INTRODUCTION
Nonpoint Source Pollution has a great impact on the quality of surface waters. Stormwater
best management practices (BMPs) help control nonpoint source pollution through various
techniques that intercept, filter, and treat runoff from developed areas. The Metropolitan St.
Louis Sewer District (MSD) recognizes that, over time, new structural BMPs will be
developed, including many with proprietary designs. This document provides additional
guidance concerning the use of proprietary devices within MSD’s boundaries.
MSD has adopted regulations (“Rules and Regulations and Engineering Design
Requirements for Sanitary Sewer and Stormwater Drainage Facilities,” February 2006) that
represent a more comprehensive approach to stormwater management, and include water
quality standards that must be met at development and redevelopment sites. These
standards, found in Section 4 of the regulations, apply to any construction activity
disturbing, individually or in aggregate, 1 acre or more. While providing incentives and
preference for nonstructural practices, these standards also address the design of structural
BMP’s to mitigate water quality and channel stability impacts.
BMP DESIGN
While MSD regulations specify and allow certain structural BMP’s, for specific guidance
regarding structural BMPs, reference is made to the Maryland Department of the
Environment’s (MDE), April 2000, “Stormwater Design Manual, Vol. I and Vol. II.” This
publication outlines the selection, design and construction of various structural BMPs. The
structural BMPs allowed for stormwater quality control are divided into five general
categories as shown in Table 1.
Jan. 2008, Rev Jan. 2009 (blue) 2
TABLE 1: STRUCTURAL BMPs ALLOWED FOR “STAND ALONE” WATER
QUALITY TREATMENT BY MSD
According to section 4.080.05 of MSD’s regulations, to be considered an effective BMP for
stand-alone treatment of water quality, a design shall:
1. Capture and treat the water quality volume (stormwater quality design storm).
2. Remove 80% of the total suspended solids (TSS).
3. Have an acceptable longevity rate in the field.
MSD will consider for review and approval manufactured or proprietary BMPs meeting the
applicable requirements, but not included in Table 1. MSD reserves the right to add, modify
or delete approval criteria as deemed appropriate and without prior notice. Future criteria or
requirements may also change due to any future changes in MSD’s MS4 permit.
PROPRIETARY BMPS
Definition
A proprietary BMP is a pre-fabricated stormwater treatment structure utilizing settling,
filtration, absorptive/adsorptive materials, vortex separation, vegetative components, and/or
other appropriate technology to remove pollutants from storm runoff. Proprietary BMPs are
intended to capture sediments, metals, hydrocarbons, floatables, and/or other pollutants in
stormwater runoff before being conveyed to a storm sewer system, or waterbody. A
proprietary BMP is generally adequate for small drainage areas that contain a predominance
of impervious cover that is likely to contribute high hydrocarbon and sediment loadings,
such as small parking lots and gas stations. For larger sites, multiple BMPs may be
necessary.
A manufactured treatment device must also have an appropriate maintenance plan. If
privately owned, the device shall be protected by a reserved area, or other legal measures
that prevent its neglect, adverse alteration, and/ or removal.
Stormwater Ponds
· Micropool Extended-Detention (ED)
Ponds
· Wet Ponds
· Wet ED Ponds
· Multiple Pond System
· “Pocket Ponds”
Stormwater Wetlands
· Shallow Wetland
· ED Shallow Wetland
· Pond/Wetland System
· “Pocket Wetland”
Stormwater Infiltration
· Infiltration Trench
· Infiltration Basin
Stormwater Filtering System
· Surface Sand Filters
· Underground Sand Filters
· Perimeter Sand Filters
· Organic Filters
· Pocket Sand Filters
· Bioretention
Open Channel Systems
· Dry Swale
· Wet Swale
Jan. 2008, Rev Jan. 2009 (blue) 3
DESIGN CRITERIA
The basic design parameters for a proprietary BMP will depend on the techniques it employs
to remove particulate and dissolved pollutants from runoff. In addition, a proprietary BMP
shall have a certified pollutant removal (TSS removal) rate. To achieve its assigned TSS
removal rate, a proprietary BMP must treat the runoff generated by the stormwater quality
“design storm.” Depending on the device’s pollutant removal technique(s), the primary
design parameter for a proprietary BMP will normally be either the peak flow rate (WQf)
and/or total runoff volume from the stormwater quality design storm (WQv). Devices that
convey inflow with little or no storage and provide pollutant removal only through such
techniques as vortex flow, filtration, and/or absorption are generally based on the peak flow
rate of the stormwater quality design storm runoff. Devices that store and convey runoff
more slowly and provide pollutant removal through such techniques as sedimentation and/or
filtration may be based on the water quality volume.
In the selection of BMPs it should be noted that redevelopment projects, given existing site
constraints, often pose significant challenges not encountered in new development.
Additionally, different types of sites may produce different pollutant characteristics. Given
the above it is reasonable that different sites may necessitate the use of different types of
BMPs and what is suited for one site may not be suited for another. With this in mind MSD
will consider the approval of proprietary BMPs for the following Use Level Designations.
TABLE 2: PROPRIETARY BMP USE LEVEL DESIGNATIONS
USE LEVEL DESIGNATIONS DEFINITION / USES
General Use Level (GUL) BMPs approved at this level may be used at all types of
sites.
Redevelopment Use Level (RUL) BMPs approved at this level may be used at non-
residential redevelopment sites (i.e., total property area)
less than five (5) acres in size.
Highway Use Level (HUL) BMPs approved at this level may be used on public
highway and public road projects.
Provisional Use Level (PUL) BMPs approved at this level may be used only according
to specific “provisions” outlined in the approval. This
designation is intended only for use in certain and specific
instances.
Regardless of the Use Level Designation, it should be noted that all BMPs should be utilized
according to the applicable requirements of MSD regulations. Additionally, underground
structural practices are not allowed on residential type projects. A site (i.e., total property
area) is considered a redevelopment site if at least 20% of the existing site was impervious
coverage as of January 15, 2000. Development of remaining pervious area(s) in succession
will not be considered as redevelopment.
The design of all proprietary BMPs conforming to the GUL designation must be based upon
the water quality volume. Proprietary BMPs conforming to the RUL, HUL and PUL
designations may be based upon either the water quality volume (WQv) or the water quality
flow rate (WQf). Procedures for calculating WQv are included in the MSD regulations, and
procedures for calculating WQf are provided in Appendix D.10 of the Maryland Stormwater
Design Manual.
Jan. 2008, Rev Jan. 2009 (blue) 4
In general, proprietary BMPs must be placed off-line. With the off-line BMP configuration,
some of the runoff from storms larger than the stormwater quality design storm bypasses the
device through an upstream diversion structure. This not only reduces the size of the
required device overflow, but also reduces the device’s long-term pollutant loading and
associated maintenance, and reduces the threat of resuspension and release of trapped
material by larger storm inflows.
The hydraulic design of all proprietary BMPs must consider tailwater effects of downstream
waterways or facilities. This includes instances where the lowest invert in the outlet or
overflow structure is below the flood hazard area design flood elevation and/or the 15-year
20-minute flood elevation of the receiving stream/ system and possibly the tailwater
elevation of the downstream detention storage.
All subsurface or underground BMPs must be designed for HS-20 traffic loading at the
surface. All joints and connections must be watertight and durable. The manhole cover or
other approved permanent marker for the treatment device must clearly indicate that it is a
pollutant-trapping device. Sufficient and suitable access must be provided for each chamber
in the device for inspection and maintenance activities. This must include adequate
clearance from adjacent structures to allow for placement and operation of maintenance
equipment. All castings shall be standard castings where possible, or if not standard must be
captive. Where applicable, all other materials and devices used in the BMP shall be in
general accordance with the latest edition of the MSD Standard Construction Specifications
for Sewers and Drainage Facilities.
PROPRIETARY BMP PERFORMANCE CERTIFICATION
New stormwater BMP products keep appearing in the marketplace. Yet the availability of
good data and information on some of these technologies is scarce. To address this problem
MSD requires specific performance for each Use Level Designation and specific support
and certification for that performance claim. Again, the required performance, or
certification of the performance required, may vary according to the Use Level Designation.
The minimum types of performance required and certifications required are outlined in
Table 3, Proprietary BMP Performance Claims and Certification. Additional requirements
may be set forth on an individual basis as dictated by MSD standards, or specific product or
site requirements. Loss of required certifications may also result in loss of MSD approval.
Third party certification of all performance claims is required. This certification of
performance may be provided by the New Jersey Department of Environmental Protection
(NJDEP) or by the Washington State Department of Ecology. The NJDEP certification
utilizes the New Jersey Center for Advanced Technology (NJCAT) verification as
conducted according to the Technology Acceptance and Reciprocity Partnership (TARP)
Protocol. Washington State Department of Ecology utilizes the Technology Assessment
Protocol - Ecology (TAPE). In addition to all certifications and laboratory test data, all
performance claims should be supported by field test data.
Jan. 2008, Rev Jan. 2009 (blue) 5
TABLE 3: PROPRIETARY BMP PERFORMANCE REQUIREMENTS AND CERTIFICATIONS
USE LEVEL
DESIGNATION
PERFORMANCE REQUIREMENT CERTIFICATION REQUIREMENT
General Use Level
(GUL)
The BMP must be able to achieve a removal rate
of 80% Total Suspended Solids (TSS) from
stormwater runoff generated by the stormwater
quality design storm.
Final certification of proprietary BMP
performance claims by the NJDEP in
accordance with TARP Tier II protocol,
or General Use Level Designation for
Basic Treatment by the Washington
Department of Ecology.
Redevelopment Use
Level (RUL)
BMP must sequester all non-aqueous phase
hydrocarbon, scum, and floating debris and
achieve an instantaneous removal rate of 80%
TSS for the storm water quality design storm.
TSS removal efficiency shall be based on an
influent concentration of <300 mg/L and OK-
110 particle size distribution.
Interim certification of proprietary BMP
performance claims by the NJDEP in
accordance with a NJCAT technology
performance verification, or General Use
Level Designation for Pretreatment by the
Washington Department of Ecology.
Highway Use Level
(HUL)
BMP must sequester all non-aqueous phase
hydrocarbon, scum, and floating debris and
achieve an instantaneous removal rate of 80%
TSS for the storm water quality design storm.
TSS removal efficiency shall be based on an
influent concentration of <450 mg/L and OK-
110 particle size distribution.
Interim certification of proprietary BMP
performance claims by the NJDEP in
accordance with a NJCAT technology
performance verification, or General Use
Level Designation for Pretreatment by the
Washington Department of Ecology.
Provisional Use Level
(PUL)
A specific Total Suspended Solids (TSS)
removal rate applicable to the use requested is
required.
Third party documentation from a public
agency or testing agency confirming
removal efficiency is required.
MSD may allow use of some RUL approved proprietary or manufactured BMPs at
redevelopment sites larger than 5 acres, and these BMPs would be provided the PUL
designation in addition to the RUL designation. (However, the paragraphs below will also be
strictly required in concert with this enlargement.) The additional PUL designation will be
limited to proprietary devices, such as proprietary filters, that have conditional interim
certification of proprietary BMP performance claims by the NJDEP in accordance with
NJCAT technology performance verification program. These devices must also be actively
pursuing field testing in accordance with NJCAT Tier II protocol and final certification by
the NJDEP.
Key provisions of the PUL approval will include a firm due date for obtaining the final
certification and some form of annual reporting during the testing period. Annual reporting
shall include results from the TARP monitoring or a letter from NJCAT/NJDEP stating the
results of the quarterly performance monitoring reports. Annual reporting will allow the
manufacturer and MSD to identify any performance or operational issues during TARP
testing and address them or revoke the PUL designation. Also, given the uncertainty of
design flow rates tested in the laboratory versus actual flow rates encountered in the field,
MSD may require for devices not holding Tier II certification a reduced allowable flow rate
in the design of the BMP. In no case will the PUL approval date extend beyond the
expiration date of the current MSD Small MS4 permit. If final certification is not obtained
by the due date, MSD may revoke BMP approval from that date forward.
Jan. 2008, Rev Jan. 2009 (blue) 6
For larger site development projects, MSD does not believe the sole use of a BMP filter
device is sufficient to addresses a site’s obligation to manage site stormwater to the
maximum extent practicable (MEP). These devices do not minimize stormwater pollutant
loading at the point of generation nor do they mimic a site’s natural runoff condition (i.e.,
these devices accept whatever loading and pollutants are created). For these larger sites,
MSD’s goal is that the overall stormwater management plan also includes practices that
minimize directly connected impervious areas, stormwater pollution, and stormwater runoff.
While MEP is not a required percentage or amount, the goal is that the volume of runoff
treated by proprietary filters will be less than or equal to the volume of runoff managed by
other practices that minimize stormwater pollution and runoff (with an emphasis on non-
structural methods). In this way, proprietary devices should be treated as a supplementary
(rather than a primary) means of meeting MSD’s Small MS4 permit requirements. Table 4
below summarizes how this policy would be generally applied to redevelopment sites.
TABLE 4: RESTRICTIONS ON PROPRIETARY BMP USE AT REDEVELOPMENT SITES
SITE SIZE DISTURBANCE
SIZE
RESTRICTION
<5 ACRES <5 ACRES RUL or GUL approved devices may be solely used
>5 ACRES <2.5 ACRES RUL+PUL or GUL approved device may be solely used
>5 ACRES >2.5 ACRES RUL+PUL or GUL approved devices shall supplement other practices
that minimize stormwater pollution and runoff to the MEP.
MAINTENANCE
Effective performance of any BMP requires regular and effective maintenance. The
following requirements must be included in a proprietary BMPs maintenance plan.
General Maintenance
All proprietary BMPs should be inspected and maintained in accordance with
manufacturer’s instructions or MSD’s requirements (if more stringent). In addition, all
device components expected to receive and/or trap debris and sediment must be inspected
for clogging and excessive debris and sediment accumulation at least seasonally or annually,
as appropriate. Disposal of debris, trash, sediment, slurry, and other waste material shall be
done at suitable disposal/recycling sites and in compliance with all applicable local, state,
and federal regulations. Generally, for devices with the RUL and HUL designation confined
space entry requirements shall not be required to complete maintenance of the BMP.
Vegetation
In those BMPs utilizing vegetation, the trimming of vegetation must be performed on an
appropriate and regular schedule based on specific site conditions. Vegetated areas must be
inspected at least annually for erosion and scour as well as unwanted growth, which should
be removed with minimum disruption to the planting soil bed and remaining vegetation. All
use of fertilizers, mechanical treatments, pesticides, herbicides, and other means to ensure
optimum vegetation health in devices utilizing vegetation should not compromise the
intended purpose of the device. All vegetation deficiencies should be addressed in a timely
manner and without the use of fertilizers and pesticides whenever possible.
Jan. 2008, Rev Jan. 2009 (blue) 7
Structural Components
All structural components must be inspected for hardening, cracking, subsidence, spalling,
erosion, and deterioration at least annually, and be kept in good repair.
Other Maintenance Criteria
The maintenance plan must indicate the maximum level of oil, sediment, and debris
accumulation allowed before removal is required. These levels should then be monitored
during device inspections to help determine the need for removal and other device
maintenance. More frequent monitoring should be done initially until a pattern of stability,
performance and effectiveness is established. Logs and other records of inspection,
maintenance and repair shall be kept for the previous three (3) full years.
PROPRIETARY BMP REVIEW
MSD shall consider proprietary BMPs for approval and use, only if the BMP meets all the
applicable performance criteria. To facilitate the product review process a detailed
application format is attached at the end of this document and labeled as a Proprietary BMP
Application. Manufacturers should submit complete application packets to MSD for review
and approval. Depending upon the results of this application process, proprietary BMPs
may be approved for use on projects within the District boundaries.
Five (5) completed copies of the Proprietary BMP Application shall be submitted to:
Metropolitan St. Louis Sewer District
2350 Market Street
St. Louis, MO 63103-2555
Attn: Engineering Division/ Development Plan Review/ BMP Selection Committee
Applications shall be placed in a three (3) ring binder 8 1/2” x 11” sheets should be used
whenever possible. Larger sheets should be firmly attached or included in folders.
Different sections of the application should be clearly indicated.
Applications should include all data requested and be arranged in the indicated sections and
use a readily readable style. Different sections of the application should be clearly indicated
from each other. Note that information beyond that requested, differing formats, and “boiler
plate” inserts are not required nor desired.
Any questions regarding the Proprietary BMP Application should be directed to the
attention of MSD’s Development Plan Review Section. All applications will be reviewed in
the order that they are received. MSD reserves the right to request additional information
not included. Approvals for proprietary BMPs shall be for limited duration only (generally a
period of two years) and MSD reserves the right to periodically review and revise all
applications and approvals.
Jan. 2008, Rev Jan. 2009 (blue) 8
FIELD MONITORING REQUIREMENTS
Regardless of previous certifications or field testing MSD will require field monitoring of all
types of proprietary BMPs installed in the service area. Generally, this monitoring will
apply to the first of each type of unit installed in the service area. Typical monitoring
guidelines are as follows:
1. A manufacturer’s or vendor’s representative must be onsite during the proprietary
BMP installation to ensure the product’s installation requirements are met.
2. Shop drawings indicating elevations of flowlines, weirs, pipe inverts, etc. will be
required prior to installation.
3. The manufacturer or vendor must arrange for an as-built survey to the proprietary
BMP to be performed by a Missouri-registered Professional Land Surveyor once the
device has been installed, and prior to any testing or monitoring.
4. The manufacturer or vendor must perform quarterly inspections of the proprietary
BMP during its’ first year of operation, which will include visual inspections and
quantitative analysis of the service’s Sediment Removal Efficiency, especially as
compared to the design efficiency. MSD requests to be invited to these inspections
to further enhance familiarity and understanding of the device.
5. Formal reports shall be submitted to MSD, at the time of as-built submittal and at
each quarterly inspection. The reports shall include summaries, quantitative analysis
mentioned in item 4, photographs of the structure inlet, internal conditions of the
structure, the filters, and outfall conditions, etc. The reports shall also evaluate the
performance of the owner’s adherence to the approved maintenance program, and
offer suggestions for any areas of improvement.
Jan. 2008, Rev Jan. 2009 (blue) 9
REFERENCES
Metropolitan St. Louis Sewer District:
http://www.stlmsd.com
Maryland Department of the Environment, Water Programs
http://www.mde.state.md.us/Programs/WaterPrograms/index.asp
Maryland Department of the Environment Storm water Design Manual:
http://www.mde.state.md.us/Programs/WaterPrograms/SedimentandStormwater/stor
mwater_design/index.asp
New Jersey Department of Environmental Protection, Bureau of Sustainable Communities
and Innovative Technologies
http://www.state.nj.us/dep/dsr/bscit/IEETMain.htm
New Jersey Stormwater BMP Manual
http://www.state.nj.us/dep/stormwater/bmp_manual2.htm
Ohio Department of Transportation, Approved Devices
http://www.odotonline.org/materialsmanagement/qpl.asp?specref=ss-995
Ohio Department of Transportation, Office of Structural Engineering, Post Construction
Stormwater Management
http://www.dot.state.oh.us/se/hy/post%20construction.htm
U.S. Environmental Protection Agency Environmental Technology Verification Program
http://www.epa.gov/etv/verifications/verification-index.html
Washington State Department of Ecology Stormwater Treatment Technologies
http://www.ecy.wa.gov/programs/wq/stormwater/newtech/technologies.html
Jan. 2008, Rev Jan. 2009 (blue) i
THE METROPOLITAN ST. LOUIS SEWER DISTRICT’S
PROPRIETARY BMP APPLICATION
CONTENT OF APPLICATION
Cover Letter and Review Request
This section shall include:
1. A signed cover letter, limited to three (3) pages in length, introducing and properly
naming the manufacturer and the proprietary BMP. This letter should include the
following:
a. A description of the construction of the proprietary BMP and its method of operation
(i.e., filtering, settling, or hydrodynamic separation).
b. An outline of the types of sites where the BMP would be most applicable.
c. A listing of the states or localities where the BMP is currently approved for use.
d. A brief history of the manufacturer and a description of their involvement in the field
of storm water quality.
e. A request that MSD consider the use of the proprietary BMP as a stand-alone water
quality treatment device at a specific Use Level Designation and a statement
certifying that the device meets all of the applicable requirements for that Use Level
Designation.
2. The following information should be provided in the format given and included as a
separate page.
Technology Name_________________________________________________________
Indicate Use Level Designation GUL RUL HUL PUL
Vendor Name____________________________________________________________
Contact Name____________________________________________________________
Address (street, city, state, zip)_______________________________________________
Phone, Fax, e-mail address__________________________________________________
Jan. 2008, Rev Jan. 2009 (blue) ii
Product Catalog Data
This section shall include:
1. A detailed description of the operation of the device, including depiction of the flow path.
2. Complete engineering drawings or catalog sheets, to scale, of the BMP. Views should be
provided from at least two directions.
3. Specific details shall be provided of any special equipment or devices contained in the
BMP.
4. A listing of, and data pertaining to, plantings used in the device.
5. A listing of any industry construction standards used during the manufacturer of, or
applicable to the design of the device.
6. Any construction specifications or installation instructions recommended for use in site
construction plans or specifications.
Product Performance Claim and Certification
This section shall include:
1. Proprietary BMP applications must provide data that support the manufacturer’s claim of
TSS removal for each model. The application should also provide a summary table of
BMP models and the peak water quality volume or flowrate that each model can treat and
achieve the required TSS removal.
2. TSS removal efficiency shall be appropriately verified, and a complete copy of the
appropriate verification shall be attached. Also provided should be the name and contact
information of a representative of the verifying agency.
3. Regarding the field site studied, please complete the attached page, and provide an
outline of the field testing with supporting data.
Jan. 2008, Rev Jan. 2009 (blue) iii
Stormwater BMP Demonstration Summary
Technology Name_______________________________________________________
1. General Information
Vendor Name____________________________________________________
Address (street, city, state, zip)_______________________________________
2. Test Site Information
Site Name_______________________________________________________________
Address (street, city, state, zip)______________________________________________
Land Use:
Commercial/Office Residential Industrial Open Other (specify)_______
Total Contributing Drainage Area (Ac)________________________________________
3. Watershed Information
Watershed Name_________________________________________________________
Total Watershed Area (Ac)__________________________________________________
Percent of Impervious Area in Watershed______________________________________
4. Precipitation Information
Regional Climate Station___________________________________________________
Average Number of Storms per Year__________________________________________
Average Annual Rainfall (in)________________________________________________
5. BMP Information
Date System Installed______________________________________________________
Dates Tested/Sampled______________________________________________________
Storm precipitation (for each storm event during testing)__________________________
Total Storm Flow Volume Into BMP (For Each Event)____________________________
Total Storm Flow Volume Bypassed (For Each Event)____________________________
Type of Samples Collected (e.g., flow-weighted, composite)_______________________
Parameters and Units Measured______________________________________________
Analysis Method__________________________________________________________
Jan. 2008, Rev Jan. 2009 (blue) iv
Product Design Criteria
This section shall include:
1. Sample proprietary BMP sizing calculations, for a site typical to the St. Louis area.
These calculations would include how to size and select the device as well as how to size
and select any special components.
2. A sample site layout plan showing a typical layout for a site in the St. Louis area. This
layout should include any typical methods of pretreatment required.
Cost Information
This section shall include:
1. Sample cost data for a site typical to the St. Louis area. This shall include:
a. Device, material and shipping cost for the proprietary BMP.
b. Typical installation costs.
c. Typical annual maintenance costs.
Jan. 2008, Rev Jan. 2009 (blue) v
Product Sample Maintenance Plan
A sample maintenance plan must be provided for the proprietary BMPs and, at a minimum, must
include the following:
1. The person or persons responsible for the preventative and corrective maintenance of the
stormwater management measure. In the instance of a proprietary BMP, the
manufacturer, a manufacture’s representative, or the owner may perform maintenance.
2. Specific preventative and corrective maintenance tasks such as removal of sediment,
trash, and debris; mowing, pruning, and restoration of vegetation; restoration of eroded
areas; elimination of mosquito breeding habitats; control of aquatic vegetation; and repair
or replacement of damaged or deteriorated components.
3. A schedule of regular inspections and tasks.
4. Cost estimates of maintenance tasks, including sediment, trash, and debris removal.
5. Detailed logs of all preventative and corrective maintenance performed at the stormwater
management measure, including all maintenance-related work orders.
6. Maintenance equipment, tools, and supplies necessary to perform the various
preventative and corrective maintenance tasks specified in the plan. Sources of
specialized, proprietary, and nonstandard equipment, tools, and supplies should also be
provided. Limitations on the use of any reconditioned parts must be addressed.
7. Recommended corrective responses to various emergency conditions that may be
encountered at the stormwater management measure.
8. Maintenance, repair, and replacement instructions for specialized, proprietary, and
nonstandard measure components, including manufacturers’ product instructions and user
manuals.
9. Procedures and equipment required to protect the safety of inspection and maintenance
personnel.
10. Approved disposal and recycling sites and procedures for sediment, trash, debris, and
other material removed from the measure during maintenance operations or in a general