HomeMy Public PortalAboutFY2016 Consultant Services Presentation_0FY 2016 Proposed Capital
Improvement Program
Metropolitan St. Louis Sewer District
FY 2016 Capital Improvement Program
Proposed Engineering Services
Rich Unverferth P.E.
Director of Engineering
January 20, 2015
Today’s Agenda
Introductions
Proposed Program – Procurements Completed
Proposed Program – Procurements Needed
Consultant Selection Process
RFQ1/RFP1 Schedule & Project Details
RFP2 & RFP3 Schedule & Project Details
Proposed Future Program
Executive Director’s Update
Project Clear Update
Questions and Closing
Proposed FY 2016 Program
Engineering Projects – Procurements Completed
Project Consultant Budget
WATERSHED CONSULTANT - LOWER & MIDDLE RDP CSO
CONTROLS (11109)
Jacobs Engineering Group, Inc. $ 12.0 M
WATERSHED CONSULTANT - DEER CREEK SANITARY PROGRAM
(11110)
Parsons Water &
Infrastructure, Inc.
$ 6.2 M
WATERSHED CONSULTANT – BISSELL COLDWATER MISSOURI
MERAMEC PROGRAM (11144)
AMEC Environment &
Infrastructure Inc.
$ 10.7 M
WATERSHED CONSULTANT – LEMAY SANITARY PROGRAM
(11145)
Burns & McDonnell
Engineering Co., Inc.
$ 14.9 M
WATERSHED CONSULTANT - RDP TRIBUTARIES (DEER CREEK)
CONTROLS SYSTEM IMPROVEMENTS (11153)
HDR Engineering, Inc. $ 3.7 M
WATERSHED CONSULTANT – CONSTRUCTION MANAGEMENT –
TANKS/TREATMENTS/PUMP STATION FACILITIES (11151)
Kennedy Associates/
Architects, Inc.
$ 4.9 M
WATERSHED CONSULTANT – CONSTRUCTION MANAGEMENT –
RDP TUNNELS (11152)
Shannon & Wilson Inc. $ 1.4 M
WATERSHED CONSULTANT – CONSTRUCTION MANAGEMENT –
LOWER MERAMEC AND DEER CREEK TUNNELS (11826)
Black & Veatch Corporation $ 2.6 M
WATERSHED CONSULTANTS 8 $ 56.4 M
Proposed FY 2016 Program
Engineering Projects – Procurements Completed
Project Consultant Budget
LEMAY WWTP SECONDARY IMPROVEMENTS (11649) Jacobs Engineering Group $ 0.51 M
RIDGEMOOR DRIVE I/I REDUCTION & STORM
IMPROVEMENTS (10390)
Lochmueller Group, Inc. $ 0.10 M
Totals 2 $ 0.61 M
Proposed FY 2016 Program
General Services – Procurements Completed
Project Consultant Budget
PLANNING – 11755 Losli Engineering, LLC. $ 0.40 M
SEWER DESIGN - 11780
Vance Engineering, Inc. $ 0.09 M
SEWER DESIGN – 11781 Shalom Services Corporation $ 0.09 M
GEOTECHNICAL – 11753 Stantec Consulting Services, Inc. $ 0.05 M
GEOTECHNICAL – 11754 Shannon & Wilson, Inc. $ 0.05 M
GEOTECHNICAL – 12064 Terracon Consultants, Inc. $ 0.05 M
Totals 6 $ 0.73 M
Proposed FY 2016 Program
Other Projects – Procurements Completed
Project Vendor Budget
PRIVATE INFLOW/INFILTRATION PUBLIC
ENGAGEMENT PROGRAM
StandPoint Public Affairs $ 0.50 M
CRITICAL INFRASTRUCTURE ASSESSMENT RJN Group, Inc. $ 1.20 M
CCTV INSPECTION AND PHYSICAL
INSPECTION OF SEWERS (2014)
Ace Pipe Cleaning $ 2.00 M
CCTV INSPECTION OF SEWERS (2014) ADS Environmental Services $ 1.00 M
RADAR RAINFALL DATA (2014) Vieux and Associates
$ 0.13 M
STREAM FLOW WATER QUALITY
SAMPLING (2014)
Geosyntech Consultants Inc. $ 0.62 M
STREAMFLOW GAUGE OPERATION U.S. Geological Survey $ 0.56 M
Total 7 $ 6.01 M
Proposed FY 2016 Program
Engineering Projects – Procurements Needed
Project Name Budget
COLDWATER CREEK WWTF FINAL CLARIFIERS REPLACEMENT 1,500,000
COMPREHENSIVE AMMONIA AND NUTRIENT REMOVAL MASTER PLAN 1,500,000
DEGIVERVILLE COMBINED SEWER RELOCATION 650,000
LEMAY PUMP STATIONS 1 AND 2 IMPROVEMENTS 400,000
DEER CREEK OMCI STORMWATER DESIGN (CONTRACT A) 350,000
HUDSON RD. #1401 - #1405 BANK STABILIZATION (MCDW-120) 250,000
ROSEWOOD LANE & WOODARD DR. STORM SEWER 210,000
NATURAL BRIDGE RD - DARBY TO CHEVROLET COMBINED SEWER RELIEF 200,000
BIG BEND TO PAPIN STORM SEWER PHASE I 190,000
CAULKS CREEK FORCEMAIN REHABILITATION 150,000
COTTAGE #206 STORM IMPROVEMENTS 120,000
11 $ 5.52 M
Proposed FY 2016 Program
General Services – Procurements Needed
Project Name Budget
GENERAL SERVICES AGREEMENT - FACILITY & SEWER DESIGN (2016) 300,000
GENERAL SERVICES AGREEMENT - SURVEY SERVICES (2016) CONTRACT A 50,000
GENERAL SERVICES AGREEMENT - SURVEY SERVICES (2016) CONTRACT B 50,000
GENERAL SERVICES AGREEMENT - SURVEY SERVICES (2016) CONTRACT C 50,000
GENERAL SERVICES AGREEMENT - SURVEY SERVICES (2016) CONTRACT D 50,000
GENERAL SERVICES AGREEMENT - SURVEY SERVICES (2016) CONTRACT E 50,000
GENERAL SERVICES AGREEMENT - CONSTRUCTION MANAGEMENT (2016) 250,000
7 800,000
Consultant Selection Process
Pre-Qualification
RFQ/RFP Process
RFP Process
RFQ Short List Selection Criteria
RFP Selection Criteria
Selection Process Documents –
www.stlmsd.com/msd-work/consultant-selection
(under Links on bottom right)
Pre-Qualification
Packets were due on January 2, 2015
Questions – Sharon Holt at 314.768.6285
Same format as 2014
Note changes to Insurance Requirements
Previous year’s performance evaluation
will be included with the pre-qualification
letter
RFQ/RFP Process
Projects $500,000 or greater – RFQ/RFP
All consultants notified of RFQ and eligible
Short listing to 3 or more firms by RFQ
Committee after RFQ evaluation
Selection by separate RFP Committee after
RFP evaluation
Interviews may be required
RFP Process
Projects less than $500,000 – RFP
Project Pairings
Statement of Interest & Pre-Qualifications
to aid in short listing
Short listing to 3 or more firms by
RFQ Committee
Selection by separate RFP Committee after
RFP evaluation
RFQ Short List Criteria
Project Team and Key Members
Personnel Availability/Workload
Past Performance/Project Experience
Backlog
Diversity Multiplier
RFP Selection Criteria
Understanding of Project and Technical
Approach
Project Manager and Project Team
Personnel Availability
Project Design Schedule
Related Project Experience/Past
Performance
Backlog
Interview/Project Presentation (optional)
Diversity Multiplier
Workforce Diversity
Per current policy there are no sub-
contracting MWBE goals
Workforce Diversity goals on contracts
over $500,000
Qualifications and Proposals receive
additional credit through the use of
Diversity Multipliers for MWBE Primes
and meeting Workforce Diversity goals
Backlog Calculation
Backlog calculation for every firm will be
computed based on a combination of:
Watershed Consultant Contracts – Open
balance on contracts counted towards
prime and subs based on their
participation in the watershed consultant
contract.
Other Consultant Contracts – open
balance on contracts counted towards
prime only.
Backlog
Backlog for proposals on projects $500,000
and over will be computed by summing
backlog for all the firms of the team
proposing
Backlog for proposals on projects less than
$500,000 will be computed by summing
backlog for the prime only (not the team)
Proposed FY 2016 Program
RFQ/RFP Schedule
RFQ1/RFP1 – 3 projects totaling $3.6 M
RFQ Issued: February 24
RFQ Due: March 18
RFP Issued: April 29
RFP Due: May 21
Selection: June 19
Proposed FY 2016 Program
RFQ/RFP Grouping
RFQ1/RFP1 – Project Details
Comprehensive Ammonia and Nutrient
Removal Master Plan, budgeted at $1.5 M.
Coldwater Creek WWTF Final Clarifiers
Replacement Design, budgeted at $1.5 M.
Degiverville Combined Sewer Relocation
Design, for construction of 3,800 feet of
combined sewer, budgeted at $600,000.
Proposed FY 2016 Program
RFP Schedule
RFP2 – 8 project designs totaling $1.9 M
Statement of Interest Issued: February 24
Statement of Interest Due: March 18
RFP Issued: May 22
RFP Due: June 16
Selection: July 17
Proposed FY 2016 Program
RFP Grouping
RFP2 – Project Details
1 Pump Station Design for electrical/mechanical
improvements at Lemay Pump Station 1 & 2,
budgeted at $400,000.
1 Combined Sewer Design sewer replacement
project, budgeted at $200,000.
1 Forcemain Design rehabilitation project,
budgeted at $150,000.
5 Stormwater Design projects, totaling $1.1 M,
which includes 3 storm sewer and 2 storm
channel projects.
Proposed FY 2016 Program
RFP Schedule
RFP3 – 7 General Services totaling $800,000
Statement of Interest Issued: February 24
Statement of Interest Due: March 18
RFP Issued: June 19
RFP Due: July 14
Selection: August 14
Proposed FY 2016 Program
RFP Grouping
RFP3 – Project Details
1 General Services Agreement for Facility and
Sewer Design Services, budgeted at $300,000.
1 General Services Agreement for Construction
Management Services, budgeted at $250,000.
5 General Services Agreements for Surveying
Services, budgeted at $250,000 ($50,000 each).
Proposed Future Program
General Services Agreements for Various
Services
Pump Station Rehabilitation Projects
Cityshed Projects in CSO Area
Miscellaneous WWTF Rehabilitation Projects
Pre-design & Design for Lower Meramec
WWTF Phase II Expansion
Stormwater Projects (dependent on
implementation of Stormwater Rate
Proposal)
Executive Director’s Update
Board of Trustees & Senior Staff Update
Consent Decree Compliance – EPA
Diversity
Rate Proposal – Wastewater
Rate Proposal – Stormwater
The Metropolitan St Louis Sewer District
Project Clear Update
January 20, 2015
Project Clear Update
History of the MSD and CD
Project Clear Communications
Planning
–How we got here
–Ongoing Process
Design
–Watershed Consultant Program Concept
–Looking Forward
Construction
–Changing Program
St. Louis MSD Statistics
From 1992 to 2012, MSD spent approximately
$2.7 billion to remove over 300 overflows.
August 2011 Department of Justice filed a
settlement or consent decree
April 27, 2012 consent decree agreement
between MSD, the EPA and the Missouri
Coalition for the Environment went into effect.
Project Estimated at $4.7 Billion (Project Clear)
30 1992 2012 2034 2023
$2.7 billion $4.7 billion
Consent Decree
Agreement to improve water quality and
alleviate many wastewater concerns in the St.
Louis region.
Major Components
–CMOM
–SSO Master Plan
•Separate Areas
–LTCP
•Combined Areas
Schedule Driven
Project Clear Communications
So what is Project Clear?
32
Helping St. Louis Understand
Building One of the Largest Public
Projects in St. Louis History
Few Know or Understand the Issues
Mostly Out of Sight
Some Solutions Hard to Understand
Rates WILL Go Up
Solution – Project Clear
33
Building Long-Term Relationships
Clear Water
–Building our image as an environmental leader
34
35
=
12
9
Perspective
Tools
Stakeholder Engagement Committee
Municipal Outreach
Traditional Media Outreach
Digital tools:
–Website
–Community Newsletter
–Social Media
–Videos and YouTube promotion
36
Planning
37
Notice to Proceed: July 21, 2003
–10-½ years of working with consultant
–Initially started on CSO LTCP
–Started SSO CP Watershed Teams in early
2007
Deadlines Met:
–CSO LTCP (approved by MDNR June
2011)
–SSO Master Plan (approved by EPA June
2014)
38
Watershed Facility Planning Project
Master Schedule of SSO Projects &
CSO Control Measures
SSO Plan to remove 148 constructed SSOs, goal
of eliminating known overflows
409 Projects, over 23 years
172 Projects for SSO removal
230 Projects for Capacity (Building Backup)
Approximately $2.0 billion
CSO Plan to control combined sewer overflows
Largest project is the Lower-Middle River Des
Peres tunnel storage system
Approximately $2.0 billion
Current Planning Efforts
Managing Compliance Schedule
–Comparing to Implementation Schedule
–Comparing to Actuals
Reporting on Implementation Status
CIRP Budgeting Process & Rate
Commission
Ongoing Collaborative Planning
40
Design
41
Watershed Consultant Program Concept
Increase in Number and Scope of Projects
Limited Staff Increases
Somewhat Short-term Bump
Watershed Consultant Contracts
–Annual Contracts (Estimated 10 Years)
–Both Design and Construction Management
–More Complete Design Delivery
–Contracted in Phases
Watershed Consultant Teams
5 Robust Design Teams
–Work Closely with District Staff
–Estimated 10 Year Contracts
–Handle Project Communications
3 Construction Management Teams
–Integral part of design process
–Administer Construction of Large Facilities
and Tunnel Projects
43
Repair &
Maintain
Build System
Improvements
44
3 Focus Areas for Project Clear
Get the Rain
Out
Get the Rain Out
Stormwater Disconnects
–Mandatory Private I/I Removal
–Touches Big Numbers
Rainscaping
–Green Infrastructure, Specific Watershed
Citysheds – Combined Sewer Area
–Resident Relocations
–Combined Sewer Separations
45
Private I/I – Stormwater Disconnects
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25Property Inspections Fiscal Year Design
Private I/I Inspections
30% All
53% Sanitary
Repair and Maintain
System Maintenance
System Inspection
System Rehab. and Replacement
Fats, Oil and Grease Control Program
Emergency Response
Operations Heavily Involved
Results Already Happening
47
0
50
100
150
200
250
300
350
400
FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14
Dry Weather Overflows
Dry Weather Overflows
Build System Improvements (currently)
Tunnels
–7 Tunnels, 28 miles,
–from 4ft – 30ft diameter
Storage Facilities
–3 Above Ground Tanks
High-Rate Treatment
–1 HRT – End of Large CSO Tunnel
Relief Sewers
–As Necessary
48
49
Lower and Middle RDP
50
51
JB Tunnel
–Deep Rock Tunnel
–Storage and
Conveyance
–3.2 Miles
–7 FT Diameter
–New Lemay 3 PS
with 15 MGD
capacity
–Eliminates 3 pump
stations
–Construction FY17
–30% Design OPC
$110 Million
52
LMRDP Storage
Tunnel
–Deep Tunnel
–9 Miles
–30 Ft Diameter
–Storing 206 MG
Flow Captured
From 47 Outfalls
–≤ 4 Events/Typ.
Yr
–Construction FY18
–Pre-Design OPC
$701 Million
53
LMRDP Pump Station
–100 MGD capacity
–Pumps to Lemay WWTP or EHRC
–Construction FY 24
–Pre-Design OPC $80 Million
Lemay CSO EHRC
–Treats 100 MGD
–≤ 4 Events/Typ. Yr
–Construction FY 25
–Pre-Design OPC $69 Million
54
Maline Creek Storage
–Deep Rock Storage Cavern
–3,000 FT
–28 FT Diameter
–Providing 12.5 MG of CSO Storage during wet weather events
–≤ 4 Events/Typ. Yr and 84 MG of untreated overflow volume
–New PS with 12.5 MGD capacity
–Construction FY16
–Estimate $82 M
Lemay Watershed
55
56
Lemay Watershed
From FY13 to FY15:
o 34 Sewer/PIR Projects
o 15 Public I/I
o 2 Storage Tanks
o 5 Preliminary Studies
45 SSOs
Private I/I
o FY13: 900 sites
o FY14: 17,000 sites
o FY15: 10,400 sites
Public I/I
o 123 miles of CIPP
57
Lemay Storage
Hafner in U-City,
6MG, cavern
Pardee in Gravois,
9MG, above or below
ground
Gravois #2,
FY27 Design
Mackenzie,
FY26 Design
Deer Creek Watershed
58
59
Deer Creek
Watershed
–Currently 23
projects
•12 Sewer/PIR
projects
•9 Public I/I
Reduction
•DC-02/DC-03
Trunk Sewer
•Deer Creek Tunnel
–42 SSOs
60
Deer Creek
Tunnel
–21,000 feet long
–19 foot diameter
–150 feet below
ground
–6 dropshafts
–Storage and
conveyance
–21 MGD PS
–20-26 events/yr
Bissell-Coldwater-Missouri-Meramec
Watersheds
61
62
BCMM
Watersheds
58 SSOs
Private I/I Reduction
17 projects in FY13
13 projects in FY14
9 projects in FY15
Public I/I Reduction
16 projects in FY13
16 projects in FY14
11 projects in FY15
Sewer Design
18 projects in FY13
12 projects in FY14
6 projects in FY15
63
Coldwater Sanitary
Relief Section B, C & D
Wet Weather Storage
Facility Tank C
–Intersection of I270 &
Lindberg
–Vacant Industrial parcel
–Construction start – May
2015
–Construction duration –
450 days
–8 SSOs removed
64
Tank
Diameter inside
180 ft
Height to Top of
Wall 46 ft
Height to Top of
Dome Roof 66 ft
Volume 8.0 MG
Hazelwood logo
RDP Tributaries
65
66
RDP Tribs Tunnel
- Deep Tunnel
- Storage/Conveyance
- 2.3 Miles
- 20 Ft Diameter
- Reduces 28 CSO to 1 CSO
- ≤ 4 Events/Yr
- Planning FY15
- Pre-Design/Design
FY17
- Construction FY24
67
Upper RDP Tunnel
- Deep Tunnel
- Storage
- 1.7 Miles
- 24 Ft Diameter
- Consolidated 39
CSO to 5 Drops
- ≤ 4 Events/Yr
- Planning FY17
- Pre-Design/Design
FY19
- Construction FY28
68
Lower Meramec Tunnel
- Deep Tunnel
- Conveyance
- 6.8 Miles
- 8 Ft Diameter
- Eliminate Fenton
WWTF
- Pre-Design/Design
FY15
- Construction FY21
Construction
Construction Management By Project Type
70
Role of CM Consultant
Design Review
–Bidability
–Constructability
–Review of Project Costs
Construction Inspection and Contract
Management
Provide Program Management Support
71
CM Project Assignments
72
Construction Bid Projections
0
20
40
60
80
100
120
2013 2014 2015 2016 2017 2018 2019 2020
67 65
88
111
89
59
66 64
Fiscal Year
Construction Bids
Tunnels
74
Questions and Closing
Questions and Answers
www.stlmsd.com
Thanks to the Engineers’ Club of St. Louis
Enjoy the Networking