTEWATER UNINCORPORAT
ED
101
12180 FORDER SANITARY INTERCONNECTION
(FORDER RD TO RINGER RD)
WASTEWATER UNINCORPORAT
ED
106
12221 SUB-TRUNK #2 SANITARY RELIEF
(BIRMINGHAM CT TO COVE LN)
WASTEWATER UNINCORPORAT
ED
76
12235 TOWNE SOUTH AND BRUNSTON I/I REDUCTION
(AMBS RD AND TOWNE CENTRE DR)
WASTEWATER UNINCORPORAT
ED
140
12239 TULANE-WILBUR OUTFALL SANITARY RELIEF
SEWER (WEBER RD TO HILDESHEIM AVE)
WASTEWATER UNINCORPORAT
ED
78
12253 VALCOUR AND BURLINGTON RR SANITARY
RELIEF AND I/I REDUCTION (VALCOUR RD AND
WATSON RD)
WASTEWATER UNINCORPORAT
ED
143
12255 LOWER MERAMEC WWTF EXPANSION PHASE II WASTEWATER UNINCORPORAT
ED
60
12372 GREEN PARK AND LAKESHIRE I/I REDUCTION
(TESSON FERRY RD AND GREEN PARK RD)
WASTEWATER UNINCORPORAT
ED
112
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12491 WATKINS CREEK PUMP STATION (P-101)
UPGRADES
WASTEWATER UNINCORPORAT
ED
82
12499 LOWER MERAMEC WWTF CORROSION AND
HUMIDITY CONTROL IMPROVEMENTS
WASTEWATER UNINCORPORAT
ED
126
12504 COLDWATER CREEK WWTF FINAL CLARIFIERS
REPLACEMENT
WASTEWATER UNINCORPORAT
ED
13
12510 GREEN PARK AND LAKESHIRE PUBLIC I/I
REDUCTION (TESSON FERRY RD AND GREEN
PARK RD)
WASTEWATER UNINCORPORAT
ED
113
12721 LEMAY WWTF REDUNDANT WATER SERVICE WASTEWATER UNINCORPORAT
ED
54
12721 LEMAY WWTF REDUNDANT WATER SERVICE WASTEWATER UNINCORPORAT
ED
125
12914 GLEN EAGLES PUMP STATION (P-189)
RELOCATION / REPLACEMENT
WASTEWATER UNINCORPORAT
ED
108
11993 82ND STREET TO I-170 SANITARY RELIEF (UR-
08, UR-09)
WASTEWATER UNIVERSITY
CITY
84
12440 UPPER RDP (UNIVERSITY CITY) CSO STORAGE
TUNNEL
WASTEWATER UNIVERSITY
CITY
79
12490 VANCE RD PUMP STATION (P-472) UPGRADES WASTEWATER VALLEY PARK 80
13072 GRAND GLAIZE WWTF FLOODWALL
PROTECTION
WASTEWATER VALLEY PARK 45
10496 GRAVOIS TRUNK (WHITECLIFF TO RDP)
SANITARY REHABILITATION (FANNIE AVE TO
PARDEE LANE)
WASTEWATER VARIOUS 109
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
11065 DEER CREEK WATERSHED INITIATIVE STORMWATER VARIOUS 196
11109 LOWER & MIDDLE RDP CSO CONTROLS
SYSTEM IMPROVEMENTS (WATERSHED
CONSULTANT)
WASTEWATER VARIOUS 56
11109 LOWER & MIDDLE RDP CSO CONTROLS
SYSTEM IMPROVEMENTS (WATERSHED
CONSULTANT)
WASTEWATER VARIOUS 57
11144 BISSELL - COLDWATER - MISSOURI - MERAMEC
SANITARY SYSTEM IMPROVEMENTS
(WATERSHED CONSULTANT)
WASTEWATER VARIOUS 5
11144 BISSELL - COLDWATER - MISSOURI - MERAMEC
SANITARY SYSTEM IMPROVEMENTS
(WATERSHED CONSULTANT)
WASTEWATER VARIOUS 6
11145 LEMAY SANITARY SYSTEM IMPROVEMENTS
(WATERSHED CONSULTANT)
WASTEWATER VARIOUS 52
11145 LEMAY SANITARY SYSTEM IMPROVEMENTS
(WATERSHED CONSULTANT)
WASTEWATER VARIOUS 53
11146 CSO VOLUME REDUCTION GREEN
INFRASTRUCTURE
WASTEWATER VARIOUS 95
11151 CONSTRUCTION MANAGEMENT SERVICES -
TANK/TREATMENT/PUMP STATION FACILITIES
WASTEWATER VARIOUS 17
11152 CONSTRUCTION MANAGEMENT SERVICES -
LOWER AND MIDDLE RDP TUNNEL FACILITIES
WASTEWATER VARIOUS 15
11153 RDP TRIBUTARIES & UPPER RDP CSO
CONTROLS & LOWER MERAMEC SYSTEM
IMPROVEMENTS (WATERSHED CONSULTANT)
WASTEWATER VARIOUS 67
11153 RDP TRIBUTARIES & UPPER RDP CSO
CONTROLS & LOWER MERAMEC SYSTEM
IMPROVEMENTS (WATERSHED CONSULTANT)
WASTEWATER VARIOUS 68
11701 PUMP STATION REPLACEMENT PROJECTS
(PHASE I) (P-708)
WASTEWATER VARIOUS 65
11701 PUMP STATION REPLACEMENT PROJECTS
(PHASE I) (P-708)
WASTEWATER VARIOUS 135
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
11731 DEER CREEK SANITARY TUNNEL (CLAYTON RD
TO RDP)
WASTEWATER VARIOUS 23
11731 DEER CREEK SANITARY TUNNEL (CLAYTON RD
TO RDP)
WASTEWATER VARIOUS 98
11746 LOWER MERAMEC RIVER SYSTEM
IMPROVEMENTS - BAUMGARTNER TO FENTON
WWTF TUNNEL
WASTEWATER VARIOUS 59
11760 GENERAL SERVICES AGREEMENT - FACILITY &
SEWER DESIGN (2016)
WASTEWATER VARIOUS 28
11826 CONSTRUCTION MANAGEMENT SERVICES -
LOWER MERAMEC AND DEER CREEK TUNNELS
WASTEWATER VARIOUS 16
11984 UNIVERSITY CITY I/I REDUCTION - EAST (UR-08
AND UR-09)
WASTEWATER VARIOUS 141
11999 CCTV INSPECTION AND PHYSICAL INSPECTION
OF SEWERS (2017)
WASTEWATER VARIOUS 10
12003 STREAM FLOW WATER QUALITY SAMPLING
(2017)
UNALLOCATED VARIOUS 75
12005 RADAR RAINFALL DATA (2017)WASTEWATER VARIOUS 66
12009 INFRASTRUCTURE REPAIRS (WASTEWATER)
(2019)
WASTEWATER VARIOUS 119
12026 BISSELL - COLDWATER - MISSOURI - MERAMEC
PUBLIC I/I REDUCTION (2019) CONTRACT C
WASTEWATER VARIOUS 88
12027 BISSELL - COLDWATER - MISSOURI - MERAMEC
PUBLIC I/I REDUCTION (2020) CONTRACT C
WASTEWATER VARIOUS 4
12029 BISSELL - COLDWATER - MISSOURI - MERAMEC
PUBLIC I/I REDUCTION (2019) CONTRACT A
WASTEWATER VARIOUS 87
12030 BISSELL - COLDWATER - MISSOURI - MERAMEC
PUBLIC I/I REDUCTION (2020) CONTRACT B
WASTEWATER VARIOUS 3
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12033 BISSELL - COLDWATER - MISSOURI - MERAMEC
PUBLIC I/I REDUCTION (2020) CONTRACT A
WASTEWATER VARIOUS 2
12038 LEMAY PUBLIC I/I REDUCTION (2019)
CONTRACT D
WASTEWATER VARIOUS 124
12042 DEER CREEK PUBLIC I/I REDUCTION (2019)
CONTRACT A
WASTEWATER VARIOUS 97
12057 LEMAY PUBLIC I/I REDUCTION (2020)
CONTRACT A
WASTEWATER VARIOUS 51
12125 COLDWATER SOUTHWEST SUBWATERSHED I/I
REDUCTION (ST. CHARLES ROCK RD AND
ASHBY RD)
WASTEWATER VARIOUS 92
12382 GENERAL SERVICES AGREEMENT - PROPERTY
APPRAISAL (2018) CONTRACT A
UNALLOCATED VARIOUS 35
12383 GENERAL SERVICES AGREEMENT - PROPERTY
APPRAISAL (2018) CONTRACT B
UNALLOCATED VARIOUS 36
12384 GENERAL SERVICES AGREEMENT - PROPERTY
APPRAISAL (2018) CONTRACT C
UNALLOCATED VARIOUS 37
12385 GENERAL SERVICES AGREEMENT - PROPERTY
APPRAISAL (2018) CONTRACT D
UNALLOCATED VARIOUS 38
12386 GENERAL SERVICES AGREEMENT -
CONSTRUCTION MANAGEMENT (2019)
WASTEWATER VARIOUS 27
12388 GENERAL SERVICES AGREEMENT -
GEOTECHNICAL (2018) CONTRACT A
WASTEWATER VARIOUS 31
12389 GENERAL SERVICES AGREEMENT -
GEOTECHNICAL (2018) CONTRACT B
WASTEWATER VARIOUS 32
12390 GENERAL SERVICES AGREEMENT -
GEOTECHNICAL (2018) CONTRACT C
WASTEWATER VARIOUS 33
12396 GENERAL SERVICES AGREEMENT - FACILITY &
SEWER DESIGN (2018) CONTRACT A
WASTEWATER VARIOUS 29
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12398 GENERAL SERVICES AGREEMENT - SEWER AND
CHANNEL DESIGN (2019)
WASTEWATER VARIOUS 39
12408 GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2018) CONTRACT A
WASTEWATER VARIOUS 40
12409 GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2018) CONTRACT B
WASTEWATER VARIOUS 41
12410 GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2018) CONTRACT C
WASTEWATER VARIOUS 42
12411 GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2018) CONTRACT D
WASTEWATER VARIOUS 43
12412 GENERAL SERVICES AGREEMENT - SURVEY
SERVICES (2018) CONTRACT E
WASTEWATER VARIOUS 44
12441 RDP TRIBUTARIES (DEER CREEK) CSO TUNNEL WASTEWATER VARIOUS 69
12471 DC-02 & DC-03 SANITARY RELIEF (BRENTWOOD
BLVD TO CONWAY RD) PHASE II
WASTEWATER VARIOUS 96
12472 DC-02 & DC-03 SANITARY RELIEF (BRENTWOOD
BLVD TO CONWAY RD) PHASE III AND PHASE
IV
WASTEWATER VARIOUS 22
12515 EASEMENT ACQUISITION FOR WASTEWATER
PROJECTS (2019)
WASTEWATER VARIOUS 102
12519 DEER CREEK OMCI STORMWATER DESIGN
(CONTRACT B)
STORMWATER VARIOUS 181
12520 DEER CREEK OMCI STORMWATER DESIGN
(CONTRACT C)
STORMWATER VARIOUS 182
12674 STORMWATER INFRASTRUCTURE REPAIR /
REPLACEMENT - DISTRICTWIDE (2019)
STORMWATER VARIOUS 215
12678 STORMWATER INFRASTRUCTURE REPAIR /
REPLACEMENT - ORIGINAL BOUNDARY (2019)
STORMWATER VARIOUS 216
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
12682 EASEMENT ACQUISITION FOR STORMWATER
PROJECTS (2019)
STORMWATER VARIOUS 198
12687 STORMWATER STREAMBANK STABILIZATION
DESIGN (CONTRACT B)
STORMWATER VARIOUS 189
12688 STORMWATER INFRASTRUCTURE
IMPROVEMENT DESIGN (CONTRACT A)
STORMWATER VARIOUS 186
12689 STORMWATER INFRASTRUCTURE
IMPROVEMENT DESIGN (CONTRACT B)
STORMWATER VARIOUS 187
12690 STORMWATER INFRASTRUCTURE
IMPROVEMENT DESIGN (CONTRACT C)
STORMWATER VARIOUS 188
12716 GENERAL SERVICES AGREEMENT - WATER
QUALITY GENERAL SUPPORT (2017)
STORMWATER VARIOUS 183
12720 CRITICAL INFRASTRUCTURE ASSESSMENT
(2017)
WASTEWATER VARIOUS 18
12759 FLOW METERING AND MONITORING (2017)WASTEWATER VARIOUS 26
12894 GENERAL SERVICES AGREEMENT - FACILITY &
SEWER DESIGN (2018) CONTRACT B
WASTEWATER VARIOUS 30
12896 INFRASTRUCTURE REPAIRS (FACILITIES) (2019)WASTEWATER VARIOUS 116
13043 INFRASTRUCTURE REPAIRS (REHABILITATION)
STORMWATER (2019)
STORMWATER VARIOUS 200
13044 GENERAL SERVICES AGREEMENT -
LANDSCAPE DESIGN (2019)
UNALLOCATED VARIOUS 34
11677 WEBSTER GROVES TRUNK E SANITARY
REHABILITATION AND I/I REDUCTION PHASE III
WASTEWATER WEBSTER
GROVES
144
17 January 2018
PROJECT INDEX BY MUNICIPALITY FOR FISCAL YEAR - FY19
PROJECT
NUMBER
PROJECT NAME PROJECT
TYPE
MUNICIPALITY PAGE
NUMBER
11678 WEBSTER GROVES TRUNK E SANITARY
REHABILITATION AND I/I REDUCTION PHASE IV
PART 3
WASTEWATER WEBSTER
GROVES
145
11678 WEBSTER GROVES TRUNK E SANITARY
REHABILITATION AND I/I REDUCTION PHASE IV
PART 3
WASTEWATER WEBSTER
GROVES
146
11679 WEST LOCKWOOD SANITARY RELIEF WASTEWATER WEBSTER
GROVES
83
12208 SPRING AVE SANITARY RELIEF (YEATMAN AVE
TO DALE AVE)
WASTEWATER WEBSTER
GROVES
72
12362 NORTH FOREST AND BROOKSIDE I/I
REDUCTION (SUMMIT AVE AND MARSHALL
AVE)
WASTEWATER WEBSTER
GROVES
132